Metro Construction Co., Inc. v. Cogun Industries, Inc.

CourtCourt of Appeals of Tennessee
DecidedJanuary 28, 1993
Docket02A01-9608-CH-00207
StatusPublished

This text of Metro Construction Co., Inc. v. Cogun Industries, Inc. (Metro Construction Co., Inc. v. Cogun Industries, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metro Construction Co., Inc. v. Cogun Industries, Inc., (Tenn. Ct. App. 1993).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE WESTERN SECTION AT JACKSON

METRO CONSTRUCTION CO., INC. ) From the Shelby County Chancery Court ) at Memphis, Tennessee Plaintiff/Appellee, ) ) The Honorable Neal Small, Chancellor vs. ) ) Shelby Chancery No. 105725-1 R.D. COGUN INDUSTRIES, INC., ) Appeal No. 02A01-9608-CH-00207 ) \ ) REVERSED AND REMANDED ) Defendant/Appellant. ) C. Hamilton Jarrett ) David A. Hughes

FILED ) ) ) Atlanta, Georgia Attorneys for Defendant/Appellant

) George D. McCrary September 4, 1997 ) Bartlett, Tennessee ) Attorney for Plaintiff/Appellee Cecil Crowson, Jr. Appellate C ourt Clerk

MEMORANDUM OPINION1

HIGHERS, J.

In this breach of contract case, Metro Construction Company, Inc. (“Plaintiff”) filed

suit against Cogun Industries, Inc. (“Defendant”) for Defendant’s alleged failure to pay

Plaintiff under the terms of the contract between Plaintiff and Defendant. The trial court

granted summary judgment in favor of Plaintiff and denied Defendant’s motion to dismiss

or, alternatively, to stay proceedings pending arbitration. Defendant appeals the judgment

of the trial court arguing that the trial court erred in granting summary judgment in favor of

Plaintiff and in not directing the case to arbitration pursuant to the arbitration clause in the

contract. For the reasons stated hereafter, we reverse the judgment of the trial court which

granted summary judgment in favor of Plaintiff, remand for entry of a stay order and direct

this case to arbitration.

FACTS

On January 28, 1993, Defendant entered into a written contract with the Whitehaven

United Pentecostal Church (“Owner”) for the construction of a $1,493,977 church building.

1 Rule 10 (Court of Ap pea ls). Mem orandum Opinion. -- (b) The Co urt, with th e concurrence of all judges participating in the case, may affirm, reverse or modify the actions of the trial court by mem orandum opinion when a formal opinion would have no precedential value. W hen a case is decided by memorandum opinion it shall be designated “MEM ORAN DUM OPINION,” shall not be published, and shall not be cited or relied on for any reason in a subsequent related case. On February 23, 1993, Defendant subcontracted a portion of the contract to Plaintiff.

Pursuant to Article 8 of the contract between Plaintiff and Defendant (the

“contract”), Plaintiff agreed to supply all labor and materials “necessary to perform a

complete finish carpentry job per the plans and specifications.” Article 12 of the contract

provided that:

Final payment . . . shall be made by the [Defendant] to the [Plaintiff] when the [Plaintiff’s] work is fully performed in accordance with the requirements of the Contract Documents. . . . If, for any cause which is not the fault of the [Plaintiff], a Certificate for Payment is not issued or the [Defendant] does not receive timely payment or does not pay the [Plaintiff] within three working days after receipt of payment from the Owner, final payment to the [Plaintiff] shall be made upon demand.

According to the affidavit of Joe Savage (“Savage”), Plaintiff’s president and

principal shareholder, and the affidavit of Bill Young (“Young”), one of Plaintiff’s

supervisor’s, Plaintiff’s construction on the project proceeded in the ordinary course until

August 24, 1993, the date Young approached Bill Russell (“Russell”), Defendant’s

superintendent, requesting that Russell call the architect so that the architect could inspect

the material on the job site and confirm that the material was appropriate for the purpose

intended before Plaintiff completed any work. On August 30, 1993, Russell advised

Young that he had met with the architect and that the architect had personally inspected

the plywood and had approved it.

Relying on Defendant’s representation, Plaintiff installed the plywood onto the

exterior of the building. Savage and Young further stated in their affidavits that Defendant

inspected Plaintiff’s work, approved Plaintiff’s application for payment in late 1994 and paid

Plaintiff for its work, with the exception of Plaintiff’s ten percent retainage fee, which

amounted to $10,916.

However, according to the affidavits of Russell and James Bareiter (“Bareiter”),

Defendant’s district manager, Defendant denied confirming to Plaintiff or to any of its

agents that the plywood materials supplied, delivered and installed by Plaintiff were in

2 accordance with contract specifications.

On February 10, 1995, Plaintiff received a letter from Defendant advising that,

according to the architect, every piece of the exterior plywood was defective and needed

to be replaced.

Owner has not paid Defendant any of the funds due for the work performed by

Plaintiff. Owner is withholding payment to Defendant based upon Owner’s contention that

the materials supplied and installed by Plaintiff do not comply with the contract

specifications.

Plaintiff filed the present action seeking payment of its ten percent retainage fee due

under the contract, which Defendant refuses to pay. Defendant, however, points our

attention to Article 6 of the contract which provides:

Any controversy or claim between the [Defendant] and the [Plaintiff] arising out of or related to this Subcontract, or the breach thereof, shall be settled by arbitration, which shall be conducted in the same manner and under the same procedure as provided in the Prime Contract with respect to claims between the Owner and the [Defendant], except that a decision by the Architect shall not be a condition precedent to arbitration. If the Prime Contract does not provide for arbitration or fails to specify the manner and procedure for arbitration, it shall be conducted in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect unless the parties mutually agree otherwise. (Emphasis added).

LAW

The three issues before this Court are as follows:

1) Whether this suit should have been dismissed or stayed and submitted to

arbitration pursuant to the arbitration clause in the contract;

2) Whether the trial court erred in granting Plaintiff’s Motion for Summary Judgment;

and

3) Whether the “Pay When Paid” clause in the contract relieves Defendant of any

duty to pay Plaintiff until Defendant receives payment from Owner.

3 Tennessee has adopted the Uniform Arbitration Act (the “Act”). T.C.A. § 29-5-

301(1980 & Supp. 1996). The Act provides that a “written agreement to submit any

existing controversy to arbitration or a provision in a written contract to submit to arbitration

any controversy thereafter arising between the parties is valid, enforceable and irrevocable

save upon such grounds as exist at law or in equity for the revocation of any contract.”

T.C.A. § 29-5-302(1980 & Supp. 1996). The Act further provides that upon application of

a party showing an agreement to arbitrate and the opposing party’s refusal to arbitrate, “the

court shall order the parties to proceed with arbitration.” T.C.A. § 29-5-303(a)(1980 &

Supp. 1996).

Plaintiff argues that this case should not be submitted to arbitration because there

is no contractual dispute between Plaintiff and Defendant. Plaintiff contends that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Metro Construction Co., Inc. v. Cogun Industries, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/metro-construction-co-inc-v-cogun-industries-inc-tennctapp-1993.