Miami Valley Reg. v. Dayton Pr. and Lgt., Unpublished Decision (11-19-1999)

CourtOhio Court of Appeals
DecidedNovember 19, 1999
DocketC.A. Case No. 17652. T.C. Case No. 96-4852.
StatusUnpublished

This text of Miami Valley Reg. v. Dayton Pr. and Lgt., Unpublished Decision (11-19-1999) (Miami Valley Reg. v. Dayton Pr. and Lgt., Unpublished Decision (11-19-1999)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miami Valley Reg. v. Dayton Pr. and Lgt., Unpublished Decision (11-19-1999), (Ohio Ct. App. 1999).

Opinion

OPINION
The Miami Valley Regional Transit Authority and Cincinnati Insurance Company, hereinafter collectively referred to as "RTA," appeal from a judgment of the Montgomery County Court of Common Pleas in favor of the Dayton Power and Light Company ("DPL").

On November 18, 1994, at approximately 3:53 a.m., an automobile struck a DPL utility pole at the corner of Third and Marion Streets in Dayton, breaking it off at ground level. The pole had supported the following: a) three DPL high voltage electrical lines, identified as phases A, B, and C, each carrying 7,200 volts; b) a DPL neutral wire; and c) RTA electrical facilities. As a result of the impact, phase A and the neutral wire fell to the ground. Phases B and C remained suspended, but were sagging due to their own unsupported weight. The circuit breaker at DPL's substation detected an overcurrent on the phases and immediately cut off power to the affected circuit and the three phases.

Two DPL troubleshooters were dispatched to the scene of the accident. Upon arrival, one of the troubleshooters used spotlights to conduct a visual inspection of phases B and C from the ground and did not detect any abnormalities. Additional DPL linemen arrived to begin repairing the pole. Upon their arrival, they also looked over the sagging phases from the ground and found no abnormalities.

By 4:24 a.m., DPL had partially re-energized the suspended phases and by 7:21 a.m., the suspended phases were fully re-energized. At approximately 11:00 a.m., while DPL linemen were in the process of making repairs, phase B broke and fell onto RTA's feeder line, resulting in an explosion that destroyed a nearby RTA substation that supplied power to its trolleys in West Dayton. The parties stipulated that RTA had suffered approximately $235,000 in damages from the destruction of the substation.

After phase B broke and fell to the ground, it was inspected. Two dime-sized burns, approximately two feet apart, were visible on the top part of the phase. The diameter of the phase itself was between the sizes of a nickel and quarter. Each phase was made of seven copper strands twisted together. The burns on phase B had severed five of the seven strands of the copper. The burns would have been visible if the top part of phase B had been inspected from a bucket truck. From the ground, however, the burns on the top part of the phase were not visible.

RTA filed suit against DPL for the damage resulting to the substation alleging that DPL had failed to discharge its duty of care while repairing the power line facilities. DPL denied that it had been negligent.

The case was tried to a jury in November of 1998. At the close of all the evidence, the trial court denied the plaintiffs' oral motion for a directed verdict. The trial court also refused plaintiffs' request to instruct the jury on res ipsa loquitur and superseding causation. The jury returned a verdict in favor of DPL and the trial court entered judgment accordingly. RTA made a motion for judgment notwithstanding the verdict or alternately for a new trial, but the motion was denied by the trial court. RTA now appeals.

RTA asserts three assignments of error.

I. THE TRIAL COURT ERRED IN FAILING TO DIRECT A VERDICT IN FAVOR OF PLAINTIFFS WHEN ELECTRIC UTILITY DEFENDANT FAILED TO INSPECT AND MAINTAIN ITS HIGH VOLTAGE ELECTRIC TRANSMISSION LINE WITH THE HIGHEST DEGREE OF CARE, THEREBY VIOLATING ITS DUTY, AND CAUSING PLAINTIFFS' DAMAGES.

RTA argues that the trial court should have granted its motion for a directed verdict because DPL breached its duty of care as a matter of law when its linemen failed to utilize a bucket truck to inspect the entire circumference of phase B.

