Merriman v. Sandeen

267 N.W.2d 714, 24 U.C.C. Rep. Serv. (West) 718, 1978 Minn. LEXIS 1301
CourtSupreme Court of Minnesota
DecidedMarch 31, 1978
Docket47730, 47754
StatusPublished
Cited by11 cases

This text of 267 N.W.2d 714 (Merriman v. Sandeen) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merriman v. Sandeen, 267 N.W.2d 714, 24 U.C.C. Rep. Serv. (West) 718, 1978 Minn. LEXIS 1301 (Mich. 1978).

Opinion

YETKA, Justice.

This is an appeal by plaintiff from an order denying motions for amended findings of fact, conclusions of law, and order for judgment or a new trial. The district court sitting without a jury determined that plaintiff’s tender of a check which was dishonored by the drawee bank caused the lapse of the option to purchase defendants’ land. Plaintiff originally sued for specific performance. With the consent of defendants, a claim for compensatory damages was added. At trial plaintiff dropped his claim for specific performance. Because the trial court found that the option had lapsed, it made no determination of damages. We affirm.

On June 1, 1971, defendants entered an option agreement concerning 282 acres of land which they owned in Washington County. The contract was with Property Underwriters, Inc., a corporation owned by plaintiff. Property Underwriters assigned its interest to the Pine Springs Limited Partnership. Macro, Inc., of which plaintiff is the president, was the general partner of Pine Springs Limited Partnership, and defendant Winstort Sandeen was one of the limited partners. In 1972 the agreement was amended and in 1974, when the partnership dissolved, the interest in the option was purportedly assigned to plaintiff.

The contract 1 granted the option holder the right to purchase defendants’ land for $797,500. In order to maintain the right to purchase, the option holder was required to make periodic payments which would be applied to the ultimate purchase price. The payments consisted of a $5,000 payment June 1, 1971, a $30,000 payment on August 1, 1971, and a $10,000 each year thereafter on August 1, until 1975. These payments were to be accompanied by notice of intent to renew. The payments could, according to the contract, be made by check. The original contract dated June 1, 1971, also contained the following clause:

“Buyer shall perform the conditions and comply with the terms of this option, all within the times above specified and a failure to give such notice and comply with the terms and perform the conditions hereof (except as hereinafter provided) within the times specified, shall terminate this option, and all rights thereunder, without further act or notice whatsoever, time being of the essence of this agreement.” 2 (Italics supplied.)

The 1972 amendment also provided that the option could be extended for an additional 5 years. The 5-year extension would have required a payment of $100,000 on August 1, 1976, in addition to continued annual payments of $10,000.

Between 1971 and July 1975, the option was renewed on a yearly basis; a total of $65,000 was paid to defendants. The payments were each made by check from plaintiff or his predecessors in interest. Each check was deposited in a bank where Mr. Sandeen maintained a personal account.

*716 In 1974 plaintiff requested an extension of the August 1,1974 payment date because of inability to raise the funds. Mr. Sandeen testified that he insisted the check be timely tendered. On July 22, 1975, when a waiver or renegotiation was requested, Mr. Sandeen informed plaintiff and his attorney that he insisted on timely payment of the 1975 $10,000 installment. 3

On July 31, 1975, plaintiff deposited $9,900 in his checking account in the Summit State Bank of Bloomington. The deposit consisted of checks which were collected from former members of the Pine Springs Limited Partnership. The deposit slips for July 31, and Aug. 1, 1975, were marked “hold for 3 days.” On August 1, 1975, an additional $12,000 was deposited, bringing the stated account balance to over $22,000. On July 31, 1975, Mr. Sandeen received from plaintiff a certified letter and an uncertified personal check for $10,000 drawn on Summit State Bank in Blooming-ton, Minnesota. Plaintiff spoke to Mr. San-deen that afternoon and Sandeen acknowledged receipt of the check.

On Friday, August 1, 1975, Mr. Sandeen took the check to Summit State Bank in Bloomington and presented it for payment. The bank refused payment. Although the check was marked “insufficient funds,” the account showed a balance greater than $10,-000 on August 1, 1975. Apparently Mr. Sandeen was told both that the check was drawn on “insufficient funds” and that it was drawn on “uncollected funds.”

A bank officer from Summit State Bank testified that the check would have been honored had it been deposited in Mr. San-deen’s Stillwater bank and taken several days to process. He also testified that by that time the funds represented by the checks on deposit would have been collected. He was clear that, although the check could have been paid, the bank would not honor it until the funds represented by the checks on deposit had been collected.

Mr. Sandeen testified that he felt a sense of relief when the option lapsed. Sandeen returned the check to his attorney for return to plaintiff by registered mail. Plaintiff received the check on August 4, 1975 and went to Summit State Bank for an explanation. He then procured a certified check for $10,000 which was delivered to defendants’ attorney on August 5, 1975. The check was refused and returned to plaintiff. Defendants have refused all subsequent retenders of $10,000.

The issue on appeal is: Was the'tender by plaintiff of a $10,000 check adequate to extend the option agreement where the check was dishonored on presentment to the drawee bank? 4

Plaintiff argues in the alternative that his tender of the $10,000 check was adequate to extend the contract; that equitable principles excuse any untimeliness; and that the trial court’s decision was unconscionable and inequitable. Defendants argue that the dishonor of the check rendered plaintiff’s performance inadequate and by its terms the option contract lapsed.

1. Standard of review. Although plaintiff’s initial brief implies that this court should apply the “clearly erroneous” standard to the trial court’s findings of fact, his reply brief abandons that line of argument and urges that this court review what are essentially conclusions of law. The trial court’s findings of fact would support the conclusion that plaintiff’s tender of performance failed and the option lapsed. The trial court did not, however, state this as a conclusion of law, but expressed it explicitly in the memorandum accompanying its findings of fact, conclusions of law, and order for judgment. 5 There is no serious argument to be made regarding the *717 findings actually made by the trial court. They are amply supported by the evidence as plaintiff indirectly recognizes. The court found, at least by implication, that there was no intent of the par-ties to vary the literal terms of the contract. It also expressly found that no course of dealing or other agreement required defendant to deposit checks in his own bank.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Skjefte
428 N.W.2d 91 (Court of Appeals of Minnesota, 1988)
State Ex Rel. Crow Wing Environment Protection Ass'n v. City of Breezy Point
394 N.W.2d 592 (Court of Appeals of Minnesota, 1986)
St. Paul Fire & Marine Insurance Co. v. Sparrow
378 N.W.2d 12 (Court of Appeals of Minnesota, 1985)
Ward v. Federal Kemper Insurance
489 A.2d 91 (Court of Special Appeals of Maryland, 1985)
Gilchrist v. Perl
363 N.W.2d 904 (Court of Appeals of Minnesota, 1985)
Sieren v. American Family Financial Services of Wisconsin, Inc.
356 N.W.2d 408 (Court of Appeals of Minnesota, 1984)
Johnson Motor Co., Inc. v. Cue
352 N.W.2d 114 (Court of Appeals of Minnesota, 1984)
Schafer v. Commissioner of Public Safety
348 N.W.2d 365 (Court of Appeals of Minnesota, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
267 N.W.2d 714, 24 U.C.C. Rep. Serv. (West) 718, 1978 Minn. LEXIS 1301, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merriman-v-sandeen-minn-1978.