Mid-Tex Electric Cooperative v. Federal Energy Regulatory Commission

864 F.2d 156, 274 U.S. App. D.C. 353, 1988 U.S. App. LEXIS 16600
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 9, 1988
Docket87-1675
StatusPublished

This text of 864 F.2d 156 (Mid-Tex Electric Cooperative v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mid-Tex Electric Cooperative v. Federal Energy Regulatory Commission, 864 F.2d 156, 274 U.S. App. D.C. 353, 1988 U.S. App. LEXIS 16600 (D.C. Cir. 1988).

Opinion

Opinion for the Court filed by Circuit Judge STEPHEN F. WILLIAMS.

STEPHEN F. WILLIAMS, Circuit Judge:

This is the third of a series of cases before this court dealing with the Federal Energy Regulatory Commission’s proposals to adjust the timing of federally regulated electric utilities’ recovery of the cost of capital employed in construction. Before the adoption of the contested rules, a utility normally could recover these costs only after a newly constructed facility became operational. It would accrue the carrying charges on the capital used to finance new construction in a separate account, “Allowance for Funds Used During Construction” (“AFUDC”), which appeared as a non-cash asset on the utility’s balance sheet. When the plant went into service, the entire value of the investment, including these accrued financing charges, would be added to the rate base. Only at this point would the utility begin to recover its financing costs from ratepayers.

FERC’s current proposal would allow a utility to include up to 50 percent of the costs of “construction work in progress,” or “CWIP,” in its rate base as it incurred them and thus to start earning a return that typically would offset 50 percent of the associated costs of debt and equity capital. The utility in principle recovers all its costs under either the AFUDC or CWIP method, but CWIP allows a substantial part to be recovered sooner.

A group of wholesale customers of suppliers of electric power have attacked this rule on a variety of grounds, focusing primarily on alleged anticompetitive effects. Although we find that the Commission has not been arbitrary or capricious in its assessment of the potential anticompetitive problems and adoption of solutions, we grant the petition for review because FERC has not supported one aspect of the rule with reasoned decisionmaking. We remand the case to the agency for further consideration of the burden of proof required of a party seeking preliminary relief from an anticompetitive “price squeeze.”

FERC’s predecessor, the Federal Power Commission, opened the door to CWIP in 1976 with an order allowing its use under *158 three exceptional circumstances: to construct pollution control facilities, to convert oil and gas plants to coal, and to remedy-severe financial hardship. Order No. 555, 56 FPC 2939, 2943-46 (1976).

Seven years later FERC expanded the availability of CWIP by adopting “a fixed percentage approach that allow[ed] any utility to file to include up to 50 percent of all CWIP in rate base in addition to any CWIP related to fuel conversion or pollution control facilities.” Order No. 298, 48 Fed.Reg. 24,323, 24,348 (1983).

The Commission stated three general purposes behind the decision to allow CWIP generally. First, it sought to mitigate a bias against capital investment in needed facilities. It saw this bias as arising from a utility’s cost of capital exceeding its allowed rate of return 1 and from cash flow problems. Second, it hoped to improve assessment of the need for facilities by having utilities send price signals more closely reflecting their future costs. Third, the Commission expected to enhance rate stability by mitigating the abrupt price increases that tend to occur under AFUDC. Id. at 24,326, 24,329-31.

The present lead petitioner and others challenged Order No. 298 in Mid-Tex Electric Cooperative, Inc. v. FERC, 773 F.2d 327 (D.C.Cir.1985) (“Mid-Tex I”). They attacked both the basic reasoning of the Commission and its failure, as they viewed it, to address properly certain anticompeti-tive effects going under the piquant labels “double whammy” and “price squeeze.” While this court found that FERC’s stated purposes were valid and that the agency had “reasonably concluded that the rule would indeed serve those purposes,” id. at 362, it nonetheless vacated certain portions of the rule and remanded the case to the Commission for further consideration of the rule’s potential anticompetitive effects. Id.

Following the remand, FERC adopted an interim rule, Order No. 448, that temporarily restored many of the features of the previous rule. Order No. 448, 51 Fed.Reg. 7774 (1986), reh’g denied, 51 Fed.Reg. 22,-065 (1986). This court upheld the interim rule in Mid-Tex Electric Cooperative, Inc. v. FERC, 822 F.2d 1123 (D.C.Cir.1987) (“Mid-Tex II”).

On June 18, 1987, after considering the comments filed in response to the promulgation of the interim order, FERC issued its final rule on CWIP. Order No. 474, 52 Fed.Reg. 23,948 (1987), clarified by Order No. 474-A, 52 Fed.Reg. 35,695 (1987). Several wholesale customers of suppliers of electric power, including Mid-Tex Electric Cooperative, Inc. and Golden Spread Electric Cooperative, Inc., electric power generation and transmission cooperatives, and the National Rural Electric Cooperative Association, a national service organization representing 1000 rural electric cooperatives, filed this suit challenging the orders. (We will refer to all the petitioners collectively as “Mid-Tex.”) The petitioners allege generally that the orders do not remedy the anticompetitive aspects of CWIP or comply with the directives of Mid-Tex I.

Soopb of Review

The Federal Power Act expressly provides that, in the event of judicial review of any order issued by FERC, “[t]he finding of the Commission as to the facts, if supported by substantial evidence, shall be conclusive.” 16 U.S.C. § 825l(b) (1985). This court observed in Mid-Tex I, however, that “it is ordinarily true that the ‘ “substantial evidence” requirement applicable to our review ... demands a quantum of factual support no different from that demanded ... by the arbitrary or capricious standard.’ ” 773 F.2d at 338 (quoting Association of Data Processing Serv. Orgs. v. Board of Governors, 745 F.2d 677, 686 (D.C.Cir.1984), and generalizing the finding that that decision had reached with respect to another substantial evidence provision).

*159 In applying this standard, we require that the agency’s decision be the product of reasoned decisionmaking that can be ascertained from the record. SEC v. Chenery Corp., 332 U.S. 194, 196-97, 67 S.Ct. 1575, 1577-78, 91 L.Ed. 1995, reh’g denied, 332 U.S. 783, 68 S.Ct. 26, 92 L.Ed. 367 (1947). “As a result, it becomes crucial that the Commission’s order include a reasoned opinion detailing those factual elements in the record that underlie the Commission’s actions.” Public Systems v. FERC, 606 F.2d 973, 979 (D.C.Cir.1979) (reviewing an agency decision under the identical review provision of the Natural Gas Act); see also Central Power & Light Co. v. FERC, 575 F.2d 937, 939 (D.C.Cir.) (FERC has an “obligation to articulate its reasoning” for agency actions), cert. denied, Dallas Power & Light Co. v. Central Power & Light Co.,

Related

Securities & Exchange Commission v. Chenery Corp.
332 U.S. 194 (Supreme Court, 1947)
Mains v. United States
439 U.S. 981 (Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
864 F.2d 156, 274 U.S. App. D.C. 353, 1988 U.S. App. LEXIS 16600, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mid-tex-electric-cooperative-v-federal-energy-regulatory-commission-cadc-1988.