Middlesex Water Co. v. Knappmann Whiting Co.

45 A. 692, 64 N.J.L. 240, 1900 N.J. LEXIS 100
CourtSupreme Court of New Jersey
DecidedMarch 5, 1900
StatusPublished
Cited by23 cases

This text of 45 A. 692 (Middlesex Water Co. v. Knappmann Whiting Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Middlesex Water Co. v. Knappmann Whiting Co., 45 A. 692, 64 N.J.L. 240, 1900 N.J. LEXIS 100 (N.J. 1900).

Opinion

The opinion of the court was delivered by

Depue, J.

The application in .writing of the manufacturing company for water was accepted by the water company, and became a contract of the parties respectively. The water company in its declaration sets out the contract as expressing the terms of its agreement, as well as the agreement on the part of the defendant. The bill of particulars shows that the water company’s claim against the defendant was founded on this agreement. The water company in this suit sued for and recovered payments for water under the contract which became due July 1st, 1898 ($150), and October 1st, 1898 ($150), as the fire in question took place in May, 1898. The litigation, therefore, must be decided upon the terms and- legal effect of this paper as the agreement inter-partes.

The facts briefly are these: The water company, having accepted the proposition of the defendant, connected defendant’s works with its mains, in accordance with the contract, in November, 1897, purchased and set up a meter and begau to supply the defendant with water. The plant of the water company, with its pumping-station, is located at South Plain-field, and its principal main extends, in an easterly direction, from South Plainfield, through the villages of Metuchen, Woodbridge and Seawaren, to the village of Carteret, on Staten Island, a distance of about fifteen miles. Between Woodbridge and Carteret the main crosses a stream in which [244]*244the tide ebbs and flows. The main at that point was laid at the bottom of the stream and was often submerged several feet below the tide. On the night of the 18th of May, 1898, a connection of the blow-off in the principal main of the water company gave way at a point where it crosses the stream, whereby water was discharged and the usual pressure was removed. The water company was notified of the absence of pressure, about eleven o’clock in the evening of the 18th, and immediately the superintendent and others set out to find the cause. It was a difficult leak to find, owing to the fact that the opening was under the waters of the creek. The men found it about four o’clock in the morning of the 19th. By that' time the tide was so high that it was impossible to repair it, and it was necessary to wait until low tide, which occurred about noon of the 19th, and the superintendent began to open the gate, just west of the creek, at two o’clock, taking about twenty'minutes to do so. O11 the day following the break in the pipe the defendant’s factory caught fire, and, with its contents, was burned and destroyed, with a loss to the defendant of $16,889, after deducting insurance and salvage. No notice of the break in the pipe was given to the defendant. There is some conflict in the evidence as to whether the pressure was on the main at the defendant’s works at the time the fire broke out. In view of the judge’s instruction, it must be assumed that the pressure was not on, or that question must have gone to the jury. It must also, for the present purposes, be assumed that the burning of the building was the result proximately of the failure of plaintiff to furnish water with a pressure sufficient for fire purposes. If any question of the causal connection between the failure to supply water and the fire was involved, that, also would have been a question for the jury.

As already observed, this contract was an agreement inter partes. Cases such as Nickerson v. Bridgeport Hydraulic Co., 46 Conn. 24; Beck v. Kittanning Water Co., 11 Atl. Rep. 300, and Boston Safe Co. v. Salem Water Co., 94 Fed. Rep. 238, which hold that where the contract of the water [245]*245company is with the city no privity of contract exists between the water company and an inhabitant of the city whose property was destroyed by fire, to lay the foundation of an action against the company, do not apply to this case.

The water company, by this agreement, in express terms contracted with the defendant to furnish to it water suitable for drinking purposes and other domestic uses and for use in steam boilers, and with a pressure sufficient for fire purposes, the manufacturing company stipulating in the same connection that it would take water for a supply of its factory and for fire purposes for the period of five years and pay for it the stipulated price. The construction of the agreement is free from doubt. The premises to which the- contract related were a factory with its contents. The enumeration in the contract of the purposes for which the water was contracted for comprehends the supply of water appropriate to and adequate for all the enumerated purposes.

