Mid-America Pipeline Company v. Federal Power Commission, Northern Natural Gas Co., Intervenor

330 F.2d 226
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 15, 1964
Docket17717
StatusPublished
Cited by2 cases

This text of 330 F.2d 226 (Mid-America Pipeline Company v. Federal Power Commission, Northern Natural Gas Co., Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mid-America Pipeline Company v. Federal Power Commission, Northern Natural Gas Co., Intervenor, 330 F.2d 226 (D.C. Cir. 1964).

Opinion

BURGER, Circuit Judge.

Petitioner, Mid-America Pipeline Company, seeks review of an order of the Federal Power Commission under Section 7 of the Natural Gas Act 1 granting a certificate of public convenience and necessity to Northern Natural Gas Company, Intervenor, to construct and operate facilities for natural gas transmission. This order also disclaimed certificate jurisdiction over an extraction plant constructed by Northern Gas Products Company (Products Company) adjacent to the certificated pipeline of Northern. The challenged order was issued December 28, 1962; Mid-America sought rehearing January 14, 1963, and rehearing was denied March 12, 1963.

Mid-America is exclusively an interstate common carrier of natural gas liquids with a liquids pipeline system extending from New Mexico and West Texas to Minnesota and intermediate points. It is subject to regulation only by the Interstate Commerce Commission. 2 Northern is a major natural gas company which owns and operates an interstate natural gas pipeline system; it also owns Products Company a subsidiary engaged in the extraction, transportation and sale of liquefied petroleum. The transmission facilities certificated by the challenged order were to supply approximately 900,000 Mef on gas per day to Products Company’s extraction plant for the extraction of liquid petroleum gases from the gas stream and thereafter return the residue natural gas to Northern’s main transmission line. In this process the natural gas so diverted and later returned to Northern’s line would be depleted by an estimated 39,862 Mcf on a peak day and would suffer a specified heating loss. See footnote 6, infra.

Mid-America attacks primarily the Commission’s disclaimer of certificate jurisdiction over the extraction plant, arguing that this facility is used as a conduit for transmission of natural gas in interstate commerce and that the extraction operations will significantly impair the heating content of the gas stream. Mid-America points out that Products Company also proposed to construct and operate a natural gas liquids pipeline *228 running from Kansas to Iowa, where it would connect with another pipeline, and that Products Company’s projected terminals for the sale of liquids along its pipelines would place facilities within Mid-America’s marketing area. The combined activities of Northern and Products Company, it is argued, would thus compete directly with Mid-America’s service both in supply and market areas. Before the Commission, Mid-America contended that it could supply the needs of the area indefinitely and that extraction operations would ultimately increase Northern’s transportation costs by preempting low-priced gas reserves and diminishing cheap expansibility. Mid-America urges that Northern would thus be enabled improperly to subsidize its liquid gas business by loading part of the extraction operating costs onto its jurisdictional natural gas customers, thereby engaging in unlawfully subsidized competition with Mid-America.

The Commission maintains that Mid-America has no standing because the claim of potential competitive injury is too speculative to meet the test of aggrievement under Natural Gas Act, § 19(b), 52 Stat. 831 (1938), as amended 15 U.S.C. § 717r(b) (1958). Mid-America will be adversely affected by operation of Products Company’s transmission facilities to the extent that Mid-America’s shippers will be unable to compete with Products Company in the sale of liquid gas. The Commission found that “Mid-America’s evidence tended to prove that Products Company’s operation will compete vigorously with Mid-America.” This affords a basis for concluding that Mid-America has standing to challenge the order under review. Cf. City of Pittsburgh v. Federal Power Commission, 99 U.S.App.D.C. 113, 118-120, 237 F.2d 741, 746-748 (1956).

Mid-America contends that the holdings in City of Detroit v. Federal Power Commission, 97 U.S.App.D.C. 260, 230 F.2d 810 (1955), cert. denied sub nom. Panhandle Eastern Pipe Line Co. v. City of Detroit, 352 U.S. 829, 77 S.Ct. 34, 1 L.Ed.2d 48 (1956); and Panhandle Eastern Pipe Line Co. v. Federal Power Commission, 113 U.S.App.D.C. 94, 305 F.2d 763 (1962), cert. denied, 372 U.S. 916, 83 S.Ct. 719, 9 L.Ed.2d 722 (1963), are dispositive in that they require Northern to obtain from the Commission a certificate of public convenience and necessity for construction and operation of the extraction plant. However, these cases arose out of rate-making rather than certification proceedings. In the City of Detroit opinion we noted that “the obvious fact that the extraction process is incident to the overall pipeline transmission and resale operations, [coupled with other factors mentioned] clearly brings the extraction operations within the jurisdiction of the Commission.” 97 U.S. App.D.C. at 270, 230 F.2d at 820. We ordered the Commission to re-examine its decision that it would not credit extraction plant revenues to natural gas pipeline operations in setting natural gas rates; subsequently, in Panhandle, supra, we concluded that the Commission had erred in construing our opinion in City of Detroit as requiring that all extraction revenues be credited to the pipeline and we again remanded to the Commission with directions “to reach an independent determination, in light of our opinion in the City of Detroit case, as to whether there should be an allocation of the extraction plant profits * * 113 U.S.App.D.C. at 99, 305 F.2d at 768. 3 Thus, these cases did not involve a question of certificate jurisdiction; rather they dealt with the circumstances in which the Commission could consider cost allocation between pipeline operations and non-certificated facilities.

In the order under review, the Commission explicitly conditioned issuance of a certificate of public convenience and necessity to Northern for the additional pipeline upon compliance with the terms of a rate settlement between Northern and the utility customers who had intervened in the Commission proceed *229 ings. In light of this condition, we conclude that the Commission was not required in this case to certificate the extraction operation and that the Commission adequately considered the relevant factors in granting Northern a certificate of public convenience and necessity for the additional transmission facilities.

Significantly the Commission stated: “ [ W] e need not finally determine the matter of cost allocations in this proceeding under Section 7 of the Act. This issue is more properly before us in Sections 4 and 5 proceedings.” This finding by the Commission accords with our holdings in the City of Detroit and Panhandle

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
330 F.2d 226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mid-america-pipeline-company-v-federal-power-commission-northern-natural-cadc-1964.