Metro Panel System Inc. v. Sordoni Skanska Construction Co.

56 Va. Cir. 399, 2001 Va. Cir. LEXIS 478
CourtNorfolk County Circuit Court
DecidedSeptember 17, 2001
DocketCase No. (Chancery) CH99-2022
StatusPublished
Cited by1 cases

This text of 56 Va. Cir. 399 (Metro Panel System Inc. v. Sordoni Skanska Construction Co.) is published on Counsel Stack Legal Research, covering Norfolk County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metro Panel System Inc. v. Sordoni Skanska Construction Co., 56 Va. Cir. 399, 2001 Va. Cir. LEXIS 478 (Va. Super. Ct. 2001).

Opinion

By Judge Charles D. Griffith, Jr.

This matter comes before the Court on a Motion for Summary Judgment made by Ladybug Concrete Specialties, Inc. (Ladybug) on July 31, 2001. Ladybug’s Motion stems from a Third-Party Bill of Complaint filed by Metro Panel Systems, Inc. (Metro) against numerous Third-Party Defendants, including Ladybug. The respective parties filed memorandums of law in support of and opposing the Motion, and arguments were made before this Court on August 15,2001. After considering the relevant facts and inferences in the light most favorable to Metro, the non-moving party, the Court holds that Ladybug’s Motion for Summary Judgment should be sustained.

This matter arose from the construction of the MacArthur Center Mall in Norfolk, Virginia. On or about November 24, 1999, Metro filed a Bill of Complaint in this Court for a breach of contract/mechanic’s lien suit against Sordoni Skanska Construction Company (Sordoni) and other defendants. In its claim against Sordoni, Metro asserted breach of contract and unjust enrichment claims and sought payment for work it allegedly completed [400]*400pursuant to the parties’ tile subcontract. (Metro’s Bill of Compl. at 14-16.) On or about January 28, 2000, Sordoni filed a counterclaim against Metro. Sordoni asserted that Metro breached the tile subcontract by not properly installing floor tiles and failing to repair and replace faulty floor tiles. (Sordoni’s Countercl. at 2-3.)

The instant matter arose from the filing of a Third-Party Motion for Judgment by Metro against Taubman MacArthur Associates, Limited Partnership, Ladybug, James Morris, and Master Setters, Inc. Metro alleged that Ladybug was hired by Sordoni to perform tile removal work in connection with tile repair at the MacArthur Mall. (Metro’s Third-Party Mot. for J. at 6.) Metro claimed that the tile removal methods employed by Ladybug were negligent and caused damage to adjacent tiles and the underlying setting beds. Id. at 7. Metro alleged that Ladybug’s negligence entitles it to contribution and/or indemnification in the event that Metro is found liable to Sordoni. Id.

On or about July 31, 2001, Ladybug filed its Motion for Summary Judgment, in which it alleges that Metro’s claim is nothing more than an attempt to recover for its disappointed economic expectations resulting from its flooring subcontract with Sordoni. (Ladybug’s Mot. for Summ. J. at 3.) It also claims that “[bjecause Metro is not in privity with Ladybug and because Metro seeks recovery of purely economic losses, Metro’s claim is barred, as a matter of law, by the economic loss doctrine.” Id. Metro argues that the economic loss rule does not apply. (Metro’s Mem. in Opp’n to Ladybug’s Mot. for Summ. J. at 2.) In support of this argument, Metro makes three assertions. First, it claims that Ladybug contractually agreed to be liable for damages caused to the work of other subcontractors. Second, Metro alleges that it is a third-party beneficiary of Ladybug’s contract with Sordoni; therefore, it is in privity with Ladybug and has a right to enforce the express and implied warranties assumed by Ladybug under its contract with Sordoni. Third, Metro claims that the economic loss rule does not prevent a subcontractor from recovering from another subcontractor who negligently causes physical harm to its property. Id.

Under Virginia Rule 2:21, summary judgment is appropriate if it appears from the pleadings, orders, and admissions that the moving party is entitled to judgment. “If it appears ... that the moving party is entitled to judgment, the court shall enter judgment in his favor.” Id. “In considering a motion for summary judgment, a court must adopt those inferences from the facts that are most favorable to the nonmoving party, unless the inferences are forced, strained, or contrary to reason.” Dickerson v. Fatehi, 253 Va. 324, 327, 484 S.E.2d 880, 882 (1997). “Summary judgment is appropriate only when there are no material facts genuinely in dispute on a dispositive issue.” Leeman v. [401]*401Troutman Builds, Inc., 260 Va. 202, 206, 530 S.E.2d 909, 911 (2000). After reviewing the complete record, including relevant facts and inferences in the light most favorable to Metro, the Court finds that there is no dispute regarding material issues of fact because Metro is barred from recovery under the economic loss rule. As such, Ladybug is entitled to summary judgment.

The first issue the Court must resolve is whether the parties are in privity of contract. Metro alleges that, under Ladybug’s subcontract with Sordoni, it contractually agreed to be responsible for alleged damages caused to Metro. (Metro’s Mem. in Opp’n to Ladybug’s Mot. for Summ. J. at 5.) Metro also argues that it is in privity with Ladybug as an intended beneficiary of the Ladybug-Sordoni subcontract. Id. at 6-8. The Court disagrees with both assertions and finds that Metro is not in privity with Ladybug.

Privity of contract is the nexus or relationship existing between two or more contracting parties. In its Third-Party Motion for Judgment, Metro states that “Ladybug was hired by Sordoni to perform certain work in connection with tile repair of the floor tile located at the MacArthur Mall, which... was installed by Metro.” (Metro’s Third-Party Mot. for J. at 6.) In September of 1997, Ladybug executed a subcontract with Sordoni. Paragraph 5.2 of the subcontract states:

In the event the Work of the Subcontractor is damaged, or should the Work of the Subcontractor be delayed or interfered with by any other Subcontractor or materials supplier on the Project, the Subcontractor and each Subcontractor or material supplier shall be directly responsible to the other, each shall look solely to the other for compensation, and the Subcontractor will not seek compensation or damages from [Sordoni] by reason thereof.

(Metro’s Mem. in Opp’n to Ladybug’s Mot. for Summ. J., Ex. 4 at 6.)

Although Metro entered into an identical subcontract with Sordoni, it was not a party to the Ladybug-Sordoni subcontract, and there was no written contract between Metro and Ladybug. Furthermore, the Court finds that the contract between Ladybug and Sordoni is not carried over to any alleged oral agreements between the parties. Therefore, Metro and Ladybug are not in privity of contract, for the provisions of the Ladybug-Sordoni agreement do not establish a contractual nexus between Ladybug and Metro.

Metro also argues that “[p]rivity exists not only among those who are a party [sic] to the contract, but also to those who are intended beneficiaries of the contract.” (Metro’s Mem. In Opp’n to Ladybug’s Mot. for Summ. J. at 5.) [402]*402In support of this argument, Metro cites Virginia Code § 55-22, which describes when a person, not a party, may sue under an instrument:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RML Corp. v. Lincoln Window Products, Inc.
67 Va. Cir. 545 (Norfolk County Circuit Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
56 Va. Cir. 399, 2001 Va. Cir. LEXIS 478, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metro-panel-system-inc-v-sordoni-skanska-construction-co-vaccnorfolk-2001.