Metro Utility v. Illinois Commerce Commission

549 N.E.2d 1327, 193 Ill. App. 3d 178, 140 Ill. Dec. 455, 1990 Ill. App. LEXIS 50
CourtAppellate Court of Illinois
DecidedJanuary 19, 1990
Docket2-89-0592
StatusPublished
Cited by17 cases

This text of 549 N.E.2d 1327 (Metro Utility v. Illinois Commerce Commission) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metro Utility v. Illinois Commerce Commission, 549 N.E.2d 1327, 193 Ill. App. 3d 178, 140 Ill. Dec. 455, 1990 Ill. App. LEXIS 50 (Ill. Ct. App. 1990).

Opinion

JUSTICE INGLIS

delivered the opinion of the court:

Appellant, Metro Utility Company (Metro), is a public utility providing sewer and water service to approximately 4,000 customers in northeastern Illinois. On November 20, 1987, Metro filed with appellee, the Illinois Commerce Commission (Commission), its revised rate schedule sheets in which it proposed changes in rules, regulations and conditions of service applicable to water and sewer extensions and sewer connection fees. Specifically, Metro proposed to increase its sewer expansion fee from $200 per population equivalent (PE) to $875 per PE. A population equivalent is one person for sewage design purposes and requires 100 gallons per day of sewage treatment capacity. A single-family residence has a PE of four and requires 400 gallons per day of capacity. Thus, the current rate is $200 per PE or $800 per single-family residence which Metro proposed to increase to $875 per PE or $3,500 per single-family residence. Of the proposed $875 per PE, Metro intended to apply $475 to help offset its increased income tax liability as a result of the Tax Reform Act of 1986 and the remaining $400 to the building of sewage treatment facilities.

On November 22, 1988, the Commission issued an order which, among other things, denied Metro’s proposed rate changes and directed Metro to maintain its current rates. On May 17, 1989, the Commission issued an order on rehearing in which it affirmed its original order. Metro filed this timely appeal seeking reversal of the Commission’s decision. On appeal, Metro does not contest the Commission’s ruling denying the increase sought to offset tax liability. Rather, Metro argues that the Commission’s determination that Metro was not entitled to any increase for the purpose of building additional sewage treatment facilities was not supported by substantial evidence and, therefore, should be reversed. We disagree and affirm the order of the Commission.

Metro was formed in the early 1980s by consolidating seven smaller utility companies. The vestiges of the original companies remain as service territories now served by Metro. One such territory is the Chickasaw Hills service area. This area is serviced by two sewage treatment plants, a north plant and a south plant. The controversy in the case at bar concerns the north plant, which Metro contends is nearing its design capacity of 700,000 gallons per day and can presently only accommodate 300 new customers. An additional 500.000 gallons per day of sewage treatment capacity must be built in order to service the projected 1,500 new residential customers. Thus, the question presented is what will it cost to attain the 500.000 gallons per day either by adding that capacity to the existing north plant or building an entirely new sewage treatment plant.

At the original hearing, Metro presented one witness, Mr. Harold A. Ritke. Ritke, the president of Metro, testified that the average utility construction costs have more than doubled over the past 12 years when the current $200 connection fee was established. Ritke’s opinion was based upon the Engineering News Record, which is an engineering technical magazine that keeps records of material, labor and construction costs for general heavy construction projects. Ritke estimated that the cost of expanding the sewage treatment plant (STP) facilities for the Chickasaw Hills and Valley Water divisions is between $2.4 million and $3 million. (Valley Water is one of the seven smaller utility companies consolidated by Metro which is also reaching its design capacity.) However, Ritke later conceded that in order to even bring the Chickasaw Hills North plant up to current Environmental Protection Agency standards, it would cost an estimated $1.2 million.

A witness for the staff of the Commission (Staff), Roy A. King, rejected Ritke’s use of the Engineering News Record figures. King testified that he analyzed the historical costs of adding capacity to the treatment plants in the Chickasaw Hills area in the years 1983 through 1987 and arrived at a figure of $1.20 per gallons per day of capacity added. King stated that Metro’s annual reports to the Commission indicate that construction costs for STP capacity had increased only 10% over the past 12 years, not doubled as Ritke claimed.

