MidAmerica C2L Incorporated v. Siemens Energy Incorporated

Court of Appeals for the Eleventh Circuit·Decided July 1, 2025·No. 24-10678·Unpublished

Opinion

[DO NOT PUBLISH]

In the

United States Court of Appeals For the Eleventh Circuit

No. 24-10678

Non-Argument Calendar

MIDAMERICA C2L INCORPORATED, a Nevada corporation, Plaintiff

Counter Defendant

Appellant,

SECURE ENERGY INC., a Nevada corporation, Plaintiff-Appellant,

versus SIEMENS ENERGY INCORPORATED, a Delaware corporation,

USCA11 Case: 24-10678 Document: 38-1 Date Filed: 07/01/2025 Page: 2 of 24

2 Opinion of the Court 24-10678

Defendant

Counter Claimant

Appellee.

Appeal from the United States District Court for the Middle District of Florida D.C. Docket No. 6:17-cv-00171-PGB-LHP

Before LAGOA, BRASHER, and ABUDU, Circuit Judges. PER CURIAM:

This case returns on appeal for a third time. For nearly a decade, Secure Energy, Inc. (“Secure”) contracted with Siemens Energy, Inc. (“Siemens”) to procure gasification equipment and technical support for its coal plant in Illinois. Marred by falling natural gas prices and malfunctioning equipment, Secure’s plant never became operational. In 2016, Secure—along with its subsidiary, MidAmerica C2L Inc.1—sued Siemens, bringing various fraud- and contract-based claims arising from the failed business venture. Following discovery, the district court granted Siemens summary judgment on each of Secure’s claims, including four claims

1 For purposes of this opinion, we refer to MidAmerica C2L Inc. as “Secure”

unless otherwise expressly noted.

USCA11 Case: 24-10678 Document: 38-1 Date Filed: 07/01/2025 Page: 3 of 24

24-10678 Opinion of the Court 3

premised on the theory that the equipment Secure purchased from Siemens was defective.

When this case was last on appeal, we reversed the district court’s entry of summary judgment for Siemens on those four counts, finding the court’s sole basis for doing so—that Secure was required to, but did not, introduce expert testimony showing a design defect—to be erroneous. MidAmerica C2L Inc. v. Siemens Energy, Inc. (MidAmerica II), 2023 WL 2733512, at *10 (11th Cir. Mar. 31, 2023). Accordingly, we remanded for the district court to consider Siemens’s alternative arguments for summary judgment in the first instance.

On remand, the district court once again entered summary judgment for Siemens. This appeal follows.

I. BACKGROUND A. Factual Background Secure was formed in 2006 2 to develop and construct a facility in Decatur, Illinois, to convert coal into synthetic natural gas using a process called coal gasification.3 To that end, Secure began

2 Secure’s subsidiary, Secure Energy Decatur, LLC, was formed shortly after this time and was the original entity contracting with Siemens. 3 Gasification converts carbonaceous, fossil-fuel based material (e.g., coal) into

gas (e.g., synthetic natural gas) by feeding pulverized coal (called feedstock) into large pieces of equipment called gasifiers. See Ronald W. Breault, Gasifi- cation Processes Old and New: A Basic Review of the Major Technologies, 3 Energies 216, 218 (2010).

4 Opinion of the Court 24-10678

shopping around for a Basic Engineering Design Package (“BEDP”) and Product Design Package (“PDP”) from a coal gasifi- cation technology provider, eventually contacting Siemens. Lars Scott and Jack Kenny, the two founders of Secure, met with Rolf Rüsseler and Harry Morehead of Siemens. During these meetings, Siemens represented to Secure that Secure was purchasing a proven technology from Siemens, as it started the equipment’s design in the mid-1970s and it had over twenty years of experience in coal gasification. Siemens also represented that its current 500-megawatt gasifiers—which Secure was interested in—employed a technologically advanced cooling-screen system that accepted a wide range of feedstock and could achieve “up to >99%” carbon conversion rates. And Siemens had sold the 500-megawatt gasifiers to one customer in China.

Impressed with these representations, Secure used Siemens for its equipment and technology needs. On July 24, 2007, Secure and Siemens entered into a “Memorandum of Understanding” memorializing the parties’ intention for Secure to buy from Siemens two 500-megawatt gasifiers, associated equipment, engineering services, and a process license.

On December 21, 2007, Secure and Siemens entered into a formal contract (the “2007 Contract”) in which Secure would purchase Siemens’s products and services for €27,715,000 plus $1,717,000—in total, about $40 million. The 2007 Contract, and every subsequent contract at issue, included a merger clause, which stated that neither “party will be bound by any prior obligations,

24-10678 Opinion of the Court 5

conditions, warranties or representations.” Secure promptly paid to Siemens the $40 million called for in the 2007 Contract.

