Metter ex rel. the Estate of Metter v. United States Army Corps of Engineers

9 F. Supp. 3d 1090, 2014 WL 1232728
CourtDistrict Court, D. Nebraska
DecidedMarch 25, 2014
DocketNos. 8:13-CV-133, 8:13-CV-134
StatusPublished
Cited by2 cases

This text of 9 F. Supp. 3d 1090 (Metter ex rel. the Estate of Metter v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering District Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metter ex rel. the Estate of Metter v. United States Army Corps of Engineers, 9 F. Supp. 3d 1090, 2014 WL 1232728 (D. Neb. 2014).

Opinion

MEMORANDUM AND ORDER

JOHN M. GERRARD, District Judge.

This matter is before the Court on the defendant’s motion to dismiss, or in the alternative, for summary judgment (case no. 8:13-ev-133, filing 13; case no. 8:13-cv-134, filing 13). The defendant has also moved to substitute the United States of America as the sole defendant. That motion will be granted and the United States will be substituted as the defendant.. For the reasons discussed below, the defendant’s motion to dismiss or for summary judgment will be granted.

STANDARD OF REVIEW

The defendant’s motion to dismiss rests upon jurisdictional grounds, and is therefore properly considered under Fed.R.Civ.P. 12(b)(1). The party asserting subject matter jurisdiction bears the burden of proof. Great Rivers Habitat Alliance v. FEMA, 615 F.3d 985, 988 (8th Cir.2010). A Rule 12(b)(1) motion can be presented as either a “facial” or a “factual” challenge. Osborn v. United States, 918 F.2d 724, 729 n. 6 (8th Cir.1990). When reviewing a facial challenge, the Court restricts itself to the face of the pleadings, and the nonmovant receives the same protections as it wpuld facing a Rule 12(b)(6) motion. Id. By contrast, when reviewing a factual challenge, the Court considers matters outside the pleadings, and the non-movant does not receive the benefit of Rule 12(b)(6) safeguards. Id. Moreover, unlike a motion for summary judgment, the Court is free to resolve disputed issues of fact. Jessie v. Potter, 516 F.3d 709, 712 (8th Cir.2008). Here, the United States has brought a factual challenge, and the Court considers matters outside the pleadings.

BACKGROUND

On October 9, 2011, Edward O. Metter was fishing from the banks of the Missouri River near the Gavins Point Dam in Cedar County, Nebraska. Case no. 8:13-cv-133, filing 1 at ¶ 5.1 With him were his son-in-[1094]*1094law and his grandson, plaintiff Justin Erickson. Case no. 8:13-cv-134, filing 1 at ¶¶ 4, 9-10. While they were fishing, a pickup truck parked on a road above the river bank came out of gear, rolled down the bank, and struck Metter, killing him. Filing 1 at ¶ 10. To understand how this tragedy occurred, one must understand the area in question and the events leading up to that day.

Gavins Point Dam sits atop the Missouri River. The impounded waters of the river above the dam created Lewis and Clark Lake, a popular recreational area. Filing 14-1 at ¶ 3. The dam, lake, and associated facilities are operated and managed by the Omaha District of the United States Army Corps of Engineers (“the Corps”). Filing 14-1 at ¶ 3. Below the spillway and leading from the dam is a 4,700-foot long protective earthen structure known as the Training Dike. The Training Dike works in conjunction with the dam to “train” the river to flow in its current channel. Filing 14-1 at ¶ 4. Running along the crest of the dike is the Training Dike Road, a two-lane asphalt road. Filing 14-1 at ¶ 6. There is a recreation area at the Training Dike which is open to the public and used for, among other things, boating access, sightseeing, hiking, and day-use fishing. Filing 14^1 at ¶ 5. The banks of the Missouri River along the Training Dike are covered with riprap (large pieces of rock or rubble), which is used to protect the shoreline and prevent erosion. Filing 14-1 at ¶8. The riprap bank is a popular spot for fishermen, particularly for catching paddlefish in the fall months. Filing 14-1 at ¶ 5.

Parking is available on the river side of the Training Dike Road. The parking areas are not striped or designated for a particular manner of parking. The first visitors of each day typically determine the day’s parking pattern, whether it be parallel, diagonal, front-in, or backing in. The Corps maintains the recreation area, the road, and the parking facilities. Filing 14-1 at ¶ 6. Most of the parking areas along the Training Dike Road are bordered by guardrails, either steel rails on wooden posts or cable guardrails. It is not known precisely when the guardrails were installed, but the Corps estimates that it was at least 30 years ago. Filing 14-1 at ¶ 7.

Due to historic flooding in May 2011, certain portions of the riprap needed to be repaired. Corps employee David A. Becker, who was the “Operations Project Manager,” was responsible for these repairs. As Project Manager, Becker was primarily responsible for all Corps activities at the dam. Filing 14-1 at ¶¶ 1, 8. In June 2011, Becker decided to remove two small sections of guardrails along the Training Dike Road to allow heavy equipment to access the river shoreline. In order to facilitate flood-related repairs, the guardrails were left down and these areas were closed to the public. At some point during the last week of September 2011, after the riprap had been repaired and inspected for stability, the areas were made open to the public, without any guardrails in place. Filing 14-1 at ¶ 8.

Earlier that summer, an inspection of the remaining guardrails had revealed that many of the wooden posts were deteriorating. Becker decided to replace the guardrail posts along the Training Dike Road, with the goal of completing the work by September 30, 2011. Filing 14-1 at ¶ 9. On August 30, 2011, the Corps contracted C.B.M.C., a Tennessee firm, to install new guard posts along 3,350 feet of the Training Dike Road. At that point, all of the guardrails (with the exception of the two sections mentioned above) were still in place. The Corps allotted 1 month for completion of the project.

On September 19, 2011, the contractor visited the worksite and advised the Corps [1095]*1095that he would return the following week to complete the project. Relying upon that assurance, and in an attempt to reduce contract costs, Gavins Point personnel removed the remaining guardrails and posts on September 28. Becker states that he did not believe this presented any danger to the public. So, no parking "restrictions or warnings were posted, and the area along the river remained open for fishing. Filing 14-1 at ¶ 11.

Unfortunately, the contractor never showed up. From September 26 to October 7, 2011, the Corps made repeated attempts to contact C.B.M.C., without success. The contract was then re-awarded to the next lowest bidder on October 26, and the guardrails were successfully replaced by November 30. Filing 14-1 at ¶ 12. ,

But on October 9, 2011, the guardrails had not yet been replaced along the Training Dike Road, where the truck that struck and killed Metter had been parked. Becker avers that, between September 28, when the guardrails were removed, and the date of the accident, nothing had occurred in the area to lead him to believe the public was in any danger. Filing 14-1 at ¶ 13.

The plaintiffs brought suit, alleging that the accident occurred as a result of the Corps’ negligence in, among other things, failing to timely replace the guardrails, failing to reasonably inspect the parking area and provide a safe parking area, and failing to warn the public. Filing 1 at ¶ 12. Plaintiff Mary Ann Metter brings suit as the personal representative for the estate of her husband, Edward O. Metter. Case no. 8:13-cv-133, filing 1 at 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heck v. Amazon.com Inc
W.D. Washington, 2025
Watson v. VA
E.D. Missouri, 2020

Cite This Page — Counsel Stack

Bluebook (online)
9 F. Supp. 3d 1090, 2014 WL 1232728, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metter-ex-rel-the-estate-of-metter-v-united-states-army-corps-of-ned-2014.