MIC/CCS, Joint Venture

Armed Services Board of Contract Appeals·Decided July 22, 2014·No. ASBCA No. 58023·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) MIC/CCS, Joint Venture ) ASBCA No. 58023 ) Under Contract No. F42650-03-D-0010 )

APPEARANCES FOR THE APPELLANT: Richard C. Johnson, Esq. John S. Pachter, Esq. Keeley A. McCarty, Esq. Richard H. Snyder, Esq. Smith Pachter Mc Whorter PLC Vienna, VA

Patrick Hendrickson, Esq. Hendrickson Law Firm South Jordan, UT

APPEARANCES FOR THE GOVERNMENT: Col Robert J. Preston II, USAF Acting Air Force Chief Trial Attorney Jeffrey M. Lowry, Esq. Skye Mathieson, Esq. Anna F. Kurtz, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE SCOTT ON APPELLANT'S MOTION FOR SUMMARY JUDGMENT

MIC/CCS, Joint Venture (MIC/CCS) has appealed under the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, from the deemed denial of its 29 December 2011 claim seeking payment of allegedly completed line items under Delivery Order (DO) No. 0383 under the subject contract. Appellant moves for summary judgment, alleging that it is entitled to payment for work performed prior to the DO's termination for default. The government opposes the motion. For the reasons stated below, we deny the motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On 31 March 2003, the Air Force awarded the subject multiple-award Indefinite Delivery, Indefinite Quantity Section 8(a) set-aside contract for design and construction services at Hill Air Force Base, Utah, and other sites to MIC/CCS for a one-year base period with seven option years. The contract was awarded pursuant to a Simplified Acquisition of Base Engineering Requirements (SABER) solicitation. (R4, tab 1) 2. The contract contained Federal Acquisition Regulation (FAR) 52.216-18, ORDERING (OCT 1995), which provides in part that: "(b) All [DOs] ... are subject to the terms and conditions of this contract. In the event of a conflict between a [DO] ... and this contract, the contract shall control" (R4, tab 1 at 16). The contract incorporated the following FAR clauses potentially relevant to MIC/CCS's entitlement to payment, the required quality of its work, and the prerequisites to reimbursement of its alleged stand-by costs: FAR 52.232-5, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (SEP 2002) (R4, tab 1 at 15); FAR 52.236-5' MATERIAL AND wORKMANSHIP (APR 1984) (id.); FAR 52.242-14, SUSPENSION OF WORK (APR 1984)(R4, tab 1at10); FAR 52.246-12, INSPECTION OF CONSTRUCTION (AUG 1996) (R4, tab 1 at 9); and FAR 52.246-21, wARRANTY OF CONSTRUCTION (MAR 1994) (R4, tab 1 at 15).

3. The contract also contained clause 5352.236-9005, ORDERING PROCEDURES- SABER (AFMC) (JUL 1997) (R4, tab 1 at 32), which provides in part as follows:

(c) Upon establishment of the scope of the individual requirement, the Contractor shall then prepare the proposal for accomplishment of the task.

(1) Part 1, Section C, of the Unit Price Book shall serve as the basis for establishing the value of the work to be performed on a unit price basis.

(2) Nonpriced work, if required, must be separately identified in the Contractor's proposal.

(d) Upon receipt of the Contractor's proposal, the Government will review the proposal for completeness. The Government will negotiate with the Contractor all nonpriced items, quantities for the prepriced items and performance time.

(e) [DOs] will then be issued by the [CO] .... Each [DO] will include the following information:

(3) Item number and description, quantity and unit prices for prepriced and nonpriced items and total.

(4) [DO] price, delivery or performance date.

2 The parties agree that the type of work required by the DO was "nonpriced work" and that the prices were derived from the proposal of the drilling subcontractor, Layne Christensen Company (Layne) (app. mot. at 3, ii 5; gov't opp'n at 1, ii 5).

