Merchants Bonding Company (Mutual) v. Arkansas Construction Solutions LLC

CourtDistrict Court, W.D. Arkansas
DecidedFebruary 5, 2019
Docket5:18-cv-05078
StatusUnknown

This text of Merchants Bonding Company (Mutual) v. Arkansas Construction Solutions LLC (Merchants Bonding Company (Mutual) v. Arkansas Construction Solutions LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merchants Bonding Company (Mutual) v. Arkansas Construction Solutions LLC, (W.D. Ark. 2019).

Opinion

IN THE UNITED STATES DISTRICT COURT WESTERN DISTRICT OF ARKANSAS FAYETTEVILLE DIVISION

MERCHANTS BONDING COMPANY (MUTUAL) and MERCHANTS NATIONAL BONDING, INC. PLAINTIFFS

V. CASE NO. 5:18-CV-05078

ARKANSAS CONSTRUCTION SOLUTIONS, LLC; R.L. STOCKETT & ASSOCIATES, LLC; RICK L. STOCKETT; and DIANA STOCKETT DEFENDANTS

MEMORANDUM OPINION AND ORDER

Now before the Court is a motion for preliminary injunction, styled “Application for Injunctive Relief” (Doc. 3), filed by Merchants Bonding Company (Mutual) and Merchants National Bonding, Inc. (collectively, “Merchants”). Defendants R.L. Stockett & Associates, LLC, Rick L. Stockett, and Diana Stockett (collectively, “the Stockett Defendants”) filed a Response in Opposition to the motion (Doc. 44), and Merchants filed a Reply (Doc. 47).1 The motion is GRANTED.2

1 Separate Defendant Arkansas Construction Solutions, LLC (“ACS”), responded to the Application for Injunctive Relief to the extent that it generally denied that Merchants was entitled to the relief it requested, and it requested extra time to submit to and complete discovery before submitting a full response. (Doc. 25). ACS’s response was filed on September 11, 2018, and it filed no further responses. Further, ACS’s counsel represented at a hearing on November 6, 2018, that ACS was insolvent. The substantive arguments discussed in the following Order were raised only by the Stockett Defendants, and not ACS, although by the terms of the Indemnity Agreement at issue here, ACS and the Stockett Defendants appear to be jointly liable for damages resulting from any alleged breach of contract.

2 The Court had reserved February 14, 2019, as a hearing date for the motion. However, after reviewing the parties’ briefing, the Court determined that no constructive purpose would be served in holding a hearing because there are no material factual controversies at issue. See United Healthcare Inc. Co. v. AdvancePCS, 316 F.3d 737, 744 (8th Cir. 2002) (“An evidentiary hearing is required prior to issuing a preliminary injunction only when a material factual controversy exists.”). Accordingly, the Stockett Defendants’ Motion to Continue Hearing (Doc. 48) is MOOT. I. BACKGROUND The parties do not dispute the following background facts. Merchants filed the instant case, requesting declaratory and injunctive relief and damages for breach of contract, on May 14, 2018. All Defendants entered into an Indemnity Agreement (Doc.

1-1) with Merchants to cover losses associated with certain payment and performance bonds that Merchants issued on behalf of ACS in connection with the Sunrise Ridge Subdivision construction project. ACS had been selected as the contractor on the construction project, and the developer, Sunrise Developers, Inc. (“Sunrise”), required ACS to obtain payment and performance bonds to insure its work. ACS approached Merchants for the bonds. In exchange, Merchants required ACS to fully indemnify Merchants against any and all losses that might be claimed against the bonds, as well as provide Merchants, upon demand, with collateral security “to cover any liability for any loss or expense for which [Merchants] may be obligated to indemnify the Company . . . .” (Doc. 1-1, p. 5). The Stockett Defendants agreed to serve as indemnitors on the payment

