Mendenhall v. Aldous

196 P.3d 352, 146 Idaho 434, 2008 Ida. LEXIS 203
CourtIdaho Supreme Court
DecidedOctober 23, 2008
Docket34700
StatusPublished
Cited by22 cases

This text of 196 P.3d 352 (Mendenhall v. Aldous) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mendenhall v. Aldous, 196 P.3d 352, 146 Idaho 434, 2008 Ida. LEXIS 203 (Idaho 2008).

Opinion

J. JONES, Justice.

Jerry Mendenhall sued Alan and Jennifer Aldous, dba Aldous Construction, for breach of contract after they failed to finish work on two contracts relating to Mendenhall’s house and a detached shop. The Aldouses moved for summary judgment, contending Mendenhall failed to comply with Idaho’s Notice and Opportunity to Repair Act, I.C. §§ 6-2501-2504. The district court granted summary judgment and Mendenhall appealed. We vacate and remand.

I.

Jerry Mendenhall filed suit against Alan and Jennifer Aldous after they disagreed about work the couple was to perform on a house Mendenhall purchased from them. The Aldouses were in the process of building the home for themselves when Mendenhall offered to buy it. The parties entered into a sales agreement that outlined several specific tasks the Aldouses were to complete on the home. Mendenhall made a separate agreement with Alan Aldous to build a detached shop on the premises. Alan completed the shop but, after an argument with Mendenhall regarding payment, he left the job site and did not finish the remaining work on the home.

The Aldouses hired attorney Jordan Smith in an effort to resolve the dispute. On February 18, 2005, Smith sent Mendenhall a letter on behalf of his clients. The letter discussed various unfinished aspects of the house and suggested a resolution for each. Mendenhall replied by letter on March 11 (“the March 11 letter”). The March 11 letter complained of unfinished work on the house and of a leaking roof. It also stated that Mendenhall was having problems with the detached shop Alan built. In the letter, Mendenhall stated he had “no choice but to hire other contractors to do [Alan’s] work” and that he expected Alan to pay for the work “at the time it is due without further dispute.” Smith wrote back on March 15 (“the March 15 letter”). He stated that “[i]t would be helpful if you would specify the proposals in my first letter that you will accept, and specify the action that you would like Alan and Jeni to perform.” After receiving the letter, Mendenhall hired attorney Ronald Swafford, who sent the Aldouses a demand letter for $29,496.74 on April 29. This letter ended communication between the parties.

Nearly a year later, Mendenhall filed a complaint against the Aldouses, alleging breach of contract based on Alan’s work on *436 the house and shop. The Adouses answered and asserted the affirmative defense that Mendenhall failed to comply with Idaho’s Notice and Opportunity to Repair Act (“NORA” or “Act”), I.C. §§ 6-2501-2504. The Adouses moved for summary judgment on that basis, which the district court granted. Mendenhall appeals, contending that his March 11 letter satisfied the requirements of NORA.

II.

On appeal, we are concerned with two issues: (1) whether the district court properly granted the Adouses’ motion for summary judgment on the basis that Mendenhall failed to comply with NORA; and (2) whether the Adouses are entitled to attorney fees.

A.

Standard of Review

When reviewing an order for summary judgment, the standard of review for this Court is the same standard used by the district court in ruling on the motion. Watson v. Weick, 141 Idaho 500, 504, 112 P.3d 788, 792 (2005). Summary judgment is proper when “the pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Idaho R. Civ. P. 56(c). A mere scintilla of evidence or only slight doubt is not sufficient to create a genuine issue of material fact. Finholt v. Cresto, 143 Idaho 894, 897, 155 P.3d 695, 698 (2007). The nonmoving party must submit more than conclusory assertions that an issue of material fact exists to withstand summary judgment. Id. at 896-97, 155 P.3d at 697-98. However, we will construe all disputed facts and reasonable inferences in favor of the nonmoving party. Carnell v. Barker Mgmt., Inc., 137 Idaho 322, 327, 48 P.3d 651, 656 (2002). If there is no genuine issue of material fact, “only a question of law remains, over which this Court exercises free review.” Watson, 141 Idaho at 504, 112 P.3d at 792.

