Michigan Wisconsin Pipe Line Company v. Walet

225 So. 2d 76
CourtLouisiana Court of Appeal
DecidedJuly 25, 1969
Docket2724
StatusPublished
Cited by22 cases

This text of 225 So. 2d 76 (Michigan Wisconsin Pipe Line Company v. Walet) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michigan Wisconsin Pipe Line Company v. Walet, 225 So. 2d 76 (La. Ct. App. 1969).

Opinion

225 So.2d 76 (1969)

MICHIGAN WISCONSIN PIPE LINE COMPANY, Plaintiff-Appellee,
v.
Douglas Joseph WALET et al., Defendants-Appellants.

No. 2724.

Court of Appeal of Louisiana, Third Circuit.

June 12, 1969.
Rehearing Denied July 24, 1969.
Dissenting Opinion July 25, 1969.

*77 Mestayer & Simon, by Ray F. Mestayer, New Iberia, for defendants-appellants.

Shotwell, Brown & Sperry, by Burt Sperry, Monroe, Earl H. Willis, St. Martinville, for plaintiff-appellee.

Before SAVOY, CULPEPPER and MILLER, JJ.

MILLER, Judge.

Six expropriation cases were filed by Michigan Wisconsin Pipe Line Company to obtain servitudes across defendants' property for the installation and operation of a natural gas pipeline within Iberia Parish, Louisiana. The cases were consolidated both for trial and appeal purposes. All issues presented in all six cases are discussed in this opinion, but a separate decision is being rendered in each case.

Plaintiff is a natural gas company within the meaning of the Natural Gas Act, U.S. C.A. Title 15, Section 717(a) and (b), and is the holder of a Certificate of Public Convenience and Necessity from the Federal Power Commission authorizing the construction of the 30-inch transmission pipeline and, as such, is entitled to institute these proceedings.

Landowners filed exceptions of prematurity and non-joinder and answers challenging the taking and the feasibility of the route. In the non-joinder exception, landowners contended that their property was under lease to tenants who had growing crops on the property and that these tenants should be made parties to the suit. With the exception of defendant Louis Dugas, Landowners failed to serve plaintiff with their respective answers and pleadings within ten days from the date each was served with the original pleadings, and *78 therefore they lost their right to challenge the taking and the feasibility of the route. LSA-R.S. 19:6 and 7. In the Dugas case, his answer was timely served and these issues were raised.

Prior to the date that exceptions of non-joinder were to be heard, the parties stipulated that the named tenants "are hereby made and recognized as party defendants in each of said suits, to the same extent and with the same effect as if they had been named defendants by plaintiff originally, and been served with the required notice, and had appeared and responded, jointly through same counsel with the landowner defendants. The parties further stipulate and agree that it shall not be necessary for said tenant-defendants to file any pleadings herein, but the said tenant-defendants shall be considered as having joined in and jointly filed every appearance, answer, exception, motion, exhibit or other document or pleading heretofore filed by the landowner defendant in the appropriate case * * *" (Volume 1, Walet case, Tr. 34).

On July 15, 1968 all exceptions, motions and objections previously filed were tried. The trial judge assigned written reasons on July 17th, holding essentially that, except in the Louis Dugas suit, all defendants failed to serve pleadings on counsel for plaintiff within the 10-day period set by LSA-R.S. 19:6 and 7, and therefore the only issue remaining, except in the Dugas suit, was that of adequate compensation. The trial court also held that tenants did not have a right to question plaintiff's right to expropriate or to challenge the feasibility of the route. All defendants applied for writs of certiorari, prohibition and mandamus to the Court of Appeal, Third Circuit, (Docket Number 2511) to have these rulings reversed. This application for writs was denied for the reason that an adequate remedy was available on appeal.

At the conclusion of the trial of the consolidated cases, counsel for Louis Dugas was specifically asked to proceed with his special defenses. It was counsel's position that the July 17th ruling limited the issue to compensation, and therefore he would not present evidence on the special defenses raised in the Dugas suit.

