Meritxell Pons Torres v. A&P Air Conditioning Corporation

CourtDistrict Court of Appeal of Florida
DecidedMarch 4, 2026
Docket3D2024-1802
StatusPublished

This text of Meritxell Pons Torres v. A&P Air Conditioning Corporation (Meritxell Pons Torres v. A&P Air Conditioning Corporation) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meritxell Pons Torres v. A&P Air Conditioning Corporation, (Fla. Ct. App. 2026).

Opinion

Third District Court of Appeal State of Florida

Opinion filed March 4, 2026. Not final until disposition of timely filed motion for rehearing.

________________

No. 3D24-1802 Lower Tribunal No. 21-24920-CC-05 ________________

Meritxell Pons Torres, et al., Appellants,

vs.

A&P Air Conditioning Corporation, Appellee.

An Appeal from the County Court for Miami-Dade County, Maria D. Ortiz, Judge.

Kopelowitz Ostrow Ferguson Weiselberg Gilbert, and Alexis Fields (Fort Lauderdale), for appellants.

Gary Bennett Goldman, P.A., and Gary B. Goldman, for appellee.

Before SCALES, C.J., and EMAS and FERNANDEZ, JJ.

EMAS, J. INTRODUCTION

A&P Air Conditioning Corp. (A&P) and Meritxell Pons Torres and

Valeria Scinto (Owners) filed competing lawsuits related to A&P’s

construction lien placed on Owners’ property. On appeal, Owners contend

the trial court erred when it (1) denied Owners’ motion for summary judgment

on A&P’s foreclosure of construction lien; (2) denied Owners’ motion for

summary judgment on their slander of title claim against A&P; and (3)

“granted” A&P’s suggestion of mootness.

For the reasons that follow, we affirm the trial court’s denial of Owners’

motions for summary judgment, but reverse the trial court’s order granting

A&P’s suggestion of mootness as well as the trial court’s final judgment

entered in favor of A&P. We remand for further proceedings.

FACTUAL AND PROCEDURAL BACKGROUND

In May 2021, Owners and A&P executed a contract for A&P to supply

and install two air conditioning units (one two-ton unit and one three-ton unit)

in Owners’ apartment for $11,400. The contract required an initial deposit of

$5,700 and a payment of $5,700 upon completion.

Owners paid the initial deposits, and the air conditioning units were

installed. Dissatisfied with A&P’s work, however, Owners refused to pay the

balance due, claiming that A&P installed the two-ton unit incorrectly. On

2 August 3, 2021, A&P recorded a claim of lien on the underlying property.

Days later, A&P filed a complaint seeking to foreclose on that lien for Owners’

failure to pay the balance due. Owners filed their own lawsuit against A&P

for slander of title.1 The two cases were consolidated, and each party filed

answers and affirmative defenses to the respective claims asserted against

them.

Two years later, on August 18, 2023, A&P filed a Suggestion of

Mootness, asserting that “all matters in [Owners’] own complaint against

[A&P] were settled.” By way of explanation, A&P cited Owners’ voluntary

payment of the balance due in November 2021 (months after the lawsuits

were filed):

On November 15, 2021, [Owners] voluntarily made a payment of $5,700 to [A&P]. [A&P] now suggests that this matter is moot. . . . [Owners], having made a voluntary payment in full of the balance owed, has resolved the controversy so fully. . . that a judicial determination can have no actual effect.

Owners did not specifically respond to the motion, but instead filed a

motion for summary judgment on their slander of title claim, averring in an

affidavit facts relevant to their 2021 payment of the amount due:

1 Initially, Owners also sued A&P for negligence and fraudulent lien; they voluntarily dropped their fraudulent lien action in April 2023, and the record and briefs suggest the parties settled Owners’ negligence claim.

3 - Shortly after installation of the air conditioning units, Owners

informed A&P that the two-ton air conditioning unit had been

installed incorrectly (i.e., “the air intake [was] on the wrong side of

the unit which would have caused the air flow to travel in the wrong

direction”; and “it was too close to the wall making it impossible to

clean the ducts.”).

- Instead of “completing” the work, A&P “prematurely” filed a claim of

lien in the amount of $5,700.

