Middletown Prof. Pk. v. Associated Cons., No. Cv94 0705070 S (Aug. 24, 1994)

1994 Conn. Super. Ct. 8591
CourtConnecticut Superior Court
DecidedAugust 24, 1994
DocketNo. CV94 0705070 S
StatusUnpublished

This text of 1994 Conn. Super. Ct. 8591 (Middletown Prof. Pk. v. Associated Cons., No. Cv94 0705070 S (Aug. 24, 1994)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Middletown Prof. Pk. v. Associated Cons., No. Cv94 0705070 S (Aug. 24, 1994), 1994 Conn. Super. Ct. 8591 (Colo. Ct. App. 1994).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION RE APPLICATIONS TO CONFIRM AND TO VACATEARBITRATION AWARD Facts

On March 7, 1988 the parties entered into a written contract in regard to a project for the development of Middletown Professional Park (Project).

Under that contract plaintiff was the construction manager.

Arbitration is provided for in Article 9 of that contract which reads in pertinent as follows:

ARTICLE 9

ARBITRATION

9.1 All claims, disputes and other matters in question between the parties to this Agreement arising out of or relating to this Agreement or the breach thereof, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. No arbitration arising out of or relating to this Agreement shall include, by consolidation, joinder or in any other manner, any additional person not a party to this Agreement except by written consent containing a specific reference to this Agreement and signed by the Construction Manager, the Owner, and any other person sought to be joined. Any consent to arbitration involving an additional person or persons shall not constitute consent to arbitration of any dispute not CT Page 8592 described therein or with any person not named or described therein. This agreement to arbitrate and any agreement to arbitrate with an additional person or persons duly consented to by the parties to this Agreement shall be specifically enforceable under the prevailing arbitration law.

. . .

9.3 The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.

A dispute arose under the contract and on August 25, 1993 the parties submitted it for arbitration. Neither the parties nor the arbitrator have set out what they consider to be a definitive submission. The issue "submitted" seems to have been a claim by defendant that plaintiff failed "to pay a balance of $160,076.00 due on construction contract" plus interest at 18%. Hearings were held in December of 1993 and later the parties submitted briefs.

On March 7, 1994 the arbitrator issued his decision and award. That award reads as follows:

"AWARD

The Arbitrator, after hearing and consideration of the entire record presented to him by the parties, awards Associated Construction Company the sum of $98,758.31, plus interest thereon to be computed at the rate of ten percent a year from February 14, 1990, to the date of payment.

The Arbitrator states that he heard the above matter at East Hartford on two days, namely December 15, 1993 and December 29, 1993, and that he spent additionally in the aggregate two days in reviewing transcript, exhibits and documentary evidence and the written memoranda of the parties, and in preparing the foregoing decision and award.

The Arbitrator further represents that he incurred travel expenses of $66.00, telephone expense of $11.87 and copying expenses of $8.40, summarized as follows: CT Page 8593

Services (four days) $1,500.00 Disbursements 86.27 -------- Total due $1,586.27

The Arbitrator further directs that his compensation and disbursements shall be borne equally by the parties Therefore, Claimant, having previously paid $500.00 on account thereof, shall pay the additional sum of $293.13 to the American Arbitration Association and the Respondent shall pay the sum of $793.13 to the American Arbitration Association for compensation and disbursements still due the Arbitrator.

The Arbitrator further directs that the administrative fees and expenses of the American Arbitration Association totaling $1,705.82 shall be borne equally by the parties. Therefore, Respondent shall pay to the American Arbitration Association the sum of $405.82, being that portion of Respondent's share of administrative fees and expenses previously advanced by Claimant to the American Arbitration Association.

The arbitrator makes the foregoing Award in full and final settlement of any and all claims submitted to him in this arbitration."

Claims

The plaintiff claims the award should be vacated because "the arbitrator has been guilty of misconduct in refusing to postpone the hearing upon sufficient cause shown and has exceeded his powers and so imperfectly executed his powers that a mutual, final and definite award upon the subject matter submitted was not made." Plaintiff then goes on to say:

"a. for the reason that the arbitrator rejected and disregarded the law of Connecticut which is, according to contract, the law applicable to disputes between these parties;

b. for that [sic] reason that the arbitrator rejected and disregarded the law of Connecticut CT Page 8594 which is, according to contract, the law applicable to disputes between these parties;

c. improperly and without just cause failed to consider all of the evidence presented to him, and,

d. failed to recognize that the dispute between these parties has been resolved by settlement in disregard of the law of the State of Connecticut and written agreement between the parties."

Law

The first obligation of this court is to determine if the award conforms to the submission. American UniversalIns. Co. v. DelGreco, 205 Conn. 178, 186. On its face it does.

I Postponement

Plaintiff's brief never mentions any problem arising from any failure of the arbitrator to grant a postponement nor does it point to any facts to support a claim in regard to such possible failure. The court considers this claim abandoned.

II Interest

The defendant claimed interest in the arbitration. The contract provides the following in regard to interest:

"15.5 Payments due the Construction Manager and unpaid under this Agreement shall bear interest from the date payment is due at the rate entered below, or in the absence thereof at the legal rate prevailing at the principal place of business of the Construction Manager (here insert any rate of interest agreed upon.) One and one-half (1 1/2%) percent."1

It could easily be argued that the annual interest rate called for is 1 1/2%. However, a kindly interpretation of the provisions for annual interest could easily be 1 1/2% per month. Of course, the expressions CT Page 8595 "monthly", "annually", "yearly" or "for 12 months" are not used in the provision.

There is a portion of the provision which states "in the absence thereof, at the legal rate prevailing at the principal place of business of the construction manager." The contract between the parties and the service of this suit allows this court to conclude that the principal place of business of defendant is Connecticut.

In Connecticut "the legal rate prevailing" is an annual rate. Conn. Gen. Stats. §§ 37-1, 2, 3a, 3b, 4, 6, 9(70)(A). As a result the arbitrator could find that both the 1 1/2% interest called for and the "legal rate prevailing" were both referring to an annual rate. Thus the arbitrator might possibly have awarded interest at an annual rate of 1 1/2%. He did not do that but found "that there is an absence of a determinable rate of interest, and therefore . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meyers v. Lakeridge Development Co.
376 A.2d 1105 (Supreme Court of Connecticut, 1977)
City of Waterbury v. Waterbury Police Union
407 A.2d 1013 (Supreme Court of Connecticut, 1979)
Caldor, Inc. v. Thornton
464 A.2d 785 (Supreme Court of Connecticut, 1983)
American Universal Insurance v. DelGreco
530 A.2d 171 (Supreme Court of Connecticut, 1987)
Garrity v. McCaskey
612 A.2d 742 (Supreme Court of Connecticut, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
1994 Conn. Super. Ct. 8591, Counsel Stack Legal Research, https://law.counselstack.com/opinion/middletown-prof-pk-v-associated-cons-no-cv94-0705070-s-aug-24-connsuperct-1994.