PER CURIAM:
Appellants, proceeding under the citizen suit provision of the Clean Air Act1 sued to force the closing of a municipally owned incinerator, alleging that its continued operation violated the District of Columbia’s approved implementation plan.2 The district court granted summary judgment for the defendant. Both parties filed appeals which were consolidated by order of this court. Appellant, Coalition, now seeks summary reversal of the lower court’s judgment. For the reasons discussed below, we grant the motion and remand the case to the district court.
Pursuant to the Clean Air Act the Government of the District of Columbia filed an implementation plan with the Administrator of the Environmental Protection Agency on July 2, 1972. A provision of that plan called for the closing of all large solid waste incinerators with the exception of incinerator # 5, which was given authorization to continue operation until July 4, 1973. The implementation plan was approved by the Administrator shortly after its submission on July 2, 1972.
On May 31, 1973, the Mayor asked the City Council to amend the plan in order to eliminate the required closing of the incinerator. The Council responded on the eve of the scheduled closing of incinerator # 5 by postponing it until September 4, 1973. On that day, the Council granted a second postponement until June 30, 1974. Neither of the extensions was submitted in time to receive approval from the EPA.3
Appellants filed suit against the District to enforce4 the implementation [245]*245plan of July 2, 1972, which had set the July 4, 1973, closure date. The Coalition moved for a preliminary injunction and the District moved to dismiss. The district court consolidated the hearing on the preliminary injunction with the final determination on the merits,5 and granted summary judgment for the District.6
I.
The district court acknowledged that “absent a valid revision of the plan or authorized postponement of the timetable, the Court is required to enforce the original timetable for Incinerator No. 5’s compliance with the District of Columbia Air Quality Implementation Plan.” 7 It concluded, however, that the delay of the closing of the incinerator qualified as a “revision” of the plan which did not require compliance with the stringent “postponement” provision of the statute, 42 U.S.C. § 1857c-5(f) (1970), and applicable regulations, 40 C.F.R. § 51.32 (1974).8 The Addendum to the opinion below indicates the trial judge’s view that “the controlling question of law” involved the “availability of the ‘revision’ mechanism for adjusting an implementation plan”9 — a question eliciting conflicting answers from the circuit courts and presently pending before the [246]*246Supreme Court.10 We venture no opinion on this important issue for, assuming the applicability of the revision mechanism, we find that there has been no “valid revision” of the District’s implementation plan.
The district court noted that “[a]s a revision the proposed delay has properly been submitted to the Regional Office of E.P.A. for review and approval.”11 However, at no time has EPA approved any of the delays endorsed by the City Council.12 Implicit in the lower court’s grant of summary judgment to the District was the assumption that the City Council’s adoption of the “proposed delay” alone was sufficient to effectuate the revision thereby staying the closing of the incinerator.13 Our analysis of the statute and regulations indicates that this assumption is erroneous and that EPA approval of a proposed revision is necessary to relax the implementation schedule.14
The First Circuit, in a decision relied upon by the district court, concluded that “[rjevisions are not to be considered part of a plan until approved by the Administrator.”15 This conclusion has been expressly endorsed by the Eighth and Ninth Circuits and impliedly adopted by the Second Circuit.16 Al[247]*247though the revision regulations, unlike the postponement regulations, contain no express provision directing this result,17 the requirement of EPA approval is a necessary consequence of the limited nature of the revision exception to the more stringent postponement criteria. The Administrator’s regulations prohibit resort to the revision procedures whenever the state’s proposed deferral of any portion of the control strategy “will prevent attainment or maintenance of a national standard within the time specified in such plan.” 18 This restriction reflects the limited scope of the Administrator’s discretion to utilize the revision mechanism to authorize individual variances.19 If unilateral state action served to relax its implementation schedule pending EPA approval, any state could sidestep the crucial limitations on the revision procedure and undermine the national program of air quality improvement. Under the regulations, a revision need not even be sent to EPA until 60 days after its adoption and agency review can be expected to require additional time after receipt.20 A requirement of EPA approval prior to effectuation of any proposed revision is thus essential to prevent critical, irreparable delays which the Administrator is not empowered to authorize under the less rigorous revision provisions or which do not meet the standards for revision.