and performance bonds. The day after all Defendants signed the Indemnity Agreement, Merchants formally issued the payment and performance bonds on behalf of ACS as principal, and for the benefit of Sunrise as developer. See Doc. 29-1, p. 32. At some point, problems arose on the construction site of the Sunrise Ridge Subdivision, and some subcontractors began making claims against ACS and Sunrise for payment. One of those subcontractors, Del-Sha Construction, LLC, (“Del-Sha”) filed a lawsuit against ACS, Sunrise, and Merchants in Benton County, Arkansas Circuit Court, Case Number 04CV-17-1370, requesting payment under the Merchants payment bond for work Del-Sha performed on the Sunrise Ridge subdivision. See Doc. 29-1. Then ACS filed a mechanics lien against Sunrise, and Sunrise filed a cross-claim against ACS and Merchants. In an earlier Order issued in the case at bar (Doc. 42), this Court found that the federal case before it (concerning the Indemnity Agreement) and the Del-Sha case

currently being litigated in state court (concerning the amounts disputed and allegedly owed under the payment and performance bonds), are not parallel, and this Court was therefore not required to abstain from ruling on the issues before it. The Court explained its reasoning as follows: The state court is currently being asked to adjudicate the parties’ rights under the payment and performance bonds and determine who should be paid and in what amounts. These claims are not at issue in the federal lawsuit. The Stockett Defendants also contend that the “preliminary issue of whether the construction contract was breached by SD [Sunrise] or by ACS . . . must be decided first” by this Court, [Doc. 29] at 10. Their thinking on this point, apparently, is that if ACS is eventually absolved of all liability in state court on the bond issues, then any action by this Court to require the Stockett Defendants to pony up collateral to secure the bonds will end up being a waste of time. Certainly, the Stockett Defendants prefer not to indemnify Merchants and not to post any collateral. They would much rather wait and see how the state court action plays out, and then, perhaps a year or more from now, after all obligations under the payment and performance bonds have been fully resolved, permit Merchants to then proceed with their federal claims under the Indemnity Agreement. But surely this “wait-and- see” strategy was not contemplated by the parties when they signed the Indemnity Agreement.

Contrary to the Stockett Defendants’ position, the Court believes that deciding Merchants’ claims in the instant lawsuit will not require the Court to decide “the preliminary issue of whether the construction contract was breached by SD [Sunrise Developers] or by ACS.” (Doc. 29, p. 10). It is the state court that is tasked with resolving the parties’ claims under the payment and performance bonds, not the federal court. It is therefore also the state court’s task to determine the validity and enforceability of those bonds, if called upon to do so. Accordingly, if any party to this action requests that this Court make rulings concerning the validity, enforceability, or obligations owed under the payment and performance bonds, the Court will abstain from doing so in favor of allowing the state court to rule on those issues. Further, if the state court eventually determines that the bonds are null and void (as Mr. Stockett contends), such a decision will not adversely affect the rulings made by this Court with respect to the Indemnity Agreement or otherwise result in a net waste of judicial resources.

(Doc. 42, pp. 9-10)

The issue that is now ripe for decision is whether Merchants is entitled to a preliminary injunction that would require the Stockett Defendants to provide collateral to Merchants in the sum of $700,000. Although the full penalty sum of the payment bond at issue is only $500,000, it appears Merchants is demanding $700,000 in collateral because it estimates that its total current outstanding exposure under the bonds, including its projected attorney’s fees, is $200,000 in excess of the full penalty sum of the bonds. There are four factors that a court must consider, generally, in ruling on a motion for preliminary injunction. The Stockett Defendants contend that none of the four factors weighs in favor of issuing the preliminary injunction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dataphase Systems, Inc. v. C L Systems, Inc.
640 F.2d 109 (Eighth Circuit, 1981)
S & M Constructors, Inc. v. The Foley Company
959 F.2d 97 (Eighth Circuit, 1992)
United Healthcare Insurance Co. Aarp v. Advancepcs
316 F.3d 737 (Eighth Circuit, 2002)
Mazurek v. Armstrong
520 U.S. 968 (Supreme Court, 1997)
Firemen's Ins. Co. of Newark, NJ v. Keating
753 F. Supp. 1146 (S.D. New York, 1990)
United States Surety Co. v. Stevens Family Ltd. Partnership
905 F. Supp. 2d 854 (N.D. Illinois, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Merchants Bonding Company (Mutual) v. Arkansas Construction Solutions LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merchants-bonding-company-mutual-v-arkansas-construction-solutions-llc-arwd-2019.