4. In August 2010, the Air Force issued a Statement of Work (SOW), as amended, for a "Re-Drill Well 7 and Repair/Reline Well 1" project (R4, tab 4 at 1-2, tab 6). Mr. Rodney Sanders was the Air Force's SABER project manager (R4, tab 2 at 2). MIC/CCS forwarded Layne's draft scope of work to Mr. Sanders on 17 September 2010. Under the draft Layne would be responsible for repairing Well # 1 and drilling the replacement for Well #7. (R4, tab 19)

5. An internal email of 21 September 2010 noted that MIC/CCS would decline to submit a proposal because the drilling subcontractor proposals it had received did not comply with the SOW; the quotes were qualified with unit rates for work accomplished and unit pricing for delays, standby, etc.; none of the drillers were guaranteeing water quality; and all were providing daily rates for delays, unforeseen conditions, etc. (R4, tab 22 at 2). MIC/CCS stated as follows:

In order for MIC/CCS to provide a proposal, the Government would need to agree to accept the conditions and qualifications in the subcontractor's proposal, plus markups to MIC/CCS for the various unit prices and daily rates in case of delays or differing site conditions. Basically this would change the project to a unit rate fixed price contract with a not-to-exceed amount with no guarantee of performance.

(R4, tab 22 at 3) MIC/CCS forwarded the email to Mr. Sanders (R4, tab 25). MIC/CCS alleges that, because the Air Force received a copy of this email, and because it ultimately accepted MIC/CCS's proposal, the Air Force agreed that the DO was changed to a unit rate fixed-price contract.

6. Later on 21 September 2010, MIC/CCS informed CO Douglas Young and Mr. Sanders that it was "willing to turn in a number on this project" if the Air Force would acknowledge the subcontractor's conditions and qualifications and use its proposal instead of the SOW (R4, tab 22 at 1-2). MIC/CCS attached a copy of Layne's pricing proposal, which broke down the work on each well into components, with a unit price, a quantity, and a total price for each. Layne's pricing included a Loss of Fluids clause, which would compensate it at $550 per hour plus costs and a 20% markup, for all drilling fluid materials and additives used during a loss of fluids period. The proposal assumed 24/7 drilling and that well design was subject to change. (R4, tab 22 at 2 and at Layne proposal) In a subsequent email to the CO and Mr. Sanders, MIC/CCS stated that "[t]he total for the project would be $1,757,438.00[.] I just need the response and I can ... bring up the proposal" (R4, tab 21 at 1).

3 7. Mr. Sanders replied that, after discussing the project with Layne, and its drilling process, the Air Force felt comfortable with MIC/CCS's proposal, which he asked MIC/CCS to submit to the CO (R4, tab 22 at 1). MIC/CCS submitted a proposal dated 22 September 2010, which attached Layne's proposal (R4, tab 2 at 6-44).

8. MIC/CCS's proposal, marked "Preliminary Estimate," stated that it would "perform this project for the total price of$ One Million Seven Hundred Fifty Seven Thousand Four Hundred Thirtv Eight Dollars and no Cents. ($1,757,438.00)" in 300 days (R4, tab 2 at 6). It stated that its proposal was based upon Layne's proposal, not the government's SOW, including Layne's "unit rates for work accomplished and unit pricing for delays, etc. plus MIC/CCS markups" and that it incorporated all of Layne's "assumptions, exclusions, clauses, compensations, and hourly pricing to perform work" (R4, tab 2 at 13, 15).

9. Layne's proposal included tables for Well #1 and Well #7 work items, which indicated a unit of "LS," "FT," or "HR" ("lump sum," "per foot," "per hour" (app. hr. at 6, ~ 15)); a unit price; a quantity; and a total price for each line item (R4, tab 2 at 7-8).

Free access — add to your briefcase to read the full text and ask questions with AI

MIC/CCS, Joint Venture, (asbca 2014).

MIC/CCS, Joint Venture (MIC/CCS, Joint Venture) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)