NUMBER 13-18-00039-CV
COURT OF APPEALS
THIRTEENTH DISTRICT OF TEXAS
CORPUS CHRISTI - EDINBURG
METROPOLITAN WATER COMPANY, LP, Appellant,
v.
NATHAN AUSLEY, Appellee.
On appeal from the 21st District Court of Burleson County, Texas.
MEMORANDUM OPINION Before Chief Justice Contreras and Justices Hinojosa and Tijerina Memorandum Opinion by Justice Tijerina
Appellee Nathan Charles Ausley sued appellant Metropolitan Water Company,
L.P. (Met Water) for breach of contract. Ausley and Met Water have differing
interpretations of the relevant contract, and each moved for summary judgment. The trial
court granted Ausley’s motion for summary judgment and denied Met Water’s. By its sole issue, Met Water contends that summary judgment for Ausley was improper because Met
Water timely made payment pursuant to the contract. We affirm. 1
I. BACKGROUND
On January 26, 2005, Ausley entered into two groundwater leases with Met Water
(collectively, the contract). The contract provided that Met Water would pay Ausley
certain royalty payments once production began and described a process by which any
deficiencies in royalty payments would be addressed.
On July 6, 2016, Ausley mailed Met Water notice asking Met Water to correct
royalty payment deficiencies. Met Water received this notice on July 8. Met Water issued
a check for the proper amount and deposited it in the mail on September 6. Ausley
received this payment on September 8 and claims it was two days late pursuant to a sixty-
day deadline imposed by the contract.
Thereafter, Ausley sued Met Water asserting the late payment constituted a
breach of contract. Both parties moved for traditional summary judgment, and the trial
court granted Ausley’s motion and denied Met Water’s motion. In their motions for
summary judgment, both parties agreed that payment was due by September 6, 2016.
While Met Water argued that it made payment on September 6 when it deposited payment
in the mail, Ausley argued that Met Water paid on September 8—the date Ausley received
payment. The trial court determined that Met Water’s payment was untimely and awarded
Ausley attorney’s fees and costs. It subsequently denied Met Water’s motion for new
trial. This appeal followed.
II. STANDARD OF REVIEW
1This case is before this Court on transfer from the Tenth Court of Appeals in Waco pursuant to a docket-equalization order issued by the Supreme Court of Texas. See TEX. GOV’T CODE ANN. § 73.001.
2 We review the trial court’s summary judgment de novo. See Provident Life &
Accident Ins. Co. v. Knott, 128 S.W.3d 211, 215 (Tex. 2003). Summary judgment is
proper when the movant conclusively establishes the elements of the claim. Id.; Sci.
Spectrum, Inc. v. Martinez, 941 S.W.2d 910, 911 (Tex. 1997). Here, the claim is breach
of contract, which requires proof of four elements: “(1) the existence of a valid contract;
(2) performance or tendered performance by the plaintiff; (3) breach of the contract by the
defendant; and (4) damages sustained by the plaintiff as a result of the breach.” Eaves
v. Unifund CCR Partners, 301 S.W.3d 402, 407 (Tex. App.—El Paso 2009, no pet.); Doss
v. Homecoming Fin. Network, Inc., 210 S.W.3d 706, 713 (Tex. App.—Corpus Christi–
Edinburg 2006, pet. denied). 2
When reviewing a summary judgment, we take as true all evidence favorable to
the nonmovant, and we indulge every reasonable inference and resolve any doubts in the
nonmovant’s favor. City of Keller v. Wilson, 168 S.W.3d 802, 822 (Tex. 2005). The party
moving for traditional summary judgment has the burden to show that no genuine issue
of material fact exists and that it is entitled to judgment as a matter of law. TEX. R. CIV. P.
166a(c); Nixon v. Mr. Prop. Mgmt. Co., 690 S.W.2d 546, 548 (Tex. 1985). When, as here,
both parties move for summary judgment on the same issue and the trial court grants one
motion and denies the other, we consider the summary judgment evidence presented by
both sides, determine all questions presented, and if we determine that the trial court
erred, render the judgment the trial court should have rendered. See FM Props.
Operating Co. v. City of Austin, 22 S.W.3d 868, 872 (Tex. 2000).
III. THE CONTRACT
2The issue on appeal is whether Met Water breached the contract; therefore, we will only address this element.
3 By its sole issue, Met Water contends the trial court erred by granting Ausley’s
motion for summary judgment on Ausley’s breach of contract claim. Met Water argues
that it paid on September 6, 2016 when it deposited payment in the mail—not when
Ausley received the payment—“because payment by mail was permitted by [the contract]
and because it was customary for the parties to exchange payments by mail.” Ausley
argues Met Water did not pay on time because Ausley received payment on September
8.
“Ordinarily, simply mailing a premium check before the last day for payment is not
sufficient to constitute timely payment,” but when “remittance by mail is customary or
authorized,” performance is completed when “remittance, properly addressed, is
deposited in the mail.” Am. Cas. Co. of Reading, Pa. v. Conn, 741 S.W.2d 536, 538 (Tex.