In ruling on a motion for summary reversal, we must consider whether the movant has met his heavy burden of establishing “that his remedy is proper and that the merits of his claim so clearly warrant relief as to justify expedited action.”21 In this case, the movant established a prima facie case that the pertinent implementation plan, the July 2, 1972, plan, was not being adhered to by the District. Certainly when such an unrebutted showing is made, the remedy of summary reversal lies to redress an adverse judgment entered against the plaintiff.
We do not hold that the court should have granted judgment for appellants, but only that this is a live controversy which is not resolved by the City Council’s submission of proposed revisions to the EPA.
On remand the court should consider any additional factors which may have arisen during the intervening period. The fact that the District was once in violation of the Act does not necessarily [248]*248mean that it cannot cure that violation short of closing down the stationary source. Appellee has called to our attention various proposals made by the EPA to permit continued operation of the incinerator. While we do not reach the question of the validity of these proposed modifications, the lower court should consider any changes that are made in determining whether there is a violation.
II.
Free access — add to your briefcase to read the full text and ask questions with AI
PER CURIAM:
Appellants, proceeding under the citizen suit provision of the Clean Air Act1 sued to force the closing of a municipally owned incinerator, alleging that its continued operation violated the District of Columbia’s approved implementation plan.2 The district court granted summary judgment for the defendant. Both parties filed appeals which were consolidated by order of this court. Appellant, Coalition, now seeks summary reversal of the lower court’s judgment. For the reasons discussed below, we grant the motion and remand the case to the district court.
Pursuant to the Clean Air Act the Government of the District of Columbia filed an implementation plan with the Administrator of the Environmental Protection Agency on July 2, 1972. A provision of that plan called for the closing of all large solid waste incinerators with the exception of incinerator # 5, which was given authorization to continue operation until July 4, 1973. The implementation plan was approved by the Administrator shortly after its submission on July 2, 1972.
On May 31, 1973, the Mayor asked the City Council to amend the plan in order to eliminate the required closing of the incinerator. The Council responded on the eve of the scheduled closing of incinerator # 5 by postponing it until September 4, 1973. On that day, the Council granted a second postponement until June 30, 1974. Neither of the extensions was submitted in time to receive approval from the EPA.3
Appellants filed suit against the District to enforce4 the implementation [245]*245plan of July 2, 1972, which had set the July 4, 1973, closure date. The Coalition moved for a preliminary injunction and the District moved to dismiss. The district court consolidated the hearing on the preliminary injunction with the final determination on the merits,5 and granted summary judgment for the District.6
I.
The district court acknowledged that “absent a valid revision of the plan or authorized postponement of the timetable, the Court is required to enforce the original timetable for Incinerator No. 5’s compliance with the District of Columbia Air Quality Implementation Plan.” 7 It concluded, however, that the delay of the closing of the incinerator qualified as a “revision” of the plan which did not require compliance with the stringent “postponement” provision of the statute, 42 U.S.C. § 1857c-5(f) (1970), and applicable regulations, 40 C.F.R. § 51.32 (1974).8 The Addendum to the opinion below indicates the trial judge’s view that “the controlling question of law” involved the “availability of the ‘revision’ mechanism for adjusting an implementation plan”9 — a question eliciting conflicting answers from the circuit courts and presently pending before the [246]*246Supreme Court.10 We venture no opinion on this important issue for, assuming the applicability of the revision mechanism, we find that there has been no “valid revision” of the District’s implementation plan.
