Mid-Continent Life Insurance v. Henry's, Inc.

520 P.2d 1319, 214 Kan. 350, 1974 Kan. LEXIS 345
CourtSupreme Court of Kansas
DecidedApril 6, 1974
Docket47,158
StatusPublished
Cited by6 cases

This text of 520 P.2d 1319 (Mid-Continent Life Insurance v. Henry's, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mid-Continent Life Insurance v. Henry's, Inc., 520 P.2d 1319, 214 Kan. 350, 1974 Kan. LEXIS 345 (kan 1974).

Opinion

The opinion of the court was delivered by

Prager, J.:

This is a dispute between the lessor and lessee of a a commercial building as to who has tibe duty to rebuild an exterior wall. The action was brought by the plaintiff-appellant, Mid-Continent Life Insurance Company, as lessor, against Henry’s, Inc., the defendant-appellee, as lessee. We will refer to the Mid- *351 Continent Life Insurance Company as Mid-Continent or plaintiff. We will refer to Henry’s, Inc., as Hemy’s or defendant. The facts in this case are not greatly in dispute and are as follows: In the late 1940’s Henry’s Building Company, Inc. constructed a three-story commercial building for use as a retail clothing store. The building company had earlier acquired 99-year leases covering the store site. After completion the building was leased to a sister corporation, Henry’s, Inc., which operated the store. Three brothers, Henry, Isadore and Leo Levitt, were the original owners and the only stockholders of both companies. The store building is located in the downtown area of Wichita. The store sits immediately to the south of the Bissantz building, another three-story structure which existed when the store was erected. The Bissantz building abutted directly on the property line and at the time of construction the north wall of Hemy’s building was built in close proximity to the wall of the Bissantz building touching it in a number of places. Because of the location of the Bissantz building’s wall it was impossible to install exterior brick to finish the north wall of Hemy’s building. Instead a parapet was built between the roofs of the Hemy’s building and the Bissantz building so that the area between the two buildings was fully protected from the elements. As finally constructed the external face of the north wall of Hemy’s building consisted only of hollow tile. This was perfectly satisfactory so long as the wall was protected by the adjoining Bissantz building. Except for the penthouse area of the store building which houses the elevator shafts, the entire north wall was hidden from view by the wall of the Bissantz building.

In 1962 upon the advice of their tax consultant the Levitt brothers decided to sell the store building and enter into a sale-leaseback arrangement. The Levitt brothers through their agent got in touch with Mid-Continent and offered to sell their leasehold rights in the land and building to Mid-Continent for $1,050,000 with a leaseback to Hemy’s, Inc. for a 25-year term with a guaranteed rent of $80,000 per year, plus two percent of the annual gross sales in excess of $4,000,000. In the course of the negotiations the Levitts delivered the plans and specifications of the building to Mid-Continent for their examination. Mid-Continent employed an architect from Oklahoma City to inspect the building and to advise them as to its condition. Thereafter Mid-Continent purchased the leasehold interests and the building from Hemy’s Building Company, Inc. and *352 simultaneously entered into a lease agreement under the terms of which Henry’s, Inc. leased the premises for a term of 25 years commencing July 1, 1962. It should be noted that the leasehold ownership in the land was based upon two 99-year leases, one of which terminated in the year 2023 and the other in 2028. Henry’s, Inc. took possession under the lease effective July 2, 1962, and continued to operate its merchantile business as it had done for many years. The lessor and lessee got along very well and apparently had no serious problems.

The problem in this case arose in 1970 when the owners of the Bissantz building decided to remove its two-top floors. The contractor who was hired to remove the top floors of the Bissantz building discovered the unfinished condition of the north wall of Henry’s building during the course of the construction work. Mr. Teall, the contractor, upon the discovery of the condition of the wall notified the Wichita City Inspection Department. Mr. Teall was advised that hollow tile on an exterior wall did not comply with the city building code. Mr. Teall immediately got in touch with one of the Levitt brothers and informed him that the north wall of the Henry’s building was not in compliance with the city building code and that something had to be done. The Levitt brothers through their attorney advised Mid-Continent of the condition of the wall and took the position that it was the obligation of Mid-Continent, as lessor, to rebuild the wall. At this point the controversy between Mid-Continent and Henry’s began. Whose obligation was it under the lease to rebuild the wall? Each of the parties pointed the finger of responsibility at the other. On one point there was complete agreement — the condition of the wall constituted an emergency situation and immediate steps should be taken to correct it. The parties agreed that Mr. Levitt should employ a contractor to proceed to rebuild the north wall but neither of the parties would waive its rights nor jeopardize its position that the responsibility for rebuilding the wall was on the other. Thereafter the wall was rebuilt with dispatch. Mid-Continent paid the contractor the cost of construction in the amount of $33,808.41. Henry’s employed an architect for the project and paid his fee in the amount of $3,416.15. Each of the parties stood firm in its position that the cost of rebuilding the wall should be borne by the other. On July 7, 1971, Mid-Continent filed this action against Henry’s for the recovery of the $33,808.41 which it had paid to the contractor. Henry’s counter-claimed for the architect fees it had paid in the amount of $3,416.15.

*353 After the issues were framed the case was tried to the court which entered judgment in favor of the defendant Henry’s in the amount of the architect fees. The basis for the trial court’s holding was that the obligation to rebuild the wall fell on the shoulders of the lessor Mid-Continent. The trial court made extensive findings of fact and conclusions of law which it incorporated in its judgment. Mid-Continent has appealed to this court.

The petition filed by Mid-Continent contained a cause of action in Count 1 based upon the rights and obligations of the parties under the written lease. It further contained a cause of action in Count 2 based upon alleged false representations made by the Levitts as to the condition of the north wall at the time the building was sold to Mid-Continent. The trial court found from disputed evidence that false representations had not been established. It is contended by Mid-Continent on this appeal that the trial court erred in so finding. Based upon the entire evidentiary record we have concluded that the findings of the trial court are supported by substantial, competent evidence and that the trial court did not commit error in finding against Mid-Continent on the issue of false representation.

The remaining point of error asserted by the appellant is that the trial court erred as a matter of law in failing to hold that, under the express terms of the lease, Henry’s was required to assume the cost of restoring the north wall of the store building to first-class condition after the partial razing of the adjacent building. Furthermore Mid-Continent contends that the trial court’s findings of fact and conclusions of law to the contrary are clearly erroneous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Statler Arms, Inc. v. APCOA, Inc.
700 N.E.2d 415 (Cuyahoga County Common Pleas Court, 1997)
Brown v. Green
884 P.2d 55 (California Supreme Court, 1994)
Dennison v. Marlowe
744 P.2d 906 (New Mexico Supreme Court, 1987)
Baca v. Walgreen Co.
630 P.2d 1185 (Court of Appeals of Kansas, 1981)
Scott v. Prazma
555 P.2d 571 (Wyoming Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
520 P.2d 1319, 214 Kan. 350, 1974 Kan. LEXIS 345, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mid-continent-life-insurance-v-henrys-inc-kan-1974.