Mid-South Contractors, Inc. v. Ratcliff

325 So. 2d 375, 1975 La. App. LEXIS 4316
CourtLouisiana Court of Appeal
DecidedDecember 24, 1975
DocketNo. 5224
StatusPublished
Cited by4 cases

This text of 325 So. 2d 375 (Mid-South Contractors, Inc. v. Ratcliff) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mid-South Contractors, Inc. v. Ratcliff, 325 So. 2d 375, 1975 La. App. LEXIS 4316 (La. Ct. App. 1975).

Opinion

HOOD, Judge.

Mid-South Contractors, Inc., instituted this suit to recover the profits it allegedly would have received under a contract entered into with defendant, J. E. Ratcliff, had plaintiff been permitted to complete the contract. Defendant Ratcliff filed a [377]*377reconventional demand seeking to recover damages for an alleged breach of contract by plaintiff. Judgment was rendered by the trial court in favor of defendant, rejecting plaintiff’s demands and condemning Mid-South to pay to Ratcliff the sum of $12,610.20 as damages. Plaintiff Mid-South appealed.

The issues presented are (1) whether the trial court erred in refusing to grant plaintiff a continuance, and (2) whether Mid-South breached its subcontract with Ratcliff.

In November, 1972, the Rapides Parish School Board awarded a contract to defendant Ratcliff, a general contractor, to renovate the Boyce High School. Ratcliff then entered into a subcontract with Mid-South, under the terms of which the latter agreed to do the painting work on the project, pursuant to plans and specifications prepared by the architects, for a contract price of $16,490.00.

The subcontract entered into between the parties was evidenced by a letter from Mid-South to Ratcliff dated November 24, 1972, submitting a bid for the painting work, and a letter from Ratcliff to Mid-South, dated December 20, 1972, in which defendant accepted plaintiff’s bid, with one mutually acceptable modification. Rat-cliff’s letter to plaintiff contains the following statements:

“All matters within the scope of this contract shall be governed by the necessary conditions of the specifications and by the provisions of my contract- with the Owner. You are to comply with all governmental regulations concerning the health and safety of your employees and the public.
“We expect to start at an early date on the work in the Gymnasium Building and to complete that part by June 1, 1973. Most of the work in the Classroom Building will have to be done between June 1, 1973 and August 15, 1973. Please mark your records so that you will plan to have men ready to complete the work as outlined above.”

The evidence shows that Mid-South did some painting in the gymnasium building in April and May, 1973, but that the painting work on that building was not completed by June 1, 1973, as required by the contract. Also, despite repeated demands by employees of defendant, Mid-South failed to begin the painting of other parts of the project by the middle of July, when it became apparent that it would be impossible even with due diligence for plaintiff to complete all of the painting work by August 15, 1973.

After plaintiff had failed to resume work on the gymnasium and to commence painting the rest of the project following repeated demands made by representatives of defendant to do so, Robert T. Ratcliff, an authorized employee of the defendant’s construction company, sent a “mailgram” to Mid-South on July 14, 1973, advising that “because of your failure to timely perform your subcontract with J. E. Ratcliff General Contractors reference Boyce High School job, it is terminated this date.” Plaintiff performed no more work on the school renovation project after that mail-gram was received by it.

Immediately after terminating the contract in that manner, Ratcliff engaged another painting contractor, Raymond Prest-ridge, to complete the painting work on the project. Prestridge began working immediately, employing six to eight painters who at times worked six and seven days a week, nine or ten hours a day. Despite what we consider to be diligent efforts on the part of Prestridge, the latter was unable to complete the painting work on the entire project by August IS, 1973, as required by the contract, but instead the painting work, was actually completed the latter part of December, 1973, while school was in session.

Mid-South filed this suit on December 12, 1974, to recover $3500.00, being the [378]*378profits which it allegedly would have earned under the subcontract if it had been permitted to finish the job. Defendant answered, alleging that Mid-South had breached the contract by failing to perform the painting work required by the subcontract, and it reconvened for damages in the amount of $12,610.20, being the additional cost allegedly incurred by Ratcliff in having the painting work completed.

At a pre-trial conference held on February 13, 1975, the case was scheduled for trial on May 27, 1975. When the case came up for trial on the last mentioned date, plaintiff filed a motion for a continuance, alleging as grounds therefor: (1) That plaintiff’s attorney had withdrawn as its counsel in this case and from the practice of law on April 30, 1975; (2) that important records of Mid-South had been subpoenaed by Ratcliff and by the United States District Court for the Western District of Louisiana, thus making it impossible for Mid-South to properly prosecute its original demand or defend itself in the reconventional demand without serious and undue risk; and (3) that the president of Mid-South had been subpoenaed by the United States District Court to appear before a Federal grand jury on May 28, 1975, and thus would not be able to be present during the trial of the instant suit.

The trial court denied plaintiff’s motion for a continuance, and the case was tried on its merits on May 27, 1975. Following that trial, the trial judge concluded that plaintiff Mid-South had breached the painting subcontract which had been entered into between the parties, and he accordingly rendered judgment in favor of Ratcliff and against Mid-South for the amount demanded in defendant’s reconven-tional demand. Mid-South appealed.

Motion for Continuance

Plaintiff contends, first, that the trial court erred in refusing to grant its motion for a continuance and that the judgment thus should be reversed and the case remanded for a new trial.

From the time the suit was filed until April 30, 1975, plaintiff was represented by the firm of Burnett, Harrison, Sutton and Walker, a professional law corporation, with Michael H. Wainwright, a member of that firm, handling the case for plaintiff. On April 30, 1975, Wainwright left that firm and he discontinued representing plaintiff in this suit on that day. Thereafter, although the same law firm, Burnett, Harrison, Sutton and Walker, continued to represent plaintiff, the files were turned over to Stephen V. Calloway, a member of the same firm, and Mr. Callo-way has handled the case for plaintiff since that time.

The record shows that the deposition of Harry Phillips, the superintendent of painters for plaintiff, was taken on March 12, 1975. The deposition of Malcolm Fu-qua, supervisor of the Boyce High School project for defendant, was taken on May 9, 1975, while plaintiff was being represented by its new counsel. And, the oral depositions of Dan Holt Hicks, James E. Ratcliff and Robert T. Ratcliff, all of whom occupied managerial positions with defendant construction company and had personal knowledge of the facts which are relevant to the issues presented here, were taken on May 14, 1975. Plaintiff’s new counsel, Calloway, was present and participated in-the taking of the last mentioned depositions.

Much of the relevant evidence was in the record before trial, therefore, and most of it was available to plaintiff’s new counsel, Mr. Calloway, as soon as it would have been available to Mr. Wainwright. The issues presented in this case are not unusually complicated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JLN v. State
894 So. 2d 751 (Supreme Court of Alabama, 2004)
Thomas v. Winn Dixie Louisiana, Inc.
407 So. 2d 520 (Louisiana Court of Appeal, 1981)
Mid-South Contractors, Inc. v. Ratcliff
329 So. 2d 463 (Supreme Court of Louisiana, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
325 So. 2d 375, 1975 La. App. LEXIS 4316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mid-south-contractors-inc-v-ratcliff-lactapp-1975.