Michael Abbas v. Dte Energy

CourtMichigan Court of Appeals
DecidedSeptember 18, 2025
Docket370668
StatusUnpublished

This text of Michael Abbas v. Dte Energy (Michael Abbas v. Dte Energy) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michael Abbas v. Dte Energy, (Mich. Ct. App. 2025).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

MICHAEL ABBAS, UNPUBLISHED September 18, 2025 Plaintiff-Appellant, 10:16 AM

v No. 370668 Wayne Circuit Court DTE ENERGY AND LECOM INC, LC No. 22-008538-NO

Defendants-Appellees, and

MICHIGAN MILLERS INSURANCE,

Defendant.

Before: CAMERON, P.J., and MURRAY and KOROBKIN, JJ.

PER CURIAM.

Plaintiff, Michael Abbas, appeals by right the trial court’s order granting defendants, DTE Energy (DTE) and Lecom, Inc. (Lecom), summary disposition under MCR 2.116(C)(10) (no dispute of material fact). Because we conclude that plaintiff has not raised a genuine issue of material fact on causation, we affirm.

I. BACKGROUND AND FACTS

DTE contracted with Lecom to upgrade crossarms—the wooden arms on the top of electrical poles—in the area outside plaintiff’s employer, Cherry Hill Motors. On the day of the incident that gave rise to this case, Lecom employee Dave Wheelihan and other crewmembers removed a transformer, or B can, from an electrical pole that serviced the business to reach the crossarms.

Wheelihan testified in his deposition that he advised plaintiff about a day before that the work would interrupt the delivery of three-phase (higher voltage) electrical service to plaintiff’s business, meaning that larger specialized equipment such as plaintiff’s air compressor would not function properly. Wheelihan further testified that plaintiff offered to completely shut off the power, but that Wheelihan did not instruct plaintiff to do so, although he told plaintiff that if

-1- plaintiff did, he would personally notify plaintiff once the work was completed. Wheelihan explained that plaintiff could choose whether to shut off the power to the air compressor or shut down power to the whole building. In contrast, plaintiff testified at his deposition that Wheelihan told him that the workers would turn off the power themselves and that there would be no power to the building at all once they began their work.

Plaintiff testified that the power stayed on, and he heard a “heavy noise,” like the sound of an earthquake or an F-16. He and the other auto shop workers looked around the building for the source, and then heard the sound of an explosion. Plaintiff then saw that the air compressor was on fire, and he went to turn off the power on the main circuit breaker, but the power would not turn off. Meanwhile, Wheelihan and his crew were completing the last phase of the work on the top of the pole when they were notified by a Cherry Hills employee on the ground that there was smoke coming out of the air compressor. At that time, according to Wheelihan, the transformer that supplied three-phase service was offline. Plaintiff explained that he then attempted to turn off the air compressor, but when he touched its handle, he was electrocuted and thrown onto a frame machine where he hit his head. His memory of exactly which component he touched was somewhat fuzzy, because he was running around trying to stop the fire. Indeed, a video capturing the incident shows the air compressor becoming engulfed in flames while plaintiff runs back and forth before going off-camera. Plaintiff alleged that because of the incident, he suffered injuries including numbness on the right side of his body and lasting neurological issues. He then filed this negligence suit against defendants.

Following the incident, DTE’s safety team inspected the air compressor and circuit box. They believed that plaintiff touched an illegally wired connection in the circuit box. After reading the incident report, Wheelihan agreed, suspecting that the cause of the incident was improper grounding of the breaker box, because if a breaker box became energized, then the current could go through the person touching it to the ground if there is no proper ground wire. He could not say how a breaker box could have become energized. Wheelihan denied that anything the crew did outside affected the equipment inside Cherry Hill Motors. Plaintiff, by contrast, testified that he believed that defendants were the cause of the electric shock because they added more power, bringing the voltage to 440. Plaintiff surmised that this was the case because of the loud earthquake-like sound that he heard.

