Menard County Housing Authority v. Johnco Construction, Inc.

CourtAppellate Court of Illinois
DecidedJuly 18, 2003
Docket4-03-0273 Rel
StatusPublished

This text of Menard County Housing Authority v. Johnco Construction, Inc. (Menard County Housing Authority v. Johnco Construction, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Menard County Housing Authority v. Johnco Construction, Inc., (Ill. Ct. App. 2003).

Opinion

NO. 4-03-0273

IN THE APPELLATE COURT

OF ILLINOIS

FOURTH DISTRICT

MENARD COUNTY HOUSING AUTHORITY, ) Appeal from

Plaintiff-Appellee, ) Circuit Court of

  1. ) Menard County

JOHNCO CONSTRUCTION, INC., ) No. 02MR9

Defendant-Appellant. )

) Honorable

) M. Carol Pope,

) Judge Presiding.

_________________________________________________________________

JUSTICE COOK delivered the opinion of the court:

Defendant, Johnco Construction, Inc. (Johnco), appeals an order of the Menard County circuit court denying Johnco's motion to stay and to compel arbitration pursuant to the Uniform Arbitration Act (710 ILCS 5/1 through 23 (West 2000)).  We reverse and remand.

In March 2000, the Menard County Housing Authority (MCHA) hired Johnco to renovate an MCHA public housing building.  The contract provided that Johnco would complete the renovations within 365 days with exceptions for unforseen or unavoidable causes for delay.  The contract included a liquidated-damages provision, which provided that liquidated damages would be assessed at a rate of $100 per calendar day for every day that Johnco took to finish the renovations beyond 365 days.  The contract also had an optional arbitration clause.  It provided that when the contracting officer made a final decision regarding a claim arising under or relating to the contract, Johnco could appeal that decision to an arbitrator or mediator, but it had to do so within 30 days of the contracting officer's decision.  Finally, the contract provided that Johnco would "proceed diligently" with performance of the contract, even while claims relating to the contract were pending.  

On November 15, 2001, Anne Smith, who was the executive director of MCHA and listed as the contracting officer in the contract, sent a letter to Johnco informing it that $20,400 in liquidated damages had accrued because of the delay in finishing the renovations.  Johnco had finished the actual physical renovations to MCHA's building, but it took longer than 365 days.  MCHA offered to forego 10% of the liquidated damages if Johnco would finalize the project by producing certain close-out papers pursuant to the contract, such as lien releases from subcontractors, architect-requested documents, and a final pay request, by December 10, 2001.  MCHA needed these close-out documents to administratively complete the project and be able to secure funding for the project.

Johnco responded with a letter dated November 16, 2002, which generally alleged that the delays had not been Johnco's fault and that no liquidated damages should have accrued.  According to Johnco, the delay occurred because MCHA had failed to disclose that the heating system in the building made it impossible to do any renovations in the winter and still have heat for the tenants of the building.  Johnco had anticipated being able to work during the winter months when it set a completion date for the project.  Johnco did not provide the requested close-out papers.

On May 3, 2002, MCHA's attorney mailed a letter to Johnco again requesting that Johnco produce the previously requested close-out papers.  The letter acknowledged Johnco's argument that the delay in completing the renovations was not Johnco's fault but stated that "[MCHA] has previously taken into account the substance of said protest in modifying its assessment of liquidated damages and is not amenable to further adjustment."  The letter finished by saying that if the requested close-out documents were not produced, MCHA would pursue legal proceedings to force Johnco to produce the documents.

Johnco responded to the May 3, 2002, letter with a letter addressed to Anne Smith dated May 16, 2002.  This letter generally reiterated Johnco's claim that the delays in finishing the renovations were not Johnco's fault and that any assessment of liquidated damages was unwarranted.  The letter ended with the following paragraph:

"Please review and advise what course

of action you want to take.  We are prepared

for anything.  If MRA and MCHA want to pursue

legal action, so be it.  We are very optimis-

tic that somewhere, someone in the legal

system will be open-minded, reasonable, and

understanding."

Johnco did not produce the requested close-out documents.  

MCHA filed its complaint for declaratory judgment and for further relief on June 26, 2002.  The complaint sought a declaration that Johnco was obligated pursuant to the contract to provide the close-out papers and an order compelling Johnco to provide those documents.  Johnco responded with a motion to stay and to compel arbitration pursuant to the contract's arbitration provision.  

The trial court denied Johnco's motion to compel arbitration, finding that Johnco could no longer invoke the arbitration provision in the contract.  The contract provides that the "Contracting Officer" will decide any claims made by either party and:

"The Contracting Officer's decision shall

be final unless the Contractor [(Johnco)] (1)

appeals in writing to a higher level in the

PHA/IHA in accordance with the PHA's/IHA's

policy and procedures, (2) refers the appeal

to an independent mediator or arbitrator,

or (3) files suit in a court of competent

jurisdiction.  Such appeal must be made

within [30 days] after receipt of the Con-

tracting Officer's decision."

The court found the May 3, 2002, letter from MCHA's attorney rejecting Johnco's claim that it was not liable for liquidated damages was a final decision of the contracting officer and that 30 days had passed without Johnco referring the appeal to an arbitrator.  Therefore, pursuant to the terms of the arbitration provision itself, Johnco could no longer invoke arbitration.  Johnco appeals.

A motion to compel arbitration is treated as a complaint for injunctive relief, and a denial of that motion is reviewed pursuant to Supreme Court Rule 307(a)(1) (134 Ill. 2d R. 307(a)(1)).   Yandell v. Church Mutual Insurance Co. , 274 Ill. App. 3d 828, 830, 654 N.E.2d 1388, 1389 (1995).  Rule 307(a)(1) allows an interlocutory appeal of an order granting or denying injunctive relief.  See 134 Ill. 2d R. 307(a)(1).  "The sole issue before the appellate court on an interlocutory appeal is whether a sufficient showing was made to sustain the order of the trial court denying the motion to compel arbitration."   Yandell , 274 Ill. App. 3d at 830, 654 N.E.2d at 1389.  Thus, the standard of review in an interlocutory appeal is whether the trial court abused its discretion.   Yandell , 274 Ill. App. 3d at 831, 654 N.E.2d at 1389.

The issue whether a contract to arbitrate exists must be determined by the court, not an arbitrator.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Donaldson, Lufkin & Jenrette Futures, Inc. v. Barr
530 N.E.2d 439 (Illinois Supreme Court, 1988)
Village of Carpentersville v. Mayfair Construction Co.
426 N.E.2d 558 (Appellate Court of Illinois, 1981)
Salsitz v. Kreiss
761 N.E.2d 724 (Illinois Supreme Court, 2001)
Yandell v. Church Mut. Ins. Co.
654 N.E.2d 1388 (Appellate Court of Illinois, 1995)
Rauh v. Rockford Products Corp.
574 N.E.2d 636 (Illinois Supreme Court, 1991)
Board of Education of Posen-Robbins School District No. 143½ v. Daniels
439 N.E.2d 27 (Appellate Court of Illinois, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Menard County Housing Authority v. Johnco Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/menard-county-housing-authority-v-johnco-construct-illappct-2003.