Michaels v. Pinten

175 N.W. 465, 208 Mich. 455, 1919 Mich. LEXIS 593
CourtMichigan Supreme Court
DecidedDecember 23, 1919
DocketDocket No. 88
StatusPublished
Cited by2 cases

This text of 175 N.W. 465 (Michaels v. Pinten) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michaels v. Pinten, 175 N.W. 465, 208 Mich. 455, 1919 Mich. LEXIS 593 (Mich. 1919).

Opinion

Stone, J.

The plaintiff is, and has been for about 20 years, a contractor and builder in Houghton county. [457]*457This suit was brought to recover a balance claimed to be due him from the defendant upon a building contract made in June, 1916. Plaintiff’s claim is concisely stated in the declaration to be that on or about June 14, 1916, he made the defendant a bid to excavate for a cellar and basement, and to furnish the labor and material for erecting a dwelling house and painting and decorating the same for $5,360.37, which said bid was made in writing and delivered to defendant; that after the receipt of said bid, defendant directed the plaintiff to proceed with the erection of the building according to the plans and specifications; that said bid did not include heating and plumbing; and that on or about June 16, 1916, defendant requested the plaintiff to secure an estimate and make a bid for furnishing materials and labor for heating and plumbing said dwelling house; that plaintiff at once secured an estimate of the cost for heating and plumbing from an experienced and competent plumber, which estimate was in the sum of $1,068, which was submitted to the defendant, and the plaintiff was directed to proceed with the work, and furnish materials for said heating and plumbing, which made the contract price for work and labor and materials, including plumbing and heating, $6,428.37; that after said bid was accepted, certain modifications and changes were made, which were mutually agreed to by the parties, from time to time during the progress of the erection of said building, which the defendant agreed to pay for as extras, as shown by the bill of particulars annexed to and made a part of the declaration; that the amount of the extras, including the plaintiff’s services, amounted to $1,428.76; that plaintiff furnished the labor and materials for all of the above matters, including said extras, for which defendant agreed to pay the plaintiff $7,857.13; that after the plaintiff had completed said dwelling house in accordance with said modified plans, [458]*458including said extras, the defendant accepted and occupied the said dwelling, and has ever since occupied the same as a home; that defendant has paid to the plaintiff on account of said work and labor, and for furnishing said materials, as aforesaid, $6,500, leaving a balance due the plaintiff of $1,357.18, with interest from the date of such occupancy.

The plea was the general issue with notice of settlement and payment in full. Upon the trial there was no question that the plans agreed upon by the parties were known as the “Radford plans,” with certain modifications, although certain plans called the “Maas plans” were discussed. A sharp, issue of fact arose as to the price agreed upon. The plaintiff was not able to produce his written bid, it being claimed that the same had been mislaid or lost, and defendant denied that he ever had one. This issue, which , was a vital one, was clearly submitted to the jury by the trial court. After stating the plaintiff’s claim to be as substantially set forth in the declaration, the court said:

“On the other hand, the defendant denies that the total amount of the bid or agreed price of putting up the house which was built by the plaintiff for the defendant, was the sum of $6,428.37, as claimed by the plaintiff, but insists that he, the defendant, notified the plaintiff, time and time again, that he did not want to put in excess of $5,000 into a house, and that he could not afford to do. it, and that the Maas plans were submitted to him, but that his wife wouldn’t have anything to do with them, and did not want them, and finally the Radford plans were gone over by the plaintiff, at the request of the defendant, and certain alterations or deductions were made from the Radford plans which brought the total down to $5,100 to complete the building according to those plans, and that that sum was to include plumbing and heating; and it is the claim of the defendant that one evening the defendant and his wife, at a meeting in the plaintiff’s office, talked over the Radford plans, as finally altered [459]*459to conform with, the sum of $5,100, and that the plaintiff then agreed that he would erect such a dwelling for the sum of $5,100 all complete.
“So, gentlemen, the real issue that you are called upon to determine in this case is, What was the price agreed upon to erect this dwelling? Was it the sum of $6,428.37 as claimed by the plaintiff, or was it the sum of $5,100, as claimed by the defendant? There is no dispute as to the charges for extras amounting to the sum of $1,428.76. Neither is there any dispute in regard to the amounts of payments made by the defendant, amounting to $6,500. The only question for you to determine is, What was the amount of the sum to be paid by the defendant for the building complete, according to the Radford plans?”

These figures were reiterated in the charge, and finally the court said:

“If you find that the bid for the Radford plans, as modified, was $6,428.37, including plumbing and heating, and there being no dispute about the extras, your verdict will be in favor of the plaintiff and against the defendant for the sum of $7,857.13, less $6,500 paid by defendant, and add interest at five per cent. $73.51, making a total due the plaintiff of $1,430.64. On the other hand, if you find that the bid was not for the sum of $6,428.37, but was in the neighborhood of $5,~ 100 as claimed by the defendant, then your verdict will be no cause of action, because if that was the contract, that is, the sum of $5,100, the plaintiff has been fully paid, both for the contract price and the extras.”

An extended discussion of the evidence would serve no good purpose. It is sufficient to say that there ■was here a clear cut question of fact, making a sharp issue, and it was submitted to the jury in a clear charge.

All of plaintiffs requests to charge were given except the 8th, which was as follows:

“In determining the question as to the amount of the bid made by the plaintiff, for building according [460]*460to the Radford plans, you may take into consideration the years of experience of Mr. Michaels as a contractor, and the actual cost of erecting and completing said building.”

The jury were instructed by the court that they might consider a paper called the “bidding sheet,” as bearing upon the probabilities of the claim of the plaintiff and his bookkeeper, provided that they found this bidding sheet was made at the time they were figuring on the price which the dwelling house was to cost the defendant. The jury were also charged:

“You also have a right to determine the actual cost of the building as bearing upon the probabilities regarding the bid made”;

• — and two witnesses testified as to the actual cost of erecting and completing such a building; but the jury were instructed that they would consider this evidence simply in determining the probabilities of the amount actually agreed upon between the parties, because it was the amount which was actually agreed upon which was to be determined by the'verdict.

Upon the examination of defendant’s wife she was permitted to testify as to the leaky condition of the building and the damage done thereby to the interior. She testified:

“Well, we moved into the house in July, and I think, about September, we had a terrible rainstorm from the east, and I called Mr. Michaels.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Toodle
400 N.W.2d 670 (Michigan Court of Appeals, 1986)
Anderson v. Lavelle
280 N.W. 729 (Michigan Supreme Court, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
175 N.W. 465, 208 Mich. 455, 1919 Mich. LEXIS 593, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michaels-v-pinten-mich-1919.