Metropolitan Edison Co. v. City of Reading

125 A.3d 499, 2015 Pa. Commw. LEXIS 445, 2015 WL 5974066
CourtCommonwealth Court of Pennsylvania
DecidedOctober 15, 2015
Docket2188 C.D. 2014
StatusPublished
Cited by9 cases

This text of 125 A.3d 499 (Metropolitan Edison Co. v. City of Reading) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metropolitan Edison Co. v. City of Reading, 125 A.3d 499, 2015 Pa. Commw. LEXIS 445, 2015 WL 5974066 (Pa. Ct. App. 2015).

Opinion

OPINION BY

Judge P. KEVIN BROBSON.

The City of Reading (Reading) appeals from an order of the Court of Common Pleas of Berks County (trial court), which held that Reading was not immune from liability in a suit initiated by Metropolitan Edison Company (Met-Ed). The trial court further held that Reading was negligent and awarded Met-Ed $53,000 in damages. We now reverse.

On July 7, 2009, Reading began excavating a site located on the 200 block of North 5th Street, Reading, Pennsylvania. (Reproduced Record .(R.R.) at 416a.) The goal of the excavation was to uncover Reading’s sanitary sewer main in order to conduct a repair. (Id.)' During the course of the excavation, Reading encountered an electrical duct bank 1 owned by Met-Ed. (Id. at 417a.) Reading employees observed that the duct bank was in poor condition and was unstable. (Id. at 296a-97a, 349a.) Specifically, part of the concrete encasing the duct bank had col *501 lapsed.' (M. at 332a.) Reading contacted Met-Ed’s Supervisor of Regional- Operations, Kenneth Sweitzér, to notify Met-Ed of the condition of its duct bank. (Id. at 331a.) Mr. Sweitzer contacted Met-Ed’s contractor, Allen Homan, to inspect and repair the duct bank. (Id. at 332a.) Mr. Homan completed the repair of the duct bank on July 10, 2009. (Id. at 298a.) Reading resumed its excavation work, but, on July 15, 2009, Reading employees noticed that the duct bank was falling away from the wall. (Id. at 420a.) Mr. Homan returned-to the site and found that the excavated hole was deeper and there was further erosion, but the repaired duct bank was still intact. (Id. at 298a-99a.) There was no shoring in place to prevent further erosion. (Id. at 299a.) Reading continued its excavation work, but, on July 20, 2009, the duct bank fully collapsed. (Id. at 352a.) Mr. Homan conducted an extensive repair of the duct bank, which involved the removal of the collapsed portions of the duct bank and the installation of a new duct bank. (Id. at 302a.)

Met-Ed filed a complaint with the trial court, alleging that Reading’s negligence caused the collapse of the duct bank. Reading filed a motion for summary judgment, asserting that it was immune from liability pursuant to Section 8541 of what is commonly referred to as the Political Subdivision Tort Claims Act (Act). 2 The trial court denied Reading’s motion and conducted a bench trial. During the bench trial, Met-Ed presented the testimony of Mr. Homan. Mr. Homan testified that after completing the first repair of the duct bank, he informed the Sewer Department Supervisor, John Farrier, that Reading’s excavation and repair needed to be completed as soon as possible, so that the hole could be backfilled. (Id. at 304a.) Mr. Farrier indicated that the work would be completed by the end of the week. (Id.) The excavated hole was not backfilled as of July 15, 2009, and Mr. Homan again warned Mr. Farrier that Reading’s work needed to be completed quickly. (Id. at 305a.) Mr. Homan indicated that if the hole was not promptly backfilled, “bad things” could happen. (Id.)

On October 27, 2014, the trial court issued an amended verdict in favor of MetEd and adopted Met-Ed’s proposed findings of fact and conclusions of law. The trial court issued an opinion on January 20, 2015, in which it concluded that Reading was not immune from liability. The trial court explained that Readihg’s negligent conduct created a dangerous condition of the property! After Mr. Homan’s first repair' of the duct bank, Reading was aware of the “unstable conditions of dirt and soil located underneath Met-Ed’s [duct] bank and the potential danger if the [duct] bank was not adequately supported.”' (Trial Ct. Op. at 6.) Reading had sufficient notice to install shoring and correct the dangerous conduct before the foreseeable duct bank collapse on July 20, 2009. Accordingly, Reading was not immune from liability. The trial court further held that Reading’s actions were negligent, and it awarded Met-Ed damages in the amount of $53,000. Reading appealed to this Court.

The sole issue on appeal 3 is whether Reading was immune from liabili- ’ ty in the negligence suit initiated by MetEd. “Generally, local agencies are im~ *502 mune from tort liability under Section 8541 of the ... Act.” Gibellino v. Manchester Twp., 109 A.3d 336, 342 (Pa.Cmwlth.2015). There are, however, exceptions to this immunity. See 42 Pa.C.S. § 8542. Section 8542(b)(5) of the Act, 42 Pa.GS. § 8542(b)(5), provides:

(b) Acts which may impose liability.— The following acts by a local agency or any of its employees may result in the imposition of liability on a local agency:
(5) Utility service facilities. — A dangerous condition of the facilities of steam, sewer, water, gas or electric systems owned by the local agency and located within rights-of-way, except that the claimant to recover must establish that the dangerous condition created a reasonably foreseeable risk of the kind of injury which was incurred and that the local agency had actual notice or could reasonably be charged with notice under the circumstances of the dangerous condition at a sufficient time prior to the event to have taken measures to protect against the dangerous condition.

“Because of the clear intent to insulate government from exposure to tort liability, the exceptions to immunity are to be strictly construed.” Lockwood v. City of Pittsburgh, 561 Pa. 515, 751 A.2d 1136, 1139 (2000). Under Section 8542(b)(5) of the Act, “liability depends first on the strictly legal determination that the injury was caused by a condition of the property itself, which has its origin or source in the property.” Miller v. Dep’t of Transp., 690 A.2d 818, 820-21 (Pa.Cmwlth.1997). The term right-of-way, as it relates to the exception provided in Section 8542(b)(5) of the Act, “inelude[s] the strip of land on which the local agency constructs] its utility service facilities.” Id. at 820.

Reading cites Metropolitan Edison Company v. Reading Area Water Authority, 937 A.2d 1173 (Pa.Cmwlth.2007), in support of its contention that it is immune from liability. 4 In Metropolitan Edison Company, employees of the Reading Area Water Authority (water authority) struck and damaged a Met>-Ed utility line during the course of an excavation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Metropolitan Edison, Aplt. v. City of Reading
162 A.3d 414 (Supreme Court of Pennsylvania, 2017)
Coal Tubin' PA, LLC v. Cambria County Transit Authority, R. Locher
162 A.3d 549 (Commonwealth Court of Pennsylvania, 2017)
Philadelphia Housing Authority v. J. Simmons
Commonwealth Court of Pennsylvania, 2016
D. Sobat and E. Sobat v. The Borough of Midland ~ Appeal of: E. Sobat
141 A.3d 618 (Commonwealth Court of Pennsylvania, 2016)
G. Gold v. Butler Area Sewer Authority
Commonwealth Court of Pennsylvania, 2016

Cite This Page — Counsel Stack

Bluebook (online)
125 A.3d 499, 2015 Pa. Commw. LEXIS 445, 2015 WL 5974066, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metropolitan-edison-co-v-city-of-reading-pacommwct-2015.