"When determining a motion for a directed verdict, the trial court must submit an essential issue to the jury if there is sufficient credible evidence to permit reasonable minds to reach different conclusions on that issue." Campbell v. Colley (1996),113 Ohio App.3d 14, 18, 680 N.E.2d 201, 203. Because a motion for a directed verdict "tests the legal sufficiency of the evidence rather than its weight or the credibility of the witnesses," it presents a question of law and the appellate court must review the trial court's ruling de novo. Id.

The duty of care that applies to an electrical utility company is well-established in Ohio:

A power company erecting and maintaining equipment, including poles and wires, upon or along a public road, for the purpose of transmitting and distributing electrical current, is bound to exercise the highest degree of care consistent with the practical operation of such business in the construction, maintenance and inspection of such equipment, and is responsible for any conduct falling short of that standard.

Phillips v. Dayton Power Light Co. (1994), 93 Ohio App.3d 111,116, 637 N.E.2d 963, 966 (quotation omitted); Fortman v. DaytonPower Light Co. (1992), 80 Ohio App.3d 525, 529,609 N.E.2d 1296, 1299.

The record reveals that a number of DPL linemen walked underneath phase B, looking at both sides of the phase to see if any abnormalities were present. There was testimony that DPL's normal practice at accident scenes was to make a visual inspection of the lines from the ground first, and then to utilize the bucket truck if any abnormalities were detected. Several veteran linemen testified that, in their experience, any abnormalities in a phase which were serious enough to pose a hazard would have been visible from the ground. We believe that reasonable minds could differ as to whether the actions of the DPL linemen constituted an inspection with the highest degree of care consistent with the practical operation of DPL's business. Thus, the trial court did not err when it overruled RTA's motion for a directed verdict.

The first assignment of error is overruled.

II. THE TRIAL COURT ERRED IN FAILING TO GRANT PLAINTIFFS A NEW TRIAL WHEN THE JURY'S VERDICT WAS AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE.

RTA argues that because the jury's verdict was against the manifest weight of the evidence, the trial court erred when it overruled RTA's motion for a new trial. In support of its argument, RTA asserts that "[t]he most favorable interpretation of the evidence cannot reasonably yield the conclusion that what DPL did was an inspection with the highest degree of care."

"[I]n ruling on a motion for new trial upon the basis of a claim that the judgment `is not sustained by sufficient evidence,' the court must weigh the evidence and pass upon the credibility of the witnesses, not in the substantially unlimited sense that such weight and credibility are passed on originally by the jury but in the more restricted sense of whether it appears to the trial court that manifest injustice has been done and that the verdict is against the manifest weight of the evidence." Atkinson v.Internatl. Technegroup, Inc. (1995), 106 Ohio App.3d 349

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Campbell v. Colley
680 N.E.2d 201 (Ohio Court of Appeals, 1996)
Clark v. Doe
695 N.E.2d 276 (Ohio Court of Appeals, 1997)
Fortman v. Dayton Power & Light Co.
609 N.E.2d 1296 (Ohio Court of Appeals, 1992)
Gayheart v. Dayton Power & Light Co.
648 N.E.2d 72 (Ohio Court of Appeals, 1994)
Phillips v. Dayton Power & Light Co.
637 N.E.2d 963 (Ohio Court of Appeals, 1994)
Atkinson v. International Technegroup, Inc.
666 N.E.2d 257 (Ohio Court of Appeals, 1995)
Hake v. George Wiedemann Brewing Co.
262 N.E.2d 703 (Ohio Supreme Court, 1970)
Rohde v. Farmer
262 N.E.2d 685 (Ohio Supreme Court, 1970)
Riley v. City of Cincinnati
348 N.E.2d 135 (Ohio Supreme Court, 1976)
Jennings Buick, Inc. v. City of Cincinnati
406 N.E.2d 1385 (Ohio Supreme Court, 1980)
Murphy v. Carrollton Manufacturing Co.
575 N.E.2d 828 (Ohio Supreme Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Miami Valley Reg. v. Dayton Pr. and Lgt., Unpublished Decision (11-19-1999), Counsel Stack Legal Research, https://law.counselstack.com/opinion/miami-valley-reg-v-dayton-pr-and-lgt-unpublished-decision-11-19-1999-ohioctapp-1999.