App.—Austin 1987, no writ). “[A]n oil and gas lease may expressly provide for the
payment of delay rentals by the mailing of a check, draft or other form of remittance to the
lessors.” See Corley v. Olympic Petroleum Corp., 403 S.W.2d 537 (Tex. App.—
Texarkana 1966, writ ref’d).
The provision at issue, in relevant part, provides: “If [Met Water] fails to make the
minimum payment within the sixty (60) days as specified hereinabove, then this lease
shall lapse and terminate and no longer be in force and effect.” Both parties agree the
deadline for payment was September 6, 2016, and Met Water has not identified any case
law interpreting identical language. Thus, to support its argument, Met Water relies on
the following shut-in royalty provision, unrelated to royalty payment deficiencies, in the
contract: “On or before the expiration of the six (6) consecutive month period, [Met Water]
may pay or tender by check . . . a shut-in royalty amount . . . .” According to Met Water,
4 because the contract “contemplates payment of shut-in royalties by check,” the deposit
of royalty deficiency payments by mail was therefore authorized by the contract and its
deposit of the check into the mail on September 6 was timely. We disagree.
Here, the contract does not specify the manner in which the royalty deficiency
payments should be paid or received. For comparison, in TSB Exco, Inc.
Free access — add to your briefcase to read the full text and ask questions with AI
NUMBER 13-18-00039-CV
COURT OF APPEALS
THIRTEENTH DISTRICT OF TEXAS
CORPUS CHRISTI - EDINBURG
METROPOLITAN WATER COMPANY, LP, Appellant,
v.
NATHAN AUSLEY, Appellee.
On appeal from the 21st District Court of Burleson County, Texas.
MEMORANDUM OPINION Before Chief Justice Contreras and Justices Hinojosa and Tijerina Memorandum Opinion by Justice Tijerina
Appellee Nathan Charles Ausley sued appellant Metropolitan Water Company,
L.P. (Met Water) for breach of contract. Ausley and Met Water have differing
interpretations of the relevant contract, and each moved for summary judgment. The trial
court granted Ausley’s motion for summary judgment and denied Met Water’s. By its sole issue, Met Water contends that summary judgment for Ausley was improper because Met
Water timely made payment pursuant to the contract. We affirm. 1
I. BACKGROUND
On January 26, 2005, Ausley entered into two groundwater leases with Met Water
(collectively, the contract). The contract provided that Met Water would pay Ausley
certain royalty payments once production began and described a process by which any
deficiencies in royalty payments would be addressed.
On July 6, 2016, Ausley mailed Met Water notice asking Met Water to correct
royalty payment deficiencies. Met Water received this notice on July 8. Met Water issued
a check for the proper amount and deposited it in the mail on September 6. Ausley
received this payment on September 8 and claims it was two days late pursuant to a sixty-
day deadline imposed by the contract.
Thereafter, Ausley sued Met Water asserting the late payment constituted a
breach of contract. Both parties moved for traditional summary judgment, and the trial
court granted Ausley’s motion and denied Met Water’s motion. In their motions for
summary judgment, both parties agreed that payment was due by September 6, 2016.
While Met Water argued that it made payment on September 6 when it deposited payment
in the mail, Ausley argued that Met Water paid on September 8—the date Ausley received
payment. The trial court determined that Met Water’s payment was untimely and awarded
Ausley attorney’s fees and costs. It subsequently denied Met Water’s motion for new
trial. This appeal followed.
II. STANDARD OF REVIEW
1This case is before this Court on transfer from the Tenth Court of Appeals in Waco pursuant to a docket-equalization order issued by the Supreme Court of Texas. See TEX. GOV’T CODE ANN. § 73.001.
2 We review the trial court’s summary judgment de novo. See Provident Life &
Accident Ins. Co. v. Knott, 128 S.W.3d 211, 215 (Tex. 2003). Summary judgment is
proper when the movant conclusively establishes the elements of the claim. Id.; Sci.
Spectrum, Inc. v. Martinez, 941 S.W.2d 910, 911 (Tex. 1997). Here, the claim is breach
of contract, which requires proof of four elements: “(1) the existence of a valid contract;
(2) performance or tendered performance by the plaintiff; (3) breach of the contract by the
defendant; and (4) damages sustained by the plaintiff as a result of the breach.” Eaves
v. Unifund CCR Partners, 301 S.W.3d 402, 407 (Tex. App.—El Paso 2009, no pet.); Doss
v. Homecoming Fin. Network, Inc., 210 S.W.3d 706, 713 (Tex. App.—Corpus Christi–
Edinburg 2006, pet. denied). 2
When reviewing a summary judgment, we take as true all evidence favorable to
the nonmovant, and we indulge every reasonable inference and resolve any doubts in the
nonmovant’s favor. City of Keller v. Wilson, 168 S.W.3d 802, 822 (Tex. 2005). The party
moving for traditional summary judgment has the burden to show that no genuine issue
of material fact exists and that it is entitled to judgment as a matter of law. TEX. R. CIV. P.
