Michael J. Bermes v. G.K. Cambray & Company, Inc., Gregory K. Cambray d/b/a Cambray & Associates, Inc., and Lauri Massoth

CourtIndiana Court of Appeals
DecidedMarch 31, 2014
Docket35A02-1308-PL-694
StatusUnpublished

This text of Michael J. Bermes v. G.K. Cambray & Company, Inc., Gregory K. Cambray d/b/a Cambray & Associates, Inc., and Lauri Massoth (Michael J. Bermes v. G.K. Cambray & Company, Inc., Gregory K. Cambray d/b/a Cambray & Associates, Inc., and Lauri Massoth) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michael J. Bermes v. G.K. Cambray & Company, Inc., Gregory K. Cambray d/b/a Cambray & Associates, Inc., and Lauri Massoth, (Ind. Ct. App. 2014).

Opinion

Pursuant to Ind.Appellate Rule 65(D), this Memorandum Decision shall not be regarded as precedent or cited before any court except for the purpose of establishing the defense of res judicata, collateral Mar 31 2014, 8:02 am estoppel, or the law of the case.

ATTORNEY FOR APPELLANT: ATTORNEY FOR APPELLEE:

JEREMY L. REIDY JEFFREY G. RAFF MICHAEL S. GALLO Fort Wayne, Indiana Barnes & Thornburg, LLP Fort Wayne, Indiana

IN THE COURT OF APPEALS OF INDIANA

MICHAEL J. BERMES, ) ) Appellant-Defendant, ) ) vs. ) No. 35A02-1308-PL-694 ) G. K. CAMBRAY & COMPANY, INC., ) GREGORY K. CAMBRAY d/b/a CAMBRAY & ) ASSOCIATES, INC., and LAURI MASSOTH, ) ) Appellees-Plaintiffs. )

APPEAL FROM THE HUNTINGTON CIRCUIT COURT The Honorable Thomas Hakes, Judge Cause No. 35C01-1209-PL-819

March 31, 2014

MEMORANDUM DECISION – NOT FOR PUBLICATION

RILEY, Judge STATEMENT OF THE CASE

Appellant-Defendant, Michael J. Bermes (Bermes), appeals the trial court’s

judgment in favor of Appellees-Plaintiffs, G.K. Cambray & Company, Inc. (G.K.

Cambray), Gregory K. Cambray d/b/a Cambray & Associates, Inc.,1 and Lauri Massoth

(Massoth).

We affirm.

ISSUES

Bermes raises three issues on appeal, two of which we find dispositive and restate

as the following:

(1) Whether the trial court erred in determining that G.K. Cambray held a valid

mechanic’s lien (Mechanic’s Lien) against Bermes; and

(2) Whether the trial court erred in concluding that G.K. Cambray did not commit

a deceptive act because the agreement between G.K. Cambray and Bermes is

not governed by the Indiana Home Improvement Contracts Act (the HICA).

FACTS AND PROCEDURAL HISTORY

In early 2011, Bermes began constructing a new home for his family in Andrews,

Indiana. Throughout the building process, Bermes acted as his own general contractor.

When the house was near completion, Bermes’ drywall subcontractor referred Bermes to

G.K. Cambray, an Indiana corporation that sells and installs carpet and other types of

1 Bermes dismissed his counterclaim against Gregory K. Cambray at trial; thus, Cambray is not a party to this appeal.

2 flooring. On Labor Day of 2011, Bermes went to G.K. Cambray’s office showroom in

Fort Wayne. A sign on the building’s exterior identified the business as “Cambray &

Associates.” (Appellant’s App. p. 61). Massoth, an employee of G.K. Cambray, consulted

with Bermes regarding the various materials, installation, and design services Bermes

would need for his new home.

On October 17, 2011, based on Bermes’ flooring and tile selections, Massoth

submitted a written proposal of the materials and the cost estimate to Bermes, which

provided that G.K. Cambray would furnish the carpet, the hardwood flooring, and the tile

for a total cost of $24,702. The proposal included the cost of carpet installation. In order

to reduce Bermes’ expenses, Massoth recommended a subcontractor, John Clendenen

(Clendenen), to complete the “hard surface labor.” (Appellant’s App. p. 88). The parties

agreed that Massoth would coordinate the paperwork and scheduling with Clendenen, but

Bermes would contract directly with Clendenen for his installation services. On November

9, 2011, Bermes signed the proposal. Following Bermes’ approval, Massoth ordered the

necessary materials and scheduled the installation.

By approximately February 1, 2012, G.K. Cambray had installed the carpet and had

delivered the tile for Clendenen to install. On February 6, 2012, G.K. Cambray sent an

invoice to Bermes for $24,701.77. Soon thereafter, Bermes requested that G.K. Cambray

also install carpet in the lower level of his home. G.K. Cambray completed the additional

work and sent Bermes an invoice on February 28, 2012 for $3,788.37.

