Metaal Transport B v. v. Greenwich Metals, No. Cv 96 0150631 (Feb. 8, 1999)

1999 Conn. Super. Ct. 1471
CourtConnecticut Superior Court
DecidedFebruary 8, 1999
DocketNo. CV 96 0150631
StatusUnpublished

This text of 1999 Conn. Super. Ct. 1471 (Metaal Transport B v. v. Greenwich Metals, No. Cv 96 0150631 (Feb. 8, 1999)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metaal Transport B v. v. Greenwich Metals, No. Cv 96 0150631 (Feb. 8, 1999), 1999 Conn. Super. Ct. 1471 (Colo. Ct. App. 1999).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
This case was brought by the plaintiff, Metaal Transport B.V., a warehouser and freight forwarder in the Netherlands, against the defendant, Greenwich Metals, Inc., the owner of scrap brass coils. The plaintiff alleges in its complaint that on September 28, 1994, it entered into a written contract with the defendant and agreed to ship to the United States the defendant's brass coils, and that the defendant refuses to pay the shipping cost of $16,795.

The defendant admitted that the plaintiff shipped the brass coils to this country, but denied that any money was due to the plaintiff. The defendant also asserted four special defenses. The first defense asserts that the plaintiff negligently, and in breach of its contract with the defendant, mishandled the loading of defendant's 200 metric tons of brass coils in such a fashion as to damage these coils. It is further alleged that this damage necessitated repairs to the coils and additional shipping costs. In the second its contract with the defendant, mishandled the loading of defendant's 200 metric tons of brass coils in such a fashion as to damage these coils. It is further alleged that this damage necessitated repairs to the coils and additional shipping costs. In the second special defense, the defendant alleges that its contract required the plaintiff to load and ship defendant's brass coils so that they could be unloaded from a cargo ship by a CT Page 1472 forklift, but that this became impossible and that the defendant spent approximately $43,450 to offload the coils. In the third special defense, the defendant contends that this dispute should be resolved through arbitration pursuant to the "Dutch Forwarding Conditions." In the fourth special defense, the defendant argues that the claim by the plaintiff is "time-barred" by the Dutch Forwarding Conditions.

The defendant also filed a counterclaim with three counts. In the first count, the defendant alleges that the plaintiff breached the express contract with the defendant because the coils could not be offloaded by forklift as agreed but rather required an extra $43,453 to unload. In the second count of its counterclaim, the defendant contends that the plaintiff breached an implied contract that the coils could be offloaded with a forklift, which proved impossible and resulted in an additional cost of $43,453 to offload these items. The third count claims that the plaintiff's breach of an express and implied contract also constitutes negligence.

The plaintiff filed two special defenses to the counterclaim. These defenses allege that it is not responsible to the defendant for any alleged damages, and that the counterclaim by the defendant is time-barred by virtue of the Dutch Forwarding Conditions "which govern the transaction."

The case was referred to Attorney Frank W. LiVolsi, Jr., an attorney trial referee, in accordance with General Statutes §52-434 (a) and Practice Book § 19-2, formerly § 429. The attorney referee conducted a trial and then submitted a report pursuant to Practice Book § 19-4, formerly § 430A. The referee made the following findings of fact (1) the plaintiff and the defendant entered in into a written contract for the shipment of defendant's scrap brass coils from the plaintiff's warehouse in Rotterdam to a consignee in Belleforte, Pennsylvania; (2) the plaintiff loaded the coils in eleven upright shipping containers but the company that first received the coils was not able to unload the containers from the ship; (4) the goods were then offloaded by another transportation company and delivered to the ultimate destination; (5) the defendant received the full contract price for the scrap metal coils; (6) witnesses testified that the brass coils had been improperly loaded by the plaintiff, which caused the coils to be one mass of material upon arriving in this country, thus preventing unloading in the normal, conventional manner. CT Page 1473

The attorney trial referee concluded, on the basis of the above findings of fact, that: (1) the defendant incurred extra costs to unload the brass coils; (2) the Dutch Forwarding Conditions did not apply to this transaction as the plaintiff submitted itself to the jurisdiction of this court by bringing suit against the defendant in this court; (3) judgment should enter in favor of the plaintiff for $16,795, the amount of the contract with the defendant; (4) judgment should enter in favor of the defendant on its counterclaim in the amount of $36,190.45; and (5) the judgments should not include interest or attorney's fees.

As authorized by Practice Book § 19-12, formerly § 438, the defendant moved to correct1 the referee's report as follows: (1) the report should include a finding that the plaintiff agreed to load the brass coils in a careful manner but loaded them so that they became loose and unraveled; (2) because of the delay in unloading the scrap brass coils the defendant incurred two additional months of carrying costs including interest in the amount of $5,826; and (3) the referee should recommend that judgment enter only for the defendant on its counterclaim after setting off the amount due the plaintiff on its complaint.

In response to the motion to correct filed by the defendant, the attorney trial referee declined to change his recommendations. The referee did, however, comment on each item of the defendant's motion to correct and his responses can be summarized as follows: (1) the referee agreed that the defendant had been damaged by improper loading of the scrap brass coils by the plaintiff, and no further clarification on this point was needed; (2) the referee agreed that the improper loading had caused some delay in shipping the goods to the consignee; and (3) the referee could not recommend an award for carrying costs as the defendant's witness on this subject was unable to specify any such loss with a reasonable degree of probability.

In accordance with Practice Book 19-13, formerly § 439, the defendant then filed exceptions to the referee's report.2 The exceptions filed by the defendant reiterate its contention that because the recommended award to the defendant exceeds the recommended award to the plaintiff on its complaint, only one judgment should enter in favor of the defendant, not two judgments, one for the plaintiff for $16,795, and a judgment for CT Page 1474 the defendant for $36,190. The defendant argues that the smaller award should be off-set against the larger award and one judgment enter for the defendant for $19,395. The defendant contends that the plaintiff may well collect the full amount of its judgment, whereas the defendant may have difficulty in obtaining the full amount of its judgment of $36,190. Therefore, according to the defendant, there should be one judgment in its favor including obviously an off-set for the amount of the plaintiff's judgment.

This court's scope of review of an attorney trial referee's report was reiterated by the Supreme Court in Elgar v. Elgar,238 Conn. 839, 679 A.2d 937 (1996). There, the court held that, "[a] reviewing authority may not substitute its findings for those of the trier of the facts. This principle applies no matter whether the reviewing authority is the Supreme Court . . . the Appellate Court . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Elgar v. Elgar
679 A.2d 937 (Supreme Court of Connecticut, 1996)
Rostenberg-Doern Co. v. Weiner
552 A.2d 827 (Connecticut Appellate Court, 1989)
Thermoglaze, Inc. v. Morningside Gardens Co.
583 A.2d 1331 (Connecticut Appellate Court, 1991)
Romano v. City of Derby
681 A.2d 387 (Connecticut Appellate Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
1999 Conn. Super. Ct. 1471, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metaal-transport-b-v-v-greenwich-metals-no-cv-96-0150631-feb-8-1999-connsuperct-1999.