Michigan Wisconsin Pipeline Co. v. Moore

319 F. Supp. 753, 37 Oil & Gas Rep. 521, 1970 U.S. Dist. LEXIS 9306
CourtDistrict Court, N.D. Mississippi
DecidedDecember 3, 1970
DocketNo. DC 6916-S
StatusPublished

This text of 319 F. Supp. 753 (Michigan Wisconsin Pipeline Co. v. Moore) is published on Counsel Stack Legal Research, covering District Court, N.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michigan Wisconsin Pipeline Co. v. Moore, 319 F. Supp. 753, 37 Oil & Gas Rep. 521, 1970 U.S. Dist. LEXIS 9306 (N.D. Miss. 1970).

Opinion

MEMORANDUM OPINION

ORMA R. SMITH, District Judge.

Plaintiff has submitted two motions in this action for the consideration of the court. In the first motion plaintiff moves the court for permission to amend its answer to defendants’ counterclaim so as to add thereto one additional special or affirmative defense.

Rule 1, Fed.R.Civ.P. provides in part “They (the rules) shall be construed to secure the just, speedy, and inexpensive determination of every action.” Leave to amend shall be freely given when justice so requires. Rule 15(a) Fed.R.Civ. P.; 3 Moore’s Federal Practice ¶ 15.08(2) at 873.

In the present posture of the case the court sees no just reason why plaintiff should not be allowed to amend its answer to the counterclaim. The motion for leave to amend will be sustained.

Plaintiff’s second motion moves the court for a determination of the validity of the special and affirmative defenses raised by plaintiff in its answer to defendants’ counterclaim. This motion presents some difficulty to the court. In the first place, there has been no motion filed by defendants to question the sufficiency of the special and affirmative defenses interposed by plaintiff. Such a motion is authorized by Rule 12(f) Fed.R.Civ.P.

Plaintiff has not filed a motion for a summary judgment. If the court should treat the motion for a determination of the validity of defendants’ special and affirmative defenses as one for a summary judgment, disposition thereof would be required as provided in Rule 56 Fed.R.Civ.P. In such a case each party would have the right to file affidavits or other supporting evidence in regard to their respective position.

The crux of the motion is that the court is requested to render a pretrial opinion on the validity of the special and affirmative defenses without having heard any evidence in regard thereto.

Defendants have not raised any specific objection to the proposal that the court rule before a trial on the validity of said defenses. It is probable that a pretrial ruling by the court on certain of the legal issues involved in the special and affirmative defenses of plaintiff will save unnecessary and needless expense for both parties. With this in mind, the court will, to some extent at least, respond to the motion.

Plaintiff owns a right-of-way for the construction and maintenance of gas pipelines across the land of defendants acquired in 1955 from a predecessor in title to the land now owned by defendants and involved in this action. A pipeline was constructed in 1956, and, under a multiple pipeline clause in the contract for the right-of-way, a second pipeline was constructed across the land in 1966. Defendants acquired the land [755]*755in 1963, by virtue of a conveyance which excepted from the warranty of the conveyance the right-of-way above mentioned.

Plaintiff sued defendants in this action for damages said to have resulted. from the grading and removal by defendants of topsoil on the surface of the land under which the 1956 pipeline is buried. Plaintiff contends that as result of defendants’ actions the grade of the pipeline was changed and the line brought closer to the surface of the land, causing a dangerous condition to exist, and necessitating the lowering of the line by plaintiff, at great expense to plaintiff. Defendants have filed a counterclaim, alleging negligence in the construction and maintenance of the 1956 pipeline, and seek to reform the right-of-way agreement so as to change, amend or cancel the multiple pipeline clause of the agreement, or, in the alternative, the recovery of damages because of the imposition of the multiple pipeline right-of-way upon the land of defendants. Defendants also seek to recover damages for the negligent construction and maintenance of the 1956 pipeline.