B.

The District Court’s Grant of Summary Judgment Was Improper

Athough Mendenhall was not aware of NORA when he drafted the March 11 letter, he argues that the district court erred in granting the Adouses’ motion for summary judgment because the March 11 letter satisfied NORA’s notice requirement. Further, he maintains that the Adouses did not comply with NORA because they did not respond to his letter in the manner required by the Act.' The Adouses argue that summary judgment was proper because the March 11 letter did not provide them with reasonably detailed notice of the construction defects Mendenhall alleged and, as a result, their duty under NORA was not triggered.

1.

Mendenhall’s March 11 Letter Satisfied NORA’s Notice Requirement

NORA is a relatively new piece of legislation, and interpretation of the statute is a matter of first impression for this Court. The Act was passed in 2003. The Idaho Building Contractors Association sponsored the bill in an effort to curb litigation against building contractors by homeowners. The purpose of the law is to give contractors the opportunity to fix construction defects before a lawsuit is filed. In furtherance of this goal, NORA requires a claimant to “serve written notice of claim on the construction professional,” prior to filing an action alleging a construction defect. I.C. § 6-2503(1). The written notice must “state that the claimant asserts a construction defect claim against the construction professional and ... describe the claim in reasonable detail sufficient to determine the general nature of the defect.” Id. If a claimant fails to provide written notice before filing suit, his or her claim will be dismissed without prejudice and it “may not be recommenced until the claimant has complied with the [notice] requirements.” Id. Importantly, nothing in the statute requires a claimant to knowingly comply with its notice provisions.

This case comes down to whether Mendenhall’s March 11 letter described his *437 claims “in reasonable detail sufficient to determine the general nature of the defeet[s].” In enacting NORA, the Legislature did not define the phrase “reasonable detail.” Accordingly, we must determine the Legislature’s intent from the statutory language and ordinary meaning of the terms. See Ag Servs. of Am., Inc., v. Kechter, 137 Idaho 62, 64, 44 P.3d 1117, 1119 (2002). “Reasonable” means “being or remaining within the bounds of reason ... not extreme ... not excessive ... not demanding too much.” Webster’s Third New International Dictionary 1892 (1966). “Detail” simply means “to relate in particulars.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

IDHW v. Beason
Idaho Supreme Court, 2024
Davis v. George and Jesse's Les Schwab Tire Store, Inc.
541 P.3d 667 (Idaho Supreme Court, 2023)
D.L. Evans Bank v. Dean
Idaho Supreme Court, 2023
Neeser v. Inland Empire Paper Company
Idaho Supreme Court, 2022
Walker v. Meyer
511 P.3d 828 (Idaho Supreme Court, 2021)
Dickinson Frozen Foods, Inc. v. J.R. Simplot Co.
434 P.3d 1275 (Idaho Supreme Court, 2019)
Davison v. Debest Plumbing, Inc.
416 P.3d 943 (Idaho Supreme Court, 2018)
Linda Ciszik v. Kootenai County Bd of Commissioners
254 P.3d 24 (Idaho Supreme Court, 2011)
Ciszek v. KOOTENAI COUNTY BD. OF COM'RS
254 P.3d 24 (Idaho Supreme Court, 2011)
Halvorson v. North Latah County Highway District
254 P.3d 497 (Idaho Supreme Court, 2011)
Carpenter v. TURRELL
227 P.3d 575 (Idaho Supreme Court, 2010)
IDAHO DAIRYMEN'S ASS'N v. Gooding County
227 P.3d 907 (Idaho Supreme Court, 2010)
STATE, EX REL. WASDEN v. Maybee
224 P.3d 1109 (Idaho Supreme Court, 2010)
State v. Scott B. Maybee
Idaho Supreme Court, 2010
Saint Alphonsus Diversified Care, Inc. v. MRI Associates, LLP
224 P.3d 1068 (Idaho Supreme Court, 2010)
Armstrong v. Farmers Ins. Co. of Idaho
205 P.3d 1203 (Idaho Supreme Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
196 P.3d 352, 146 Idaho 434, 2008 Ida. LEXIS 203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mendenhall-v-aldous-idaho-2008.