Michael Thalheimer v. Ramon and Stacey Halum

973 N.E.2d 1145, 2012 WL 3265029, 2012 Ind. App. LEXIS 386
CourtIndiana Court of Appeals
DecidedAugust 13, 2012
Docket49A02-1203-PL-167
StatusPublished
Cited by14 cases

This text of 973 N.E.2d 1145 (Michael Thalheimer v. Ramon and Stacey Halum) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michael Thalheimer v. Ramon and Stacey Halum, 973 N.E.2d 1145, 2012 WL 3265029, 2012 Ind. App. LEXIS 386 (Ind. Ct. App. 2012).

Opinion

OPINION

ROBB, Chief Judge.

Case Summary and Issues

Ramon and Stacey Halum (collectively, the “Halums”) entered into a contract with Michael Thalheimer for Thalheimer to remove carpet and tiles in the Halums’s home and to install new tiles. After Thal-heimer did so, a dispute arose among the parties regarding whether, when, and what Thalheimer would do about some portion of the work with which the Halums were dissatisfied. Following a bench trial, Thal-heimer appeals the trial court findings and judgment in favor of the Halums. Thal-heimer raises four issues, which we restate as: 1) whether the Halums’s spoliation of evidence, if at all, required a finding in favor of Thalheimer; 2) whether the doctrine of economic loss precluded the Ha-lums’s negligence claim; 3) whether the warranty in the contract precluded the *1148 Halums’s breach of contract claim; and 4) whether the evidence presented supports the trial court’s findings regarding the quality of Thalheimer’s work. The Ha-lums contend Thalheimer’s appeal was made in bad faith, and accordingly they request appellate attorney fees.

We affirm upon concluding that Thal-heimer waived his claim that the Halums spoliated evidence; the economic loss doctrine did not preclude the Halums’s negligence claim; the trial court did not abuse its discretion in finding that Thalheimer’s conduct negated the warranty in the contract; and the trial court did not abuse its discretion in finding that Thalheimer’s work was of poor quality. We deny the Halums’s request for appellate attorney fees.

Facts and Procedural History 1

On June 8, 2008, the Halums entered into a written contract with Thalheimer for his compensation to remove carpet and tiles in the Halums’s living room, entryway, and at least one hallway, and to install new tiles. Thalheimer completed the work in late June, the Halums conducted an initial review 2 of his work, and Thal-heimer and the Halums made a verbal agreement for Thalheimer to return at some unspecified later date to fix about six of the tiles which were unsatisfactory to the Halums. The Halums also paid Thal-heimer in full and provided Thalheimer with two $100 gift cards as well, which Thalheimer believed to be a bonus.

Over the next several months, Thalheimer and the Halums corresponded by email to negotiate when and how many tiles Thalheimer would adjust when he returned to the Halums’s home because the Halums identified additional tiles with which they were dissatisfied. At some point, the Halums became frustrated with the negotiations, hired another contractor to redo the flooring, and retained an attorney.

A little over a year after the contract was signed, on June 16, 2009, the Halums filed suit against Thalheimer, alleging breach of contract, negligence, and violation of an implied warranty of habitability.

Following a bench trial, the trial court entered an order which states:

[T]he Court ... now finds as follows:
1. That the [Halums] are entitled to Judgment against [Thalheimer] on their Complaint in the amount of $14,262.38, which represents the amount [the Ha-lums] paid in labor and materials to Jeremy Keenan to have their floor torn out and re-installed as a result of [Thal-heimer]’s Breach of Contract and negligence in installing the original floor per the parties’ contract.
[[Image here]]

Appellant’s Appendix, at 3-4.

Thalheimer filed a motion to correct error, which the trial court denied in an order which states:

FINDINGS OF FACT
[[Image here]]
4. [Thalheimer] alleged [in his motion to correct error] that the Court misap *1149 plied the law to the facts of this case and if certain corrections are made that the outcome would have been in favor of [Thalheimer].
5. The Court rejects [Thalheimer]’s arguments on the Motion to Correct Error and hereby denies the same.
CONCLUSIONS OF LAW
1. The contract was performed by [Thalheimer] and he was paid in full by the [Halums]. The contract was also supposed to be performed in a “good and workmanlike manner”.
2. The tile floor installation was done improperly, installed in an unworkman-like manner, and was a poor quality job. The [Halums] attempted to have [Thal-heimer] complete repair to the floor for several months, to no avail, and ended up having the entire floor replaced.
3. [Thalheimer] breached the contract, but was paid for his work, quantum meruit.
4. “Damage from a defective product or service may be recoverable under a tort theory if the defect causes personal injury or damage to other property, but contract law governs damage to the product or service to perform as expected.” Gunkel v. Renovations, Inc., 822 N.E.2d 150, 153 (Ind.2005). [The Ha-lums] presented additional evidence of physical injury to their son due to' scuffing his feet and falling down due to the unevenness of the tile floor installed by [Thalheimer] in order to support their claim of negligence. Gunkel is applicable to the facts of this case because the loss to [the Halums] was not purely economic. Tort law is therefore pertinent and should have been applied.
5. Expert testimony was presented by [the Halumsj’s witness, Jeremy Keenan, that the tile floor installation was of poor quality and needed to be redone in its entirety due to tile color and texture differences found in each new tile lot. He also found that he could not insure that the replacement of the offending tiles, by themselves, would not cause further damage to the floor during installation due to cracking and misalignment when placed next to the other non-offending tiles. Mr. Keenan was qualified as a skilled witness to establish the standard of care in installing this type of floor. That standard should have been met by [Thalheimer] in his initial installation and was not which supports the finding in favor of [the Halums].
6. Error alleged by [Thalheimer] that relates to spoliation of evidence and standing to sue were waived by [Thal-heimer] and therefore not considered in this order.
[[Image here]]

Id. at 5-7.

Thalheimer now appeals.

Discussion and Decision

I. Standard of Review

In reviewing an order in which the trial court makes findings of fact and conclusions of law, our standard of review is well-settled:

First, we determine whether the evidence supports the findings and second, whether the findings support the judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
973 N.E.2d 1145, 2012 WL 3265029, 2012 Ind. App. LEXIS 386, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michael-thalheimer-v-ramon-and-stacey-halum-indctapp-2012.