Michael B. Gaffney v. City of Richland, Mississippi

202 So. 3d 238, 2016 Miss. App. LEXIS 633
CourtCourt of Appeals of Mississippi
DecidedOctober 4, 2016
DocketNO. 2014-CA-01648-COA
StatusPublished

This text of 202 So. 3d 238 (Michael B. Gaffney v. City of Richland, Mississippi) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michael B. Gaffney v. City of Richland, Mississippi, 202 So. 3d 238, 2016 Miss. App. LEXIS 633 (Mich. Ct. App. 2016).

Opinion

LEE, C.J.,

FOR THE COURT:

FACTS AND PROCEDURAL HISTORY

I. 2002 to 2012

¶ 1. On February 27, 2002, the City of Richland issued a building permit to Mi *239 chael Gaffney to start building a house at 126 Hemlock Drive in Richland, Mississippi. The permit indicated that it would become void if work or construction did not commence within six months of the date of issuance, or if work was suspended or abandoned for a period of six months at any time after work started. After obtaining the permit, Gaffney began construction.

¶2. In a letter dated April 16, 2007— over five years after the issuance of the permit—Gaffney was notified that the building permit was void and was ordered to stop work. Jeff Sims, the building official for the City, testified that he typically received a request for an inspection prior to a builder moving on to the next phase of construction. According to Sims, he had not received such a request from Gaffney in three years. Subsequently, Gaffney applied for a second set of permits, which were issued with the same six-month provisions,

¶ 3. In a letter dated Hay 5, 2012—over ten years after the issuance of the original building permit—the City notified Gaffney that the second set of permits was void. According to Sims, Gaffney had suspended or abandoned construction again. Aggrieved, Gaffney asked to be heard by the Board of Aldermen,

II. Complaint

¶ 4. In the meantime, in November 2012, the City filed a complaint against Gaffney in the Chancery Court of Rankin County, claiming:

(1) Gaffney repeatedly failed to complete construction;
(2) Gaffney failed to maintain the property;
(3) The property constituted a danger and/or nuisance under Mississippi Code Annotated section 21-19-11 (Rev. 2015); and
(4)Gaffney breached the terms of the building permits as well as his representations and covenants to the City.

¶5. The City requested the following relief:

(1) Enjoin Gaffney to complete construction within a , period of time determined by the chancery court;
(2) In the event Gaffney failed to complete construction, authorization of demolition and removal;
(3) Reasonable attorney’s fees and costs; and
(4) Other relief to which the City may be entitled.

III. 2012 to 2014

¶ 6. Notwithstanding the filing of the complaint, on December 18, 2012, the Board passed a resolution allowing Gaff-ney to obtain new permits and complete construction by April 2, 2013. However, according to the City, Gaffney did not complete construction.

¶ 7. On April 16, 2013, the Board passed another resolution allowing Gaffney an additional sixty days to complete construction. Gaffney was issued new permits, which stated: “Per Resolution of [the] Board ... [April 16, 2013], all construction to be completed no later than [June 16, 2013] in accordance with applicable codes — No further permits shall be issued.” According to the City, Gaffney did not complete construction again. As a result, in September 2013, the City filed an amended complaint in the chancery court.

IY. August 19, 2014 Hearing

¶ 8. Because Gaffney was a pro se litigant, the chancellor granted Gaffney a standing objection to all matters at the August 19, 2014 hearing.

*240 A. Testimony

¶ 9. An inspection of Gaffney’s house took place a few days before the hearing. Sims testified that electrical extension cords and water hoses were being run from the neighboring house to Gaffney’s house. Sims also noted the following issues with Gaffney’s house: electrical issues; the ditch alongside the house was eroding into the foundation and in need of a retaining wall; an air-conditioning unit blocked egress through a window; the concrete slab lacked flooring; the door landing lacked a staircase; a leak over the dishwasher in the kitchen; broken glass on the floor; clothing in a closet and a bed leaning up against a wall, indicating Gaffney was occupying the house; and an RV outside.

¶ 10. Gaffney testified that the concrete slab would be stained; the leak over the dishwasher was from a small refrigerator sitting on the counter; and the glass on the floor was safety glass. Gaffney also testified that he had never occupied the house.

B. Ruling 1

¶ 11, The chancery court ordered Gaff-ney to complete construction no later than 5:00 p.m. on September 5, 2014. Gaffney was ordered to immediately disconnect and remove electrical extension cords and water hoses running from the neighboring property, make arrangements for a temporary power pole, and refrain from occupying the house. The chancery court also indicated that it would award attorney’s fees, provided the City submitted claims for such. Finally, Gaffney was advised

of the potential remedies and relief which the [chancery court] may impose should [Gaffney] fail to comply with the [chancery court’s] orders herein, including but not limited to granting the City the right to commence demolition ... and/or such other remedies and relief which the [chancery court] may find in order.

Y. October 8, 2014 Hearing

¶ 12. In September 2014, the City filed a motion to hold Gaffney in contempt for failing to comply with the chancery court order. The City also filed a motion for attorney’s fees and costs.

¶ 13. In early October 2014, Gaffney filed a motion to continue the hearing. Gaffney also filed a motion to dismiss and strike the City’s motion to hold him in contempt. The chancery court denied Gaff-ney’s motion to continue, and a hearing was held on October 8,2014.

¶ 14. Donald Jones, the building inspector for the City, testified that an inspection was conducted at 5:00 p.m. on September 5, 2014. Jones testified that although there had been some improvements to the house, construction was not complete. Jones stated that Gaffney removed the extension cords and water hoses and, to his knowledge, Gaffney had not occupied the house. But, according to Jones, a final inspection could not take place because no temporary power pole had been erected and there were no utilities. Jones also testified that there was still no retaining wall.

¶ 15. When the chancery court asked Gaffney if he had finished construction, Gaffney responded, “Yes, I think I have.” According to Gaffney, he tried to obtain a temporary power pole, but Entergy did not provide the power pole until a week after the September 5 inspection. And Gaffney testified that utilities were not hooked up because he had to go through the City to get them turned on.

¶ 16. At this point, the hearing was recessed, and another inspection took place. Sims returned from the inspection and tes- *241

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A-1 PALLET CO. v. City of Jackson
40 So. 3d 563 (Mississippi Supreme Court, 2010)
Heidkamper v. Odom
880 So. 2d 362 (Court of Appeals of Mississippi, 2004)
Bray v. City of Meridian
723 So. 2d 1200 (Court of Appeals of Mississippi, 1998)
Van Meter v. City of Greenwood
724 So. 2d 925 (Court of Appeals of Mississippi, 1998)
Pierce v. Pierce
132 So. 3d 553 (Mississippi Supreme Court, 2014)
Bond v. City of Moss Point
240 So. 2d 270 (Mississippi Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
202 So. 3d 238, 2016 Miss. App. LEXIS 633, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michael-b-gaffney-v-city-of-richland-mississippi-missctapp-2016.