Defendants moved in the trial court for summary disposition under MCR 2.116(C)(10), arguing that plaintiff failed to establish a genuine issue of material fact on negligence and that DTE could not be liable for the negligence of its subcontractor, Lecom. In support, defendants presented an expert report from engineer Erik Swonder, which stated that “operating a three phase motor on a single phase power supply is a known condition that results in ‘single phasing’ and overheating of the motor.” The expert concluded that the fire on the compressor was caused by the failure to shut off power to the compressor while the electrical work was being performed. Swonder also observed that photographs of the circuit boxes taken on the day of the incident showed evidence of fuses being removed from the circuit box while it was energized. He further opined that temporary disconnection of the transformer, or B can, would not energize the handle of the air compressor’s disconnect switch. Finally, Swonder concluded that “improper electrical contact with an energized live conductor inside an opened electrical enclosure” could not be excluded as the cause of plaintiff’s injury. In a separate affidavit, Swonder averred that nothing in his inspection supported plaintiff’s assertion that the voltage increased when the transformer

-2- was disconnected, and that disconnecting the transformer could not increase the voltage to 440 under fundamental principles of electrical engineering. In response, plaintiff submitted what he described as his expert’s testimony, but the trial court found that the report was inadmissible because it did not include the name of the author, the date, or a signature. Plaintiff’s attorney stated that he believed that he had filed a supplemental brief containing “the full expert report,” but the court did not see it in the record.

The trial court granted defendants’ motion, finding that there was no genuine issue of material fact on negligence because while defendants’ expert report supported defendants’ position that there was no negligence, plaintiff failed to counter that conclusion given that plaintiff’s expert report was inadmissible. This appeal followed.

II. STANDARD OF REVIEW

“This Court reviews de novo a trial court’s decision on a motion for summary disposition.” BC Tile & Marble Co v Multi Bldg Co, Inc, 288 Mich App 576, 583; 794 NW2d 76 (2010). “In making this determination, the Court reviews the entire record to determine whether defendant was entitled to summary disposition.” Maiden v Rozwood, 461 Mich 109, 120; 597 NW2d 817 (1999).

Summary disposition under MCR 2.116(C)(10) “tests the factual sufficiency of a claim.” El-Khalil v Oakwood Healthcare, Inc, 504 Mich 152, 160; 934 NW2d 665 (2019) (emphasis omitted). “In evaluating a motion for summary disposition brought under this subsection, a trial court considers affidavits, pleadings, depositions, admissions, and other evidence submitted by the parties, MCR 2.116(G)(5), in the light most favorable to the party opposing the motion.” Maiden, 461 Mich at 120. “A motion under MCR 2.116(C)(10) may only be granted when there is no genuine issue of material fact.” El-Khalil, 504 Mich at 160.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O’neal v. St John Hospital & Medical Center
791 N.W.2d 853 (Michigan Supreme Court, 2010)
Woodard v. Custer
702 N.W.2d 522 (Michigan Supreme Court, 2005)
Valcaniant v. Detroit Edison Co.
679 N.W.2d 689 (Michigan Supreme Court, 2004)
Helmus v. Department of Transportation
604 N.W.2d 793 (Michigan Court of Appeals, 2000)
Jones v. Porretta
405 N.W.2d 863 (Michigan Supreme Court, 1987)
Maiden v. Rozwood
597 N.W.2d 817 (Michigan Supreme Court, 1999)
SSC Associates Ltd. Partnership v. General Retirement System
480 N.W.2d 275 (Michigan Court of Appeals, 1991)
Skinner v. Square D Co.
516 N.W.2d 475 (Michigan Supreme Court, 1994)
Sherman v. Sea Ray Boats, Inc
649 N.W.2d 783 (Michigan Court of Appeals, 2002)
Schultz v. Consumers Power Co.
506 N.W.2d 175 (Michigan Supreme Court, 1993)
Moning v. Alfono
254 N.W.2d 759 (Michigan Supreme Court, 1977)
Locke v. Pachtman
521 N.W.2d 786 (Michigan Supreme Court, 1994)
John Pugno v. Blue Harvest Farms LLC
930 N.W.2d 393 (Michigan Court of Appeals, 2018)
BC Tile & Marble Co. v. Multi Building Co.
794 N.W.2d 76 (Michigan Court of Appeals, 2010)
Rataj v. City of Romulus
858 N.W.2d 116 (Michigan Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Michael Abbas v. Dte Energy, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michael-abbas-v-dte-energy-michctapp-2025.