Secure and Siemens also entered into a licensing agreement (the “2007 LSA”) in which Secure licensed Siemens’s technology for about €11.7 million. Secure was to pay the €11.7 million licensing fee pursuant to an agreed upon fee schedule within the 2007 LSA.

The burners—a core component of Siemens’s gasifiers—

were delivered to Secure in Decatur, Illinois, in March 2009. Secure alleges that the pins in the cooling screen of the burners were too short and out of specification, although Siemens disputes this characterization . But Secure only learned of this alleged defect during the litigation—it never opened or put into operation the Siemens gasifiers after it took possession of them.

The price of natural gas plummeted in 2009; as a result, Secure abandoned its original plan of converting coal to natural gas and began planning to build a coal-to-gasoline gasification plant instead . But because the plot of land Secure had acquired in Decatur could not accommodate this change, Secure decided to move its plant to West Paducah, Kentucky.

Secure’s new plans in Kentucky required no changes to the Siemens gasification equipment, so the parties continued their business relationship. On March 31, 2010, Secure and Siemens entered into a Completion Agreement (the “2010 Completion Agreement ”), which terminated the parties’ previous agreements in the 2007 Contract and 2007 LSA, as well as a new License Agreement (the “2010 LSA”). The 2010 Completion Agreement also stipulated

6 Opinion of the Court 24-10678

that Siemens had met its performance goals under the 2007 Contract and 2007 LSA and released both parties from any claim related to those contracts. In addition, the 2010 LSA included a warranty extension on the gasifiers (which would have otherwise expired in 2011) upon Secure’s payment of a €1 million fee, but Secure never paid the fee. The 2010 LSA also set forth terms for paying the licensing fee under the agreement, requiring: (1) Secure to pay Siemens €300,000 at the “Contract Date”; (2) €700,000 within five business days of the date of “Closing of New Equity” or July 31, 2010, whichever was later; (3) €10.2 million upon “Financial Close,” but no later than August 30, 2011 (unless otherwise agreed to by the parties); and (4) €1.2 million when “Acceptance” occurred, but no later than December 31, 2014.

At around the same time Siemens was working with Secure, Siemens sold five 500-megawatt burners to a client which installed the burners at its coal-to-polypropylene plant in China (“NCPP”). These burners were first used in October 2010. Immediately, there were problems. The burners that Siemens had used were having trouble converting the Chinese coal into synthetic gas. The pilot burner was also “unreliable” and had to be removed twenty-five times on two of the gasifiers at NCPP in the first two months. The cooling screens also had issues, with the flame from the burner hitting them at an awkward angle.

Siemens explains away these problems by explaining that the Chinese client used below-grade coal in the gasifiers at NCPP and loaded the incorrect fuel source into the burners. And Siemens

24-10678 Opinion of the Court 7

Free access — add to your briefcase to read the full text and ask questions with AI

MidAmerica C2L Incorporated v. Siemens Energy Incorporated, (11th Cir. 2025).

MidAmerica C2L Incorporated v. Siemens Energy Incorporated (MidAmerica C2L Incorporated v. Siemens Energy Incorporated) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Access Now, Inc. v. Southwest Airlines Co.
385 F.3d 1324 (Eleventh Circuit, 2004)
McCullough Ex Rel. McCullough v. Antolini
559 F.3d 1201 (Eleventh Circuit, 2009)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Marian Fontenot, Etc. v. The Upjohn Company
780 F.2d 1190 (Fifth Circuit, 1986)
Amber Nicole Wright v. Farouk Systems, Inc.
701 F.3d 907 (Eleventh Circuit, 2012)
PK Ventures, Inc. v. Raymond James & Associates, Inc.
690 So. 2d 1296 (Supreme Court of Florida, 1997)
Moransais v. Heathman
744 So. 2d 973 (Supreme Court of Florida, 1999)
J Square Enterprises v. Regner
734 So. 2d 565 (District Court of Appeal of Florida, 1999)
Hotels of Key Largo, Inc. v. RHI HOTELS
694 So. 2d 74 (District Court of Appeal of Florida, 1997)
HTP, Ltd. v. Lineas Aereas Costarricenses
685 So. 2d 1238 (Supreme Court of Florida, 1996)
Allen v. Stephan Co.
784 So. 2d 456 (District Court of Appeal of Florida, 2000)
Greenfield v. Manor Care, Inc.
705 So. 2d 926 (District Court of Appeal of Florida, 1997)
Broderick Haulage, Inc. v. MacK-international Motor Truck Corp.
1 A.D.2d 649 (Appellate Division of the Supreme Court of New York, 1956)
State v. Avco Financial Service of New York Inc.
406 N.E.2d 1075 (New York Court of Appeals, 1980)