Merritt v. Anderson, Ca2008-04-010 (4-13-2009)

2009 Ohio 1730
CourtOhio Court of Appeals
DecidedApril 13, 2009
DocketNo. CA2008-04-010.
StatusPublished
Cited by1 cases

This text of 2009 Ohio 1730 (Merritt v. Anderson, Ca2008-04-010 (4-13-2009)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merritt v. Anderson, Ca2008-04-010 (4-13-2009), 2009 Ohio 1730 (Ohio Ct. App. 2009).

Opinion

OPINION
{¶ 1} Plaintiff-appellant, Phil Merritt d.b.a. Phil Merritt Construction, appeals a decision of the Fayette County Court of Common Pleas, awarding him $469.50 on his breach of contract claim against defendants-appellees, Trent Anderson and Jannell Anderson. We reverse.

{¶ 2} On March 25, 2005, Trent Anderson and his wife, Jannell Anderson, entered into a contract with Phil Merritt and his company, Phil Merritt Construction. Under the contract, Merritt agreed to construct a single family residence for the Andersons for $183,900, with the amount to be paid in four equal installments or "draws" of $45,975. Merritt received the first three draws without objection. In October 2005, Merritt told the Andersons that he could not complete the contract without receiving a portion of the final draw. With the Andersons' approval, their lender released an additional $22,987.50 to Merritt.

{¶ 3} After receiving this partial payment, Merritt worked on the project until late March or early April of 2006, at which time Merritt presented the Andersons with a "Final Draw Evaluation." On April 14, 2006, Merritt tried to obtain a "certificate of occupancy" for the residence but was told by Fayette County Building Inspector Jay Myers that the Andersons had filed a complaint against him, alleging that he failed to place black felt paper under the roof's shingles. Myers told Merritt that a certificate of occupancy would not be issued for the residence until this issue was resolved.

{¶ 4} However, on April 19, 2006, the Andersons obtained a certificate of occupancy from Fayette County's Chief Building Official, Steve Rivera, who determined that the problem with the roof was insufficient to prevent issuance of a certificate of occupancy. The Andersons moved into the residence shortly thereafter. *Page 3

{¶ 5} Sometime after the Andersons moved into the residence, Merritt sought to return to the premises with his construction crew to fix the problem with the roof, but the Andersons refused to allow him to do so. Around this time, the Andersons, through their attorney, sent Merritt a letter, dated April 26, 2006, wherein they advised Merritt that they were terminating the parties' construction contract "based upon your breach of failure to perform [sic]." The letter instructed Merritt not to enter upon their premises "or criminal charges may ensue." Merritt subsequently presented the Andersons with a final bill of $25,932.50, which the Andersons refused to pay.

{¶ 6} On July 18, 2006, Merritt filed a complaint against the Andersons in the Fayette County Court of Common Pleas, alleging breach of contract, for which he sought compensatory and punitive damages. The Andersons filed a counterclaim, alleging Merritt failed to perform his construction duties in a workmanlike manner.

{¶ 7} In May 2007, a trial was held over two separate days on the parties' claims. On January 23, 2008, the trial court issued a decision finding that Merritt breached the parties' construction agreement by, among other things, failing to perform in a workmanlike manner. The trial court found that the Andersons were entitled to $15,987 to replace their roof as a result of the lack of black felt paper, and $3,496 to increase the amount of insulation in the attic to the amount required under the parties' contract, for a total damages award of $19,483. The trial court then subtracted this amount from the $19,952.50 that the trial court found Merritt was due on the remaining half of the fourth draw, 1 thereby leaving him with a net judgment of $469.50.2 *Page 4

{¶ 8} Merritt now appeals the trial court's decision and assigns the following as error:

{¶ 9} "THE TRIAL COURT ERRED AS A MATTER OF LAW TO THE PREJUDICE OF APPELLANT BY AWARDING APPELLEES DAMAGES OF $19,483.00 ON THEIR COUNTERCLAIM AGAINST APPELLANT FOR BREACH OF CONTRACT."

{¶ 10} Merritt first argues that he was deprived of a "fair disposition" of his case because it took the trial court nearly eight months to issue a decision in this matter. We find this argument unpersuasive.

{¶ 11} R.C. 2701.02 states in pertinent part:

{¶ 12} "[W]hen submitted to a court * * * on final trial on the issues joined, a cause begun in a court of record shall be determined and adjudicated within thirty days after such submission."

{¶ 13} The 30-day time limit in R.C. 2701.02, while binding on the conscience of a trial court, is merely directory and not mandatory, and therefore, a trial court's failure to observe the 30-day time limit does not deprive the court of jurisdiction to rule on the matter. SeeKyes v. Pennsylvania RR. Co. (1952), 158 Ohio St. 362, 367-368, paragraph seven of the syllabus (interpreting G.C. 1685, the predecessor statute to R.C. 2701.02). See, also, Knox v. Knox (1986),26 Ohio App.3d 17, 20 (a party who has submitted his case to the court should not be required to sue the judge in mandamus to force a decision since trial judges should render their decisions in a timely fashion).

{¶ 14} This court has stated that "based on R.C. 2701.02, [a trial court] should attempt to issue a decision within a reasonable time after submission taking into *Page 5 consideration its caseload, the nature of the dispute, and the difficulty of the issues." Parker v. Slivinski (June 16, 1986), Madison App. No. CA85-03-008, at p. 2.

{¶ 15} There is nothing in the record to show that the trial court's delay in deciding this case was intentional, nor is there any indication that Merritt suffered any harm, injury, or prejudice as a result of that delay. Therefore, the delay did not amount to reversible error. See id., and see, generally, Buchholz v. West Chester Dental Group, Butler App. No. CA2007-11-292, 2008-Ohio-5299, ¶ 32 (dentist failed to demonstrate that he suffered any harm, injury, or prejudice as a result of a five-month delay in arbitrator's decision, and therefore, delay was not unreasonable).

{¶ 16} In his chief argument under this assignment of error, Merritt contends that since the Andersons prevented him from remedying any alleged defect in their residence, as the parties' contract permits him to do, the trial court erred in awarding the Andersons $19,483 on their counterclaim against him.

{¶ 17} The parties' construction agreement contains a provision allowing Merritt to remedy any defect in the residence upon receiving timely notice thereof. It is undisputed that the Andersons failed to provide Merritt with an opportunity to do so. However, the trial court found that the Andersons were relieved of that contractual duty because Merritt breached the parties' contract by, among other things, failing to perform his construction duties in a workmanlike manner. As a result, the trial court found that the Andersons were justified in unilaterally terminating the parties' agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patrick v. Dixie Imports, Inc.
2017 Ohio 9093 (Ohio Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2009 Ohio 1730, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merritt-v-anderson-ca2008-04-010-4-13-2009-ohioctapp-2009.