Further, King testified to a telephone conversation with an employee of the Environmental Protection Agency wherein he was told that $2 per gallon per day was an appropriate figure to use. The conversation was supported by a letter which was later admitted into evidence over the objection of Metro. The letter was from Charles W. Fellman, a professional engineer employed as the manager of the facility process unit of the permit section of the Environmental Protection Agency. The letter was dated August 18, 1988, and provided “that in most instances such improvements can be made for $2.00 per gallon per day of capacity added or less.” As an example of the costs required, the letter set forth two facilities. The first was Creve Coeur, Illinois, at a cost of $1.73 per gallon per day of capacity. The second was Robinson, Illinois, at a cost of $1.33 per gallon per day of capacity.

Applying the $2-gallon-per-day figure to the 500,000-gallons-per-day additional capacity necessary to the Chickasaw Hills area, King arrived at a cost of $1 million. Subtracting a reasonable company investment of 25%' left $750,000 to be paid by new customers. Then, using Metro’s estimate of 1,500 projected new customers in the Chickasaw Hills area, King divided the $750,000 cost by 1,500 to get a required connection fee of $500 per home or $125 per PE. Thus, King concluded that the current $200 per PE connection fee, or $800 per single-family residence, would provide Metro with $200,000 more than necessary to finance the Chickasaw Hills expansion. Nonetheless, King adopted the $200-per-PE connection fee as reasonable and testified that it should not be increased.

After the hearings had concluded, the Commission denied Metro’s proposed fee increases and held that Metro had “not provided sufficient cost data to determine reliable STP expansion costs.” The Commission found that “Metro’s use of the Engineering News Record as a cost basis for new facilities [was] not supported by the actual cost figures derived from Metro, and its predecessors, as set forth in the Annual Reports to the Commission.” The Staff’s analysis of design capacity was held to be “more accurate” and “quite reasonable.” Further, the Commission found that connection fees should not be used to cure Environmental Protection Agency violations. Thus, the Commission ruled to deny Metro's proposed increases and held that the current connection fees should remain in effect.

In Metro’s motion for rehearing, Metro alleged that it had commenced a series of negotiations to purchase six acres of land approximately 3,000 feet west of the Chickasaw Hills North Plant upon which to construct an additional sewage treatment plant. Metro claimed that the negotiations had progressed further since the time of the original hearing such that Metro was better able to provide definitive cost estimates of the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stone v. Department of Human Rights
Appellate Court of Illinois, 1998
Alcequeire v. Human Rights Comm'n
Appellate Court of Illinois, 1997
Alcequeire v. Human Rights Commission
685 N.E.2d 974 (Appellate Court of Illinois, 1997)
Citizens Utility Board v. Illinois Commerce Commission
683 N.E.2d 938 (Appellate Court of Illinois, 1997)
Zunino v. Cook County Commission on Human Rights
682 N.E.2d 178 (Appellate Court of Illinois, 1997)
Zunino v. Cook County Comm'n on Human Rights
Appellate Court of Illinois, 1997
Ill. Bell Telephone v. Ill. Comm. Com'n
669 N.E.2d 919 (Appellate Court of Illinois, 1996)
City of Chicago v. Illinois Commerce Commission
666 N.E.2d 1212 (Appellate Court of Illinois, 1996)
Metro Utility Co. v. Illinois Commerce Commission
262 Ill. App. 3d 266 (Appellate Court of Illinois, 1994)
Governor's Office of Consumer Services v. Illinois Commerce Commission
607 N.E.2d 1322 (Appellate Court of Illinois, 1992)
Bong Jin Kim v. Nazarian
576 N.E.2d 427 (Appellate Court of Illinois, 1991)
Illinois Bell Telephone Co. v. Illinois Commerce Commission
561 N.E.2d 426 (Appellate Court of Illinois, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
549 N.E.2d 1327, 193 Ill. App. 3d 178, 140 Ill. Dec. 455, 1990 Ill. App. LEXIS 50, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metro-utility-v-illinois-commerce-commission-illappct-1990.