At the end of February 2012, Bermes moved into his newly constructed home.

Around that same time, Clendenen completed the tile installation and sent a final invoice

3 to Bermes for $3,057.30. Bermes was dissatisfied with the quality of Clendenen’s work,

and he contacted Massoth to request her assistance in resolving the issue. On March 6,

2012, Bermes met with Massoth and Clendenen at G.K. Cambray’s office. To settle the

dispute, Clendenen agreed to reduce the amount owed to $2400, which Bermes then paid,

and Clendenen signed a lien waiver in Bermes’ favor. After the meeting, Massoth

requested that Bermes remit a payment on his outstanding invoices; Bermes wrote a check

to G.K. Cambray for $15,000.

Also at this time, Massoth and Bermes discussed an issue regarding Bermes’ tile

order. Bermes had requested that Massoth eliminate some backsplash tile from the design,

and, in so doing, Massoth had also mistakenly eliminated the decorative shower tile from

the proposal. To remedy this error, Massoth agreed that if Bermes would pay for the cost

of the decorative shower tile, she would not charge a labor fee for its installation. Massoth

commissioned another subcontractor, Carl Neuhaus (Neuhaus), to install the omitted

decorative shower tile. During a meeting with Massoth and Neuhaus at his house, Bermes

requested that Neuhaus make several corrections to Clendenen’s “substandard work” as

well. (Transcript p. 84). A few months later, Bermes informed Massoth that the corrective

work was complete.

On July 9, 2012, G.K. Cambray sent Bermes an account statement reflecting a

balance of $13,490.14. The following week, on July 16, 2012, G.K. Cambray invoiced

Bermes for $3,060.34 for the additional repair work completed by Neuhaus. When Bermes

received the statement, which indicated that his payment was past due, he contacted G.K.

Cambray and requested that Massoth adjust the invoice to reflect a credit of $650 “for the

4 removal of the [glass] doors that was required for [Neuhaus] to do the work on the tile”

and to delete the past due notation. (Tr. p. 90). Because Bermes did not receive a revised

invoice, he never paid G.K. Cambray the remaining balance of $16,550.48.

On August 1, 2012, G.K. Cambray filed a Sworn Statement of Intention to Hold a

Lien (Lien Notice) with the Huntington County Recorder. The Lien Notice provided that

G.K. Cambray intended to hold a mechanic’s lien against Bermes’ real property, including

“all buildings, other structures and improvements on it or connected with it[,]” for

$16,550.48 owed for “labor and material for carpet and tile installation.” (Appellant’s App.

p. 13). In response, on August 6, 2012, Bermes served G.K. Cambray with a Notice of

Deceptive Act, alleging that G.K. Cambray had violated the HICA.

On September 25, 2012, G.K. Cambray filed a Complaint with the trial court,

seeking to foreclose on the Mechanic’s Lien and requesting that Bermes’ property be sold

to satisfy the unpaid invoices. On November 21, 2012, Bermes counterclaimed, alleging

that G.K. Cambray had engaged in poor workmanship and deceptive conduct. Namely,

Bermes averred that G.K. Cambray had failed to provide him with a written contract

pursuant to the HICA and that Massoth had misrepresented the name of the company. In

addition, Bermes asserted a claim for slander of title and sought a declaratory judgment

regarding whether G.K. Cambray was entitled to a Mechanic’s Lien on Bermes’ property.

On November 29, 2012, G.K. Cambray filed a motion to dismiss Bermes’

counterclaim for failure to state a claim under Indiana Trial rule 12(B)(6). Specifically,

G.K.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hayes v. Chapman
894 N.E.2d 1047 (Indiana Court of Appeals, 2008)
Logansport Equipment Rental, Inc. v. Transco, Inc.
755 N.E.2d 1135 (Indiana Court of Appeals, 2001)
Abbey Villas Development Corp. v. Site Contractors, Inc.
716 N.E.2d 91 (Indiana Court of Appeals, 1999)
Mullis v. Brennan
716 N.E.2d 58 (Indiana Court of Appeals, 1999)
Ford v. Culp Custom Homes, Inc.
731 N.E.2d 468 (Indiana Court of Appeals, 2000)
Imperial Insurance Restoration & Remodeling, Inc. v. Costello
965 N.E.2d 723 (Indiana Court of Appeals, 2012)
Albrecht v. C. C. Foster Lumber Co.
26 N.E. 157 (Indiana Supreme Court, 1890)
Von Tobel Corp. v. Chi-Tec Construction & Remodeling, Inc.
994 N.E.2d 1215 (Indiana Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Michael J. Bermes v. G.K. Cambray & Company, Inc., Gregory K. Cambray d/b/a Cambray & Associates, Inc., and Lauri Massoth, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michael-j-bermes-v-gk-cambray-company-inc-gregory-k-cambray-dba-indctapp-2014.