MIC/CCS, Joint Venture

CourtArmed Services Board of Contract Appeals
DecidedMay 14, 2014
DocketASBCA No. 58242
StatusPublished

This text of MIC/CCS, Joint Venture (MIC/CCS, Joint Venture) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MIC/CCS, Joint Venture, (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) MIC/CCS, Joint Venture ) ASBCA No. 58242 ) Under Contract No. F42650-03-D-0010 )

APPEARANCES FOR THE APPELLANT: Richard C. Johnson, Esq. John S. Pachter, Esq. Smith Pachter Mc Whorter PLC Vienna, VA

Patrick Hendrickson, Esq. Hendrickson Law Firm South Jordan, UT

APPEARANCES FOR THE GOVERNMENT: Col Robert J. Preston II, USAF Acting Air Force Chief Trial Attorney Jeffrey M. Lowry, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE SCOTT ON APPELLANT'S MOTION FOR SUMMARY JUDGMENT

MIC/CCS, Joint Venture (MIC/CCS) has appealed under the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, from the contracting officer's (CO's) termination of Delivery Order (DO) No. 0383 under the subject contract for default. It moves for summary judgment, converting the default termination to one for convenience, on the basis that the government waived the DO's completion date and appellant was excusably delayed through the termination date. The government opposes. At appellant's request, the Board heard oral argument. For the reasons stated below we deny the motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION 1

1. On 31 March 2003, pursuant to a Simplified Acquisition of Base Engineering Requirements (SABER) solicitation, the Air Force awarded negotiated Contract No. F42650-03-D-0010, a multiple award Indefinite Delivery, Indefinite Quantity section

1 Appellant presents additional proposed facts (PF) in its redacted 14 June 2013 response to the Air Force's opposition to its motion for summary judgment (app. resp.). We have reviewed them but do not find them necessary to our resolution of the motion. 8(a) set-aside contract for design and construction services at Hill Air Force Base (AFB), Utah, and other sites, to MIC/CCS for a one-year base period with seven option years (R4, tab 1at1-6of33, Description of Work at 5).

2. The contract incorporates by reference or contains numerous Federal Acquisition Regulation (FAR) clauses, including the following:

FAR 52.211-12, LIQUIDATED DAMAGES - CONSTRUCTION (SEP 2000), which provides that if the contractor fails to complete the work in the time specified, it "shall pay liquidated damages to the Government in the amount of $162.00 for each calendar day of delay until the work is completed or accepted" (R4, tab 1at10 of33).

FAR 52.232-5, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (SEP 2002) (R4, tab 1 at 15), which provides in part that the government is to "make progress payments monthly as the work proceeds ... on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the [CO]."

FAR 52.233-1, DISPUTES (JUL 2002)-ALTERNATE I (DEC 1991) (R4, tab 1at15 of 33), which provides in part:

(i) The Contractor shall proceed diligently with performance of this contract, pending final resolution of any request for relief, claim, appeal, or action arising under or relating to the contract, and comply with any decision of the [CO].

FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984) (R4, tab 1at15), which provides that the CO is to investigate promptly after receiving notice from the contractor of alleged differing site conditions and, if there are such conditions as defined in the clause, and they cause an increase in the contractor's cost of, or time to perform, the work, an equitable contract adjustment is to be made.

FAR52.249-10,DEFAULT(FIXED-PRICECONSTRUCTION)(APR 1984)(R4, tab 1 at 15), which provides in part:

(a) If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or the separable part of the work) that has been delayed~... The Contractor and its sureties shall be liable for any damage to

2 the Government resulting from the Contractor's refusal or failure to complete the work within the specified time, whether or not the Contractor's right to proceed with the work is terminated. This liability includes any increased costs incurred by the Government in completing the work.

(b) The Contractor's right to proceed shall not be terminated nor the Contractor charged with damages under this clause, if-

( 1) The delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include-

(ii) Acts of the Government in either its sovereign or contractual capacity,

(c) If, after termination of the Contractor's right to proceed, it is determined that the Contractor was not in default, or that the delay was excusable, the rights and obligations of the parties will be the same as if the termination had been issued for the convenience of the Government.

( d) The rights and remedies of the Government in this clause are in addition to any other rights and remedies provided by law or under this contract.

DO No. 0383

3. In August 2010, 2 the Air Force issued a statement of work (SOW), as amended, for a project entitled "Re-Drill Well 7 and Repair/Reline Well 1" (R4, tab 4 at 1, 2, tab 6).

2 Unless otherwise indicated, referenced dates are the dates of emails. Despite the August 2010 SOW issuance date, the SOW of record is dated 24 October 2012. We infer that this is because it was forwarded during this litigation through a 23 October 2012 email and, when the SOW document was opened, a software function changed its date to 24 October 2012.

3 Rodney Sanders was the Air Force's SABER project manager. Only items incorporated into the SOW from the contractor's accepted proposal were to be considered part of the SOW. The project involved construction of a replacement potable water well at Hill AFB, which required the contractor to drill a replacement well within 25 feet of an existing Well #7, using only reverse rotary drilling methods and qualified subcontractors experienced in those methods. The contractor was also to fill in and cap the existing Well #7 and to construct an addition to the existing well house to enclose the replacement well. Regarding Well # 1, the contractor was to provide design specifications and to ensure that Well #1 's water quality, after the relining and repair work, would meet Utah's primary and secondary drinking water standards and that the well would no longer produce sand in quantities that would damage pumping operations. The SOW also required the contractor to obtain an airfield waiver for its drilling rig and equipment due to the project's location on a flight path and to warrant the entire installation system for one year after project completion. (R4, tab 6 at SOW)

4. MIC/CCS forwarded a draft scope of work from its drilling subcontractor, Layne Christensen Company (Layne), to Mr. Sanders on 17 September 2010 (R4, tab 19). However, on 21 September 2010, MIC/CCS advised the Air Force that it had to decline submitting a proposal because the drilling proposals it had received did not comply with the government's SOW; the quotes were qualified with unit rates for work accomplished and unit pricing for delays, standby, etc.; none of the drillers were guaranteeing water quality; and all were providing daily rates for delays, unforeseen conditions, etc. (R4, tab 21). It added:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Dcx, Inc. v. William J. Perry, Secretary of Defense
79 F.3d 132 (Federal Circuit, 1996)
WeDJ/Three C's, Inc. v. Gates
382 F. App'x 928 (Federal Circuit, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
MIC/CCS, Joint Venture, Counsel Stack Legal Research, https://law.counselstack.com/opinion/micccs-joint-venture-asbca-2014.