This text of 432 A.2d 343 (Metro. Wash. Bd., Etc. v. Public Serv. Com'n) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metro. Wash. Bd., Etc. v. Public Serv. Com'n, 432 A.2d 343 (D.C. 1981).

Opinion

432 A.2d 343 (1981)

The METROPOLITAN WASHINGTON BOARD OF TRADE, Petitioner,
v.
PUBLIC SERVICE COMMISSION OF the DISTRICT OF COLUMBIA, Respondent.
Potomac Electric Power Company, Apartment & Office Building Association, People's Counsel, Intervenors.
APARTMENT & OFFICE BUILDING ASSOCIATION OF METROPOLITAN WASHINGTON, INC., Petitioner,
v.
PUBLIC SERVICE COMMISSION OF the DISTRICT OF COLUMBIA, Respondent.
Potomac Electric Power Company, People's Counsel, Intervenors.

Nos. 79-1195, 79-1254.

District of Columbia Court of Appeals.

Argued September 3, 1980.
Decided May 20, 1981.

*345 Jerry A. Moore III, Washington, D.C., with whom Raymond R. Dickey, Washington, D.C., was on the briefs, for Metropolitan Washington Board of Trade.

Frann G. Francis, Washington, D.C., for Apartment and Office Building Association of Metropolitan Washington, Inc.

Melvin J. Washington, Asst. Corp. Counsel, Washington, D.C., with whom Judith W. Rogers, Corp. Counsel, and Richard W. Barton, Deputy Corp. Counsel, Washington, D.C., at the time the brief was filed, were on the brief, for respondent.

William Dana Shapiro, Washington, D.C., with whom Edward A. Caine, Washington, D.C., was on the briefs, for Potomac Electric Power Co.

John T. Schell, Washington, D.C., with whom Brian Lederer, Elizabeth A. Noel, and Ralph A. Simmons, Washington D.C., were on the briefs, for People's Counsel.

Onkar N. Sharma, Washington, D.C., filed briefs on behalf of the Washington Metropolitan Area Transit Authority.

Before FERREN and PRYOR, Associate Judges, and GALLAGHER[*], Associate Judge, Retired.

GALLAGHER, Associate Judge, Retired:

The Apartment and Office Building Association of Metropolitan Washington (AOBA) and the Metropolitan Washington Board of Trade (Board of Trade) bring consolidated petitions for review of the Final Opinion and Order issued by the Public Service Commission in Formal Case No. 680. In Formal Case No. 680, the Commission considered and adopted marginal cost based, time-of-day (TOD) pricing[1] for large demand customers of Potomac Electric Power Company (PEPCO).

The marginal cost based, TOD pricing system adopted by the Commission reflects a recognition that demand for electricity varies from hour to hour and from season to season and that capital costs and fuel costs generally vary with the level of demand. Marginal cost based, TOD pricing attempts to allocate costs to customers who consume electricity during peak periods, when the cost of providing electricity is high, by charging higher prices per unit of electricity during these peak periods. In theory, marginal cost based, TOD pricing should discourage consumers from using electricity during peak periods and, in so doing, should result in the conservation of energy and in the reduction of capital and fuel expenditures. The Commission, then, adopted the marginal cost based, TOD pricing system, which is challenged by petitioners in this case, in order to promote three goals: (1) rate equity, (2) maximization of efficiency in facility and resource use by electric utilities, and (3) conservation of energy. See Part IV infra.

*346 The arguments of the Board of Trade and AOBA are essentially the same and address three basic questions: (1) whether the marginal cost based, TOD ratemaking principles approved by the Commission are supported by evidence in the record sufficient to allow the Commission to consider adequately the interests of PEPCO and its customers; (2) whether the application of TOD rates at this time only to PEPCO's largest commercial customers is unjustly discriminatory; and (3) whether, during the course of the Commission's exceptions procedure, the Commission properly could consider and adopt a suggested refinement in the methodology originally adopted in the Commission's Proposed Opinion without taking additional evidence. We reject petitioners' arguments that the TOD ratemaking principles approved by the Commission are unjust, discriminatory, and without sufficient record support. We uphold the decision of the Commission.