Plaintiff has asserted several special defenses to the counterclaim. These special defenses will be considered by the court and their validity determined to the extent the court deems proper at this stage of the proceeding. ' S'

THE ACTION TO REFORM OR CANCEL THE MULTIPLE PIPELINE CLAUSE IN THE RIGHT-OF-WAY AGREEMENT, OR, IN THE ALTERNATIVE, TO AWARD DAMAGES FOR THE IMPOSITION OF THE AGREEMENT UPON THE LAND

Defendants do not allege fraud or overreaching by plaintiff’s predecessor in interest in connection with obtaining the right-of-way agreement from the former owners of the land, nor do they claim mutual mistake. The agreement was made in 1955. The pipeline in question was constructed in 1956. Defendants purchased the land in 1963. The court is of the opinion that defendants, being strangers to the agreement, do not have standing in the action sub judice to question the validity of the right of way agreement. Assuming arguendo that they do have standing, the court does not know of any authority and none has been brought to the court’s attention which holds that the court is authorized to make a new contract for the parties, even in cases where the parties who executed the contract are before the court.

Defendants contend that the multiple pipeline clause of the contract is so harsh and so inequitable as to make it unconscionable and, therefore, unenforceable. The Mississippi Supreme Court has consistently upheld the validity of right-of-way agreements for pipeline construction which contain unrestricted multiple pipeline rights. Baker v. Columbia Gulf Transmission Co., Miss., 1969, 218 So.2d 39; Ashcot, Inc. v. Texas Eastern Transmission Corporation, 1961, 241 Miss. 392, 129 So.2d 405; Hamilton v. Transcontinental Gas Pipeline Corp., 1959, 236 Miss. 429, 110 So.2d 612.

This court is bound to apply the Erie doctrine to this case.1 The United States Court of Appeals for the Fifth Circuit has said “There is no area of the law more appropriate for the application of the Erie doctrine than land contracts and title law.” 2 When the court applies the Mississippi law to the issue at hand it is apparent that defendants’ counterclaim does not state a claim upon which relief can be granted for the reformation of the right-of-way agreement or for the recovery of damages on account of the imposition of the easement to the servient tenement owned and held by defendants.

Counsel for both parties have cited the case of Baker v. Columbia Gulf [756]*756Transmission Co., supra, in support of their respective positions. The Mississippi Supreme Court, speaking through Presiding Justice Honorable Robert G. Gillespie, recognized the validity of the right-of-way agreement involved in Baker. In construing the contract involved in the case, Judge Gillespie held:

“In sum, we hold that the right of way agreement vested in Columbia the right to construct and maintain the pipe line constructed on plaintiffs' land without the necessity of condemnation proceedings, upon the payment of $1.00 per lineal rod plus a sum of money sufficient to compensate plaintiffs for all damages occasioned by construction. Plaintiffs allege three categories of damages as a result of the construction of the pipe line in 1965 as follows: (1) cutting and destroying timber, (2) cutting and destroying pine seedlings, and (3) appropriation of 12.85 acres of land which ‘can no longer be used profitably by plaintiffs * * * ’ We are of the opinion that plaintiffs are entitled to recover for the first two categories.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Phil E. Aaron v. Florida Gas Transmission Company
412 F.2d 802 (Fifth Circuit, 1969)
Cities Service Oil Company v. Corley
197 So. 2d 244 (Mississippi Supreme Court, 1967)
Ashcot, Inc. v. Texas Eastern Transmission Corp.
129 So. 2d 405 (Mississippi Supreme Court, 1961)
Masonite Corp. v. Burnham
146 So. 292 (Mississippi Supreme Court, 1933)
Henritzy v. Harrison County
178 So. 322 (Mississippi Supreme Court, 1938)
Leavenworth v. Hunter
117 So. 122 (Mississippi Supreme Court, 1928)
Baker v. Columbia Gulf Transmission Co.
218 So. 2d 39 (Mississippi Supreme Court, 1969)
Chapman v. Copeland
55 Miss. 476 (Mississippi Supreme Court, 1877)
Mississippi & Tennessee R. R. v. Archibald
67 Miss. 38 (Mississippi Supreme Court, 1889)
Blodgett v. Seals
78 Miss. 522 (Mississippi Supreme Court, 1900)
Romano v. Yazoo & Mississippi Valley Railroad
40 So. 150 (Mississippi Supreme Court, 1905)
London v. Braxton
102 So. 2d 683 (Mississippi Supreme Court, 1958)
Hamilton v. Transcontinental Gas Pipe Line Corp.
110 So. 2d 612 (Mississippi Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
319 F. Supp. 753, 37 Oil & Gas Rep. 521, 1970 U.S. Dist. LEXIS 9306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michigan-wisconsin-pipeline-co-v-moore-msnd-1970.