The construction of this agreement by the learned judge at the trial presents the merits of this controversy. His instruction was as follows: “Under this agreement there is no express contract by the water company that it will furnish water uninterruptedly for five years to the defendant. There is no agreement that an unavoidable accident will not happen causing temporary stoppage of the water-supply, but the agreement on the part of the defendant to take water and pay for it imposed on the water company the duty of exercising reasonable care in the construction and maintenance of the water works in such a way as to give a proper supply of water to the defendant during the term of five years. If, therefore, the water company was guilty of any negligence in these respects it is liable for such damages as proximately resulted from such negligence.” On this construction of the agreement the judge directed a verdict for the plaintiff. To this ruling the defendant excepted.

The agreement contained an express contract to furnish water for fire purposes without condition or qualification. The learned judge, by his construction, introduced into the [246]*246agreement a qualification that would exempt the water company from -performing its agreement in cases where, without negligence on its -part, the supply of water was cut off. To sustain this construction, counsel rely mainly on Mill Dam Foundry Co. v. Hovey, 21 Pick. 417. In that case the Mill Dam Foundry Company were proprietors of a foundry. They entered into an agreement with Hovey to manufacture iron, steel, &c., on hand. The foundry company, although they were lessees of the works under the Boston Water Power Company, were, as between the parties to the suit, under an obligation for the continuance of the water' power. They made a contract with Hovey for the manufacture for them of certain iron, steel, &c., on hand into plate-iron for the market, the foundry company binding themselves to furnish all the iron, steel and other materials used in and about said manufacture. One of the mill-dams was broken by a high tide. At that time the defendant had on hand a large quantity of materials in different states of manufacture. The dam was repaired with due diligence and the waters restored. In a suit by the foundry company against the defendant for the non-performance of his agreement to manufacture, the defendant treated the covenant to repair as a condition which authorized him to repudiate the entire contract. The defence was disallowed. The case turned on the distinction between a condition and a covenant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E & M Liquors, Inc. v. Public Service Electric & Gas Co.
909 A.2d 1141 (New Jersey Superior Court App Division, 2006)
Connecticut Post Ltd. Parts. v. Allen, No. Cvnh 9610-7875 (Jan. 12, 1998)
1998 Conn. Super. Ct. 625 (Connecticut Superior Court, 1998)
Bongo v. New Jersey Bell Telephone Co.
595 A.2d 557 (New Jersey Superior Court App Division, 1991)
Weinberg v. Dinger
524 A.2d 366 (Supreme Court of New Jersey, 1987)
Newark v. North Jersey Dist. Water Sup. Comm.
254 A.2d 313 (New Jersey Superior Court App Division, 1968)
Model Vending, Inc. v. Stanisci
180 A.2d 393 (New Jersey Superior Court App Division, 1962)
Edwards v. Leopoldi
89 A.2d 264 (New Jersey Superior Court App Division, 1952)
Reimann v. Monmouth Consolidated Water Co.
87 A.2d 325 (Supreme Court of New Jersey, 1952)
Atlas Finishing Co. v. Hackensack Water Co.
163 A. 20 (Supreme Court of New Jersey, 1932)
Retail Merchant's Business Expansion Co. v. Randall
153 A. 357 (Supreme Court of Vermont, 1931)
Perea v. Ilfeld
1928 NMSC 044 (New Mexico Supreme Court, 1928)
Tapper v. Idaho Irrigation Co.
210 P. 591 (Idaho Supreme Court, 1922)
Mascall v. Reitmeier
176 N.W. 486 (Supreme Court of Minnesota, 1920)
Transparent Rubber Works v. International Glass Co.
105 A. 299 (Supreme Court of New Jersey, 1918)
Jones House Furnishing Co. v. Arkansaw Water Co.
166 S.W. 557 (Supreme Court of Arkansas, 1914)
Morris Coal Co. v. Thompson
24 Ohio C.C. Dec. 627 (Ohio Court of Appeals, 1913)
Northern Irr. Co. v. Dodd
162 S.W. 946 (Court of Appeals of Texas, 1913)
Niehaus Bros. Co. v. Contra Costa Water Co.
113 P. 375 (California Supreme Court, 1911)
Inhabitants of Milford v. Bangor Railway & Electric Co.
71 A. 759 (Supreme Judicial Court of Maine, 1908)
Hunt Bros. Co. v. San Lorenzo Etc. Co.
87 P. 1093 (California Supreme Court, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
45 A. 692, 64 N.J.L. 240, 1900 N.J. LEXIS 100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/middlesex-water-co-v-knappmann-whiting-co-nj-1900.