Michelson v. Mid-Century Insurance

99 Cal. Rptr. 2d 804, 83 Cal. App. 4th 450, 2000 Daily Journal DAR 9649, 2000 Cal. Daily Op. Serv. 7308, 2000 Cal. App. LEXIS 685
CourtCalifornia Court of Appeal
DecidedAugust 1, 2000
DocketB133127
StatusPublished

This text of 99 Cal. Rptr. 2d 804 (Michelson v. Mid-Century Insurance) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michelson v. Mid-Century Insurance, 99 Cal. Rptr. 2d 804, 83 Cal. App. 4th 450, 2000 Daily Journal DAR 9649, 2000 Cal. Daily Op. Serv. 7308, 2000 Cal. App. LEXIS 685 (Cal. Ct. App. 2000).

Opinion

Opinion

NOTT, J.

Diana Michelson appeals from a judgment entered following the grant of summary judgment in favor of respondent Mid-Century Insurance Company (Mid-Century).

Background

This is one of many cases arising out of the January 17, 1994 Northridge earthquake. Michelson was a homeowner insured by Mid-Century. The policy had a provision requiring commencement of litigation within one year after occurrence of a loss.

On February 19, 1994, Michelson submitted a claim to Mid-Century for damage sustained to her residence by the Northridge earthquake. 1 Mid-Century denied the claim on March 16, 1994. The claim was denied because the cost to repair was estimated to be $6,964.76, whereas Michelson was required to first pay a deductible of $20,700 (10 percent of $207,000). In the letter of denial, Mid-Century stated that should Michelson discover any *453 additional damage or have any further questions, Mid-Century “will be happy to re-open your file.”

On May 3, 1995, over a year after the earthquake, Michelson retained counsel, who submitted a claim showing earthquake damage of $257,816.78.

On February 16, 1996, Mid-Century made payment on a portion of Michelson’s claim. 2 Evidently the unpaid, disputed portion of the claim involved asbestos contamination, among other things. The claim was denied by Mid-Century on July 2, 1996, on the dual basis of refusal to allow inspection and the one-year limitation provision of the policy.

On December 18, 1996, Michelson requested mediation through a program sponsored by the California Department of Insurance. Mid-Century agreed. Mediation was held on January 15, 1997, 3 but was not successful in resolving the matter. The Department of Insurance gave written notice to the parties on January 27, 1997, that the program was terminated as to them.

Michelson filed suit against Mid-Century on July 29, 1997. The complaint contained causes of action for breach of contract, breach of the covenant of good faith and fair dealing, intentional and negligent misrepresentation, fraud, and unfair competition. The complaint was later amended in February 1998.

Mid-Century subsequently brought a motion for summary judgment based on the one-year suit provision in the policy. Michelson argued that the one year had been tolled. The trial court ruled that even taking tolling into consideration, Michelson had not timely filed suit.

Discussion

1. Standard of Review

The grant of a motion for summary judgment is reviewed de novo on appeal. (Edward Fineman Co. v. Superior Court (1998) 66 Cal.App.4th 1110, 1116 [78 Cal.Rptr.2d 478].) In making that independent review, we are obliged to determine whether the record shows any triable issue of material fact. (Stratton v. First Nat. Life Ins. Co. (1989) 210 Cal.App.3d 1071, 1083 *454 [258 Cal.Rptr. 721].) The overall policy of the law is to favor trial on the merits. Therefore, all close questions as to the propriety of granting the motion will be resolved in favor of the party opposing the motion. (Ibid.) In that same vein, the moving papers will be strictly construed while the opposing papers will be liberally construed. (Ibid.)

2. Analysis

a. Overview

The time line of various events is crucial to resolution of this appeal. It is:

January 17, 1994—the earthquake occurred.

February 19, 1994—Michelson made a claim to Mid-Century.

March 16, 1994—Michelson’s claim was denied.

May 3, 1995—Michelson resubmitted her claim.

February 16, 1996—the undisputed portion of the claim was paid.

July 2, 1996—the disputed portion of the claim 0was denied.

December 19, 1996—the parties were accepted into mediation.

January 15, 1997—mediation was held, but was unsuccessful.

January 27, 1997—notice of termination of the mediation program.

July 29, 1997—the complaint was filed.

The parties concur that the one-year period of limitation was tolled during Mid-Century’s consideration of Michelson’s claim and also during the time the parties were engaged in the state-sponsored mediation program. The dispute here centers on when the one-year period commenced, and the appropriate number of days the limitation period was tolled.

Michelson takes the position that the one-year period started on July 2, 1996, the date Mid-Century denied the balance of her claim. She argues that the matter was tolled during mediation, commencing December 19, 1996, until January 27, 1997, which is 40 days. She concludes she therefore had from July 2,1996, until August 11, 1997, in which to file her complaint. Since the complaint was filed on July 29, 1997, it was timely.

*455 Mid-Century states that the starting point of the limitation period was the date of the earthquake, January 17, 1994. The period ran for 33 days, until the claim was made on February 19, 1994. The matter was then tolled until the final denial on July 2, 1996. The limitation period then ran until December 19, 1996, when it was tolled until January 15, 1997, and then commenced again.

In sum, Mid-Century asserts that 33 days elapsed by July 2, 1996. Absent any further tolling, the one-year period would end on May 30, 1997 (July 2, 1996, to July 2, 1997, minus 33 days). However, Mid-Century agrees Michelson gets credit for the tolling of 28 days between December 19, 1996 and January 15, 1997, making June 27,1997, the ending date of the one-year period. The complaint was filed on July 29, 1997, which was too late.

We now turn to an examination of when the one-year period commenced, and the impact of any tolling.

b. Commencement of the One-year Period of Limitation

The pertinent policy provision states that “Suit on or arising out of this policy must be brought within one year after the loss occurs.”

The earthquake occurred on January 17, 1994. Citing Michelson’s allegations in her complaint, Mid-Century argued in its motion for summary judgment that such date commenced the start of the one-year period in which to file suit. In her response to the motion, Michelson agreed in her statement of undisputed facts that “Plaintiff’s earthquake loss occurred January 17, 1994.”

Michelson now contends that Mid-Century offered no evidence to support the proposition that January 17, 1994, was the starting date of the loss, thus creating a triable question of fact on that issue. We disagree.

As the moving party, it was Mid-Century’s burden to show that it had a complete defense to Michelson’s action. (Code Civ. Proc., § 437, subd.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Martinsen
193 Cal. App. 3d 843 (California Court of Appeal, 1987)
Stratton v. First National Life Insurance
210 Cal. App. 3d 1071 (California Court of Appeal, 1989)
North Coast Business Park v. Nielsen Construction Co.
17 Cal. App. 4th 22 (California Court of Appeal, 1993)
Edward Fineman Co. v. Superior Court of L.A. Cty.
78 Cal. Rptr. 2d 478 (California Court of Appeal, 1998)
People v. Turner
15 Cal. App. 4th 1690 (California Court of Appeal, 1993)
Waisbren v. Peppercorn Productions, Inc.
41 Cal. App. 4th 246 (California Court of Appeal, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
99 Cal. Rptr. 2d 804, 83 Cal. App. 4th 450, 2000 Daily Journal DAR 9649, 2000 Cal. Daily Op. Serv. 7308, 2000 Cal. App. LEXIS 685, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michelson-v-mid-century-insurance-calctapp-2000.