However the July 17th ruling held that Louis Dugas had not lost his right to contest the necessity of the taking or feasibility of the route. (Walet, Tr. 53). Furthermore, the Minutes of Court for July 29, 1968 (Walet, Tr. 3) state that "These cases were consolidated for the purposes of trial, with separate judgments to be rendered, on the question of damages only; the other questions or issues raised in #27947 (Dugas) will be taken up on the day set for its trial."

The record supports the trial court's finding that plaintiff had the right to institute these proceedings and that the route and location of the line were selected in accordance with sound engineering principles.

Appellants allege that the trial court erred:

(1) In holding that the owners of predial leases have no right to "challenge the taking."
(2) In refusing to issue subpoenas for maps and information vital to the defense to these takings.
(3) In limiting the trial to the question of quantum and in refusing to allow the "tenants" the right to question "location."
(4) In holding that outside of the servitude the only compensable damages were those factors which reduced the value of the land.
(5) In failing to allow damages for the loss of crops which, while not in the actual right of way, could not be harvested because of the construction of the pipeline.
(6) In failing to allow adequate damages.

As to the first and third assignments of error, there is nothing in the record to sustain *79 appellants' position that some of the leases were recorded. But appellants contend that we are not here concerned with whether there were written, recorded leases, or whether the pipeline company had actual knowledge of the existence of the leases. This argument is based on the fact that the lessees were made parties to the suits by stipulations entered before the trial judge ruled that such lessees had no right to challenge the taking. Appellants cite the case of Columbia Gulf Transmission Company v. Hoyt, 1968, 252 La. 921, 215 So.2d 114, where the landowner had granted a servitude to the pipeline company. At the time the servitude was granted there was in existence a recorded surface lease in favor of Hoyt. When Hoyt prevented the pipeline from crossing, the company sought an injunction and restraining order to prohibit Hoyt from blocking construction. The injunction was denied and it was held that "a predial lease is property within the meaning of Article I, Section 2 of the Louisiana Constitution. As such, it must be accorded constitutional protection, requiring just compensation to the lessee before the lease rights are damaged. See State Through Sabine River Authority v. Phares, 245 La. 534, 159 So.2d 144, and State ex rel. Cotting v. Sommerville, 104 La. 74, 28 So. 977."

We distinguish the Hoyt case, for the record does not support that we are here dealing with recorded predial leases. Separate ownership arising from a lease can be asserted against third persons only when the lease is recorded. LSA-R.S. 9:2721, LSA-CC Arts. 2264, 2266. See Minter v. Union Cent. Life Ins. Co., 180 La. 38, 156 So. 167; Summers & Brannins v. Clark, 30 La.Ann. 436; Yiannopoulous, Civil Law of Property, Section 44, p. 135 (1966).

Appellants also cite Texas Eastern Transmission Corporation v. Bowman, 238 La.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lanie Farms, Inc. v. Cleco Power, LLC
259 So. 3d 414 (Louisiana Court of Appeal, 2018)
Soma Enterprises v. State, DOT & Dev.
521 So. 2d 829 (Louisiana Court of Appeal, 1988)
United States v. 131.68 Acres of Land, More or Less
695 F.2d 872 (Fifth Circuit, 1983)
Sick v. Bendix-United Geophysical Corp.
341 So. 2d 1308 (Louisiana Court of Appeal, 1976)
Griffith v. Roy
269 So. 2d 217 (Supreme Court of Louisiana, 1972)
Michigan Wisconsin Pipe Line Co. v. Walet
227 So. 2d 588 (Supreme Court of Louisiana, 1969)
Michigan Wisconsin Pipe Line Co. v. Gonsoulin
225 So. 2d 86 (Louisiana Court of Appeal, 1969)
Michigan Wisconsin Pipe Line Co. v. Eldridge
225 So. 2d 87 (Louisiana Court of Appeal, 1969)
Michigan Wisconsin Pipe Line Co. v. Oubre
225 So. 2d 90 (Louisiana Court of Appeal, 1969)
Michigan Wisconsin Pipe Line Co. v. Dugas
225 So. 2d 91 (Louisiana Court of Appeal, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
225 So. 2d 76, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michigan-wisconsin-pipe-line-company-v-walet-lactapp-1969.