I. Facts and Procedural Background

This appeal arises from Order No. 7034 of the Public Service Commission of the District of Columbia (PSC or Commission), the Final Opinion and Order in Formal Case No. 680. In the course of the proceedings in Formal Case No. 680, the Commission issued Order No. 7002, the Proposed Opinion and Order of the Commission, and Order No. 7034, the Final Opinion and Order.[2] These orders establish the acceptability of adopting time-of-day rates for the large commercial customers served by PEPCO. The Commission stated that their most important decision in Case No. 680 was that the "TOD rates (particularly energy charges) should generally track PEPCO's marginal costs—that is, PEPCO's cost of producing each additional kilowatt hour[3] of electricity." 31 PUR4th 219, 221 (footnote added). Orders Nos. 7002 and 7034 go on to determine on-peak and off-peak periods[4] and to establish the basic methodology to be used in designing specific TOD rates. These orders, however, did not implement the TOD ratemaking principles by establishing specific TOD rates. The Commission formulated specific TOD rates in another proceeding—Formal Case No. 715.

The Commission ordered PEPCO to install TOD meters for its large commercial customers on November 12, 1975 and allowed PEPCO until July 16, 1977 to complete a study relating to TOD pricing for large commercial customers. PEPCO installed all meters and data processing equipment required to implement TOD pricing for this class of customers. PEPCO also filed tariff proposals and supporting studies relating to the methodology for establishing TOD rates. On August 12, 1977, the Commission issued a Public Notice establishing a prehearing conference for September 15, 1977 and specifying that the tariffs filed by PEPCO would apply to customers whose maximum demand for electricity equaled or exceeded 1,000 kilowatts (kw) during at least two months of the year. The Commission then issued Order No. 5933 on October 19, 1977 specifying the parties to the case, the issues to be litigated, *347 and the procedural ground rules. The parties prefiled testimony concerning TOD ratemaking principles and specific methodologies for formulating TOD rates. Hearings for cross-examination of this testimony began on October 24, 1978 and concluded on March 27, 1979.

The Commission issued its Proposed Opinion on June 28, 1979. AOBA, the Board of Trade, and PEPCO filed exceptions to the Proposed Opinion. In response to a problem concerning the application of the TOD rate principles set forth in the Proposed Opinion raised by PEPCO during the oral argument on exceptions, interested parties held a conference on August 8, 1979 to formulate a solution to the problem identified by PEPCO.[5] On the basis of their discussions and the evidence of record before the Commission, the parties submitted a report containing a proposed modification to the Commission's TOD rate design.

On September 7, 1979, the Commission issued its Final Opinion, which essentially adopted the Proposed Opinion. 31 PUR4th 249, 251. There were some modifications including the adoption of the proposal which had emerged from the conference. AOBA and the Board of Trade filed applications for reconsideration of Order No. 7034 which the Commission denied on October 16, 1979.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Power Commission v. Hope Natural Gas Co.
320 U.S. 591 (Supreme Court, 1944)
Abbott Laboratories v. Gardner
387 U.S. 136 (Supreme Court, 1967)
Permian Basin Area Rate Cases
390 U.S. 747 (Supreme Court, 1968)
Mobil Oil Corp. v. Federal Power Commission
417 U.S. 283 (Supreme Court, 1974)
Potomac Electric Power Co. v. Public Service Commission
402 A.2d 14 (District of Columbia Court of Appeals, 1979)
Washington Public Interest Organization v. Public Service Commission
393 A.2d 71 (District of Columbia Court of Appeals, 1978)
People's Counsel v. Public Service Commission
399 A.2d 43 (District of Columbia Court of Appeals, 1979)
Apartment House Council of Metropolitan Washington, Inc. v. Public Service Commission
332 A.2d 53 (District of Columbia Court of Appeals, 1975)
Atlantic Telephone Co. v. Public Service Commission
390 A.2d 439 (District of Columbia Court of Appeals, 1978)
Goodman v. Public Service Commission
309 A.2d 97 (District of Columbia Court of Appeals, 1973)
Chesapeake & Potomac Telephone Co. v. Public Service Commission
330 A.2d 236 (District of Columbia Court of Appeals, 1974)
Metropolitan Washington Board of Trade v. Public Service Commission
432 A.2d 343 (District of Columbia Court of Appeals, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
432 A.2d 343, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metro-wash-bd-etc-v-public-serv-comn-dc-1981.