- On August 25, 2021, three weeks after filing a claim of lien, A&P

returned to the Owners’ apartment, agreed the air conditioning unit

was improperly installed, and “voluntarily installed a new 2 Ton

Unit.”

- Even though A&P returned and “properly installed the 2 Ton Unit,”

the company failed to “pull the necessary permit to remove and

replace the 2 Ton Unit in violation of Miami-Dade County Code.”

- On November 15, 2021, Owners paid the balance due.

- A&P’s filing of the lien on August 3, 2021, was premature and

unlawful, impaired Owners’ title, and required prosecution of the

slander of title claim.

4 In short, Owners paid the balance due but only upon A&P returning to the

property and addressing Owners’ complaints about the two-ton unit which

had led to their refusal to pay the balance in the first place. These allegations

formed the basis not only for Owners’ motion for summary judgment on its

slander of title claim, but also served to rebut A&P’s claim that “all matters in

[Owners’] own complaint against [A&P] were settled” by the payment of the

balance due.

Owners concluded that, because A&P failed to properly install the two-

ton unit and to pull a new permit when it later replaced the incorrectly-

installed unit, A&P did not substantially perform under the Agreement and

cannot recover on its claim of lien—accordingly, there is no genuine issue of

material fact that the lien “is a cloud on the premises.”

A&P responded, reiterating its position that the lawsuit was moot and

refuting Owners’ position that A&P had not substantially completed its work

under the Agreement. On the latter point, A&P maintained that it

substantially performed under the Agreement because it “secured a permit

for the contracted work, performed the contract, put in place a properly

functioning air conditioning system, and obtained and passed a final

mechanical inspection from the City of Miami.” Whether a second permit was

necessary to replace the unit on August 25, A&P continued, is a question of

5 law for the Court. Put differently, the Owners failed to present evidence that

the air conditioning system was not working properly when A&P recorded the

claim of lien.

Owners later filed a motion for summary judgment on A&P’s claim for

foreclosure of the construction lien, and A&P responded. Each party

reiterated arguments made in their pleadings on Owners’ motion for

summary judgment of their slander of title claim—these arguments primarily

concerned whether A&P had substantially performed under the contract

when it filed the construction lien.

On July 30, 2024, the trial court held a hearing, limited to Owners’

motion for summary judgment on A&P’s construction lien.2 The court orally

denied Owners’ motion for summary judgment on A&P’s action for

foreclosure of its construction lien, finding that the entire case was moot:

I find that the company was correct in filing the claim of the foreclosure action and your Motion for Summary Judgment, I find that the AC company completed the work substantially. Whether it was right or not, it passed inspection based on what I'm hearing. That's substantial completion. [Appellants] should have paid then.

2 It is undisputed that the notice of hearing was limited to Owners’ “motion for summary judgment as to [A&P’s] complaint,” e.g., A&P’s fraudulent lien claim. Even the order on appeal states that the matter before the court was Owners “Motion for Summary Judgment as to [A&P’s] Foreclosure of Construction Lien.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Godwin v. State
593 So. 2d 211 (Supreme Court of Florida, 1992)
Grant v. Wester
679 So. 2d 1301 (District Court of Appeal of Florida, 1996)
Braverman v. Van Bower, Inc.
583 So. 2d 381 (District Court of Appeal of Florida, 1991)
Langley v. Knowles
958 So. 2d 1149 (District Court of Appeal of Florida, 2007)
Ocean Ridge Develop. Corp. v. Quality Plastering, Inc.
247 So. 2d 72 (District Court of Appeal of Florida, 1971)
HOTEL 71 MEZZ LENDER, LLC v. Tutt
66 So. 3d 1051 (District Court of Appeal of Florida, 2011)
Ness Racquet Club, LLC v. Ocean Four 2108, LLC
88 So. 3d 200 (District Court of Appeal of Florida, 2011)
National Constructors, Inc. v. Ellenberg
681 So. 2d 791 (District Court of Appeal of Florida, 1996)
CDI Contractors, LLC v. Allbrite Electrical Contractors, Inc.
780 So. 2d 963 (District Court of Appeal of Florida, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Meritxell Pons Torres v. A&P Air Conditioning Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meritxell-pons-torres-v-ap-air-conditioning-corporation-fladistctapp-2026.