The district court noted that “[a]s a revision the proposed delay has properly been submitted to the Regional Office of E.P.A. for review and approval.”11 However, at no time has EPA approved any of the delays endorsed by the City Council.12 Implicit in the lower court’s grant of summary judgment to the District was the assumption that the City Council’s adoption of the “proposed delay” alone was sufficient to effectuate the revision thereby staying the closing of the incinerator.13 Our analysis of the statute and regulations indicates that this assumption is erroneous and that EPA approval of a proposed revision is necessary to relax the implementation schedule.14
The First Circuit, in a decision relied upon by the district court, concluded that “[rjevisions are not to be considered part of a plan until approved by the Administrator.”15 This conclusion has been expressly endorsed by the Eighth and Ninth Circuits and impliedly adopted by the Second Circuit.16 Al[247]*247though the revision regulations, unlike the postponement regulations, contain no express provision directing this result,17 the requirement of EPA approval is a necessary consequence of the limited nature of the revision exception to the more stringent postponement criteria. The Administrator’s regulations prohibit resort to the revision procedures whenever the state’s proposed deferral of any portion of the control strategy “will prevent attainment or maintenance of a national standard within the time specified in such plan.” 18 This restriction reflects the limited scope of the Administrator’s discretion to utilize the revision mechanism to authorize individual variances.19 If unilateral state action served to relax its implementation schedule pending EPA approval, any state could sidestep the crucial limitations on the revision procedure and undermine the national program of air quality improvement. Under the regulations, a revision need not even be sent to EPA until 60 days after its adoption and agency review can be expected to require additional time after receipt.20 A requirement of EPA approval prior to effectuation of any proposed revision is thus essential to prevent critical, irreparable delays which the Administrator is not empowered to authorize under the less rigorous revision provisions or which do not meet the standards for revision.
In ruling on a motion for summary reversal, we must consider whether the movant has met his heavy burden of establishing “that his remedy is proper and that the merits of his claim so clearly warrant relief as to justify expedited action.”21 In this case, the movant established a prima facie case that the pertinent implementation plan, the July 2, 1972, plan, was not being adhered to by the District. Certainly when such an unrebutted showing is made, the remedy of summary reversal lies to redress an adverse judgment entered against the plaintiff.
We do not hold that the court should have granted judgment for appellants, but only that this is a live controversy which is not resolved by the City Council’s submission of proposed revisions to the EPA.
On remand the court should consider any additional factors which may have arisen during the intervening period. The fact that the District was once in violation of the Act does not necessarily [248]*248mean that it cannot cure that violation short of closing down the stationary source. Appellee has called to our attention various proposals made by the EPA to permit continued operation of the incinerator. While we do not reach the question of the validity of these proposed modifications, the lower court should consider any changes that are made in determining whether there is a violation.
II.
The District has raised three contentions in opposition to this appeal: First, that insufficient notice was given by the Coalition; Second, that the Coalition lacked standing to bring this action; and Third, that the Coalition failed to join a necessary party, the Administrator.
Under the citizen suit provision of the Act, 42 U.S.C. § 1857h-2, the Coalition was required to give sixty days notice before filing suit in order to give the administrative enforcement office an opportunity to act on the alleged violation and to allow the District voluntarily to comply with the implementation plan.22 Although the Coalition originally failed to provide proper notice, it cured this defect by filing a second law suit after giving notice as required by the statute to the Administrator and the District of Columbia. This notice was given by serving copies of the complaint filed in the first suit on those parties required by statute arid regulation to receive such notice.23 The District Court consolidated the two law suits into one action and properly ruled that sufficient notice had been eiven.24
The standing argument presents no barrier to plaintiffs’ action. Under the Clean Air Act’s citizen suit provision, the general requirements for standing have been relaxed to permit suits by “any citizen.” In this way citizens are recruited to serve as private attorneys-general to facilitate enforcement of the act in the face of official inaction.25 Appellants responded to this Congressional invitation to invoke the judicial process and assert the public interest. ' The question of whether there would have been standing under this complaint had the action been for private damages is not at issue. It is clear appellants had standing under the statute to represent the public.26
The District’s last contention is that failure to join the Administrator resulted in the absence of a necessary party. This would be true only if it were necessary to sue the Administrator in order to force implementation of the plan. The citizen suit provision contemplates actions against the Administrator where he fails to perform a non-discretionary act. Alternatively, the citizen, after giving sixty days notice to the Administrator, can proceed directly against the violator. When the plaintiff elects this later course, the Administrator has the right to intervene in the suit, but he is [249]*249not required to be a participant in such litigation and his absence does not render the action infirm.
Since the district court treated the adoption of the revisions by the Council as staying the required closure despite the absence of approval by the EPA, we must reverse the judgment that has been entered. We remand for further consideration of this case in light of our opinion.
So ordered.