166a(c); Nixon v. Mr. Prop. Mgmt. Co., 690 S.W.2d 546, 548 (Tex. 1985). When, as here,
both parties move for summary judgment on the same issue and the trial court grants one
motion and denies the other, we consider the summary judgment evidence presented by
both sides, determine all questions presented, and if we determine that the trial court
erred, render the judgment the trial court should have rendered. See FM Props.
Operating Co. v. City of Austin, 22 S.W.3d 868, 872 (Tex. 2000).
III. THE CONTRACT
2The issue on appeal is whether Met Water breached the contract; therefore, we will only address this element.
3 By its sole issue, Met Water contends the trial court erred by granting Ausley’s
motion for summary judgment on Ausley’s breach of contract claim. Met Water argues
that it paid on September 6, 2016 when it deposited payment in the mail—not when
Ausley received the payment—“because payment by mail was permitted by [the contract]
and because it was customary for the parties to exchange payments by mail.” Ausley
argues Met Water did not pay on time because Ausley received payment on September
8.
“Ordinarily, simply mailing a premium check before the last day for payment is not
sufficient to constitute timely payment,” but when “remittance by mail is customary or
authorized,” performance is completed when “remittance, properly addressed, is
deposited in the mail.” Am. Cas. Co. of Reading, Pa. v. Conn, 741 S.W.2d 536, 538 (Tex.
App.—Austin 1987, no writ). “[A]n oil and gas lease may expressly provide for the
payment of delay rentals by the mailing of a check, draft or other form of remittance to the
lessors.” See Corley v. Olympic Petroleum Corp., 403 S.W.2d 537 (Tex. App.—
Texarkana 1966, writ ref’d).
The provision at issue, in relevant part, provides: “If [Met Water] fails to make the
minimum payment within the sixty (60) days as specified hereinabove, then this lease
shall lapse and terminate and no longer be in force and effect.” Both parties agree the
deadline for payment was September 6, 2016, and Met Water has not identified any case
law interpreting identical language. Thus, to support its argument, Met Water relies on
the following shut-in royalty provision, unrelated to royalty payment deficiencies, in the
contract: “On or before the expiration of the six (6) consecutive month period, [Met Water]
may pay or tender by check . . . a shut-in royalty amount . . . .” According to Met Water,
4 because the contract “contemplates payment of shut-in royalties by check,” the deposit
of royalty deficiency payments by mail was therefore authorized by the contract and its
deposit of the check into the mail on September 6 was timely. We disagree.
Here, the contract does not specify the manner in which the royalty deficiency
payments should be paid or received. For comparison, in TSB Exco, Inc. v. E.N. Smith,
III Energy Corp., the contract expressly provided that payment
may be made by check or draft of Lessee delivered or mailed to the authorized depository bank or to Lessor (at the address last known to Lessee) on or before such date for payment, and the payment or tender will be deemed made when the check or draft is so delivered or mailed.
818 S.W.2d 417, 419 (Tex. App.—Texarkana 1991, no writ). In this case, although the
contract expressly authorizes payment of shut-in royalties by check, it does not expressly
authorize shut-in royalty payments, or any other royalty payments, to be deposited by
mail as Met Water suggests. Absent language specifically authorizing depositing
payments by mail, we hold that the contract did not expressly provide for royalty
deficiencies to be timely if deposited by mail on or before the due date. See Buffalo
Pipeline Co. v. Bell, 694 S.W.2d 592, 596–97 (Tex. App.—Corpus Christi–Edinburg 1985,
writ ref’d n.r.e.) (op. on reh’g)(explaining that where the subject lease had no provision
for payment by mail and there was no established custom or course of dealing between
the parties, the lessee’s deposit of payment in the mail was not timely); see also Kingsley
Props., LP v. San Jacinto Title Servs. of Corpus Christi, LLC, 501 S.W.3d 344, 349 (Tex.
App.—Corpus Christi–Edinburg 2016, no pet.) (holding that parties to a contract are
masters of their own choices).
Next, Met Water asserts that payment by mail was customary between the parties
although “the appellate record may not directly reflect it.” For summary judgment
5 purposes, it was Met Water’s burden to establish, as a matter of law, that remittance of
royalty payments by mail was customary between it and Ausley, and that, indeed, it timely
mailed the payment pursuant to its custom. See Conn, 741 S.W.2d at 538; Pentico v.
Mad-Wayler, Inc., 964 S.W.2d 708, 718 (Tex. App.—Corpus Christi–Edinburg 1998, pet.
denied) (providing that where a note on its face does not authorize payments by mail, a
pattern of dealing may establish such authorization). After reviewing the record, we find
no evidence demonstrating remittance by mail was a customary form of payment between
the parties.
Because the contract does not expressly provide for the mailing of royalty
payments and we find no evidence in the record demonstrating that this form of dealing
was customary between the parties, Ausley conclusively established that Met Water
breached the contract by failing to timely make royalty payments. Accordingly, the trial
court properly granted summary judgment in favor of Ausley on that basis. See Knott,
128 S.W.3d at 215. We overrule Met Water’s sole issue.
IV. CONCLUSION
We affirm the judgment of the trial court.
JAIME TIJERINA, Justice
Delivered and filed the 21st day of November, 2019.