Memmolo's Case

458 N.E.2d 1204, 17 Mass. App. Ct. 407, 1984 Mass. App. LEXIS 1354
CourtMassachusetts Appeals Court
DecidedJanuary 23, 1984
StatusPublished
Cited by6 cases

This text of 458 N.E.2d 1204 (Memmolo's Case) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Memmolo's Case, 458 N.E.2d 1204, 17 Mass. App. Ct. 407, 1984 Mass. App. LEXIS 1354 (Mass. Ct. App. 1984).

Opinion

Perretta, J.

General Laws c. 82, § 40, as amended by St. 1968, c. 403, § 1, and as in effect on the day here in question, October 28, 1977, prohibits the making of an excavation on a public way without at least forty-eight hours prior written notice to public utility companies of the intention to excavate. Compliance with § 40 is excused in cases of “emergency.” While drilling in an area beneath the street in order to make repairs on a sewer line on October 28, 1977, the employee, Giuseppe Memmolo, struck an electric cable with his air hammer. He was severely injured and sought *408 double compensation benefits under G. L. c. 152, § 28. 1 A single member of the Industrial Accident Board, whose findings were affirmed and adopted by the reviewing board (board), found that the employer, Bond Brothers, Inc. (Bond), had failed to show that it had complied with c. 82, § 40, or that an emergency existed to excuse its noncompliance, and that its actions constituted serious and wilful misconduct entitling the employee to enhanced benefits. We conclude that the board’s decision was warranted on the facts and law and reverse the Superior Court judgment dismissing the employee’s claim under c. 152, § 28.

1. Evidence Before the Single Member.

The trial judge “was obligated, and this court on appeal is obligated, to sustain the decision of the board, which supersedes that of the single member, Haley’s Case, 356 Mass. 678, 679 (1970), if there was any evidence to warrant the conclusion that the employee was ‘injured by reason of the serious and wilful misconduct of an employer or of any person regularly intrusted with and exercising the powers of superintendence.’ G. L. c. 152, § 28.” O’Leary’s Case, 367 Mass. 108, 111 (1975). Evidence of the following facts was presented to the single member.

a. The Injury.

Some time on October 26, 1977, a representative of Gulf Oil Company (Gulf) telephoned Bond and requested that repair work be done on a street sewer line connected with its Chelsea property. Acting on instructions from Bond, one Charles Sclafani, a foreman at Bond, went to the Gulf property, an office building, and observed that the lavatory facilities were backed up, filled to the top, and that there was a water drainage problem.

*409 Prior to 7:30 a.m. the next day, Sclafani ascertained the source of the blockage by running a plastic rod down the drain and into the sewer line. Once the source of the problem was located, Sclafani measured and marked off a square on the asphalt surface of the street. He knew what pipe he was looking for because a Gulf representative had given him a diagram, or blueprint of the “sewer and connector” from the street to the office building. There were no markings on the street to indicate whether there were any utility lines beneath the surface of the street.

Memmolo was assigned by Bond to work with Sclafani on the repair project. Memmolo had arrived in this country in 1975 from Italy, where he had received only four years of schooling and had earned his livelihood as a farmer. He was employed by Bond as a laborer, doing drill work.

Memmolo reported to the Chelsea job site at 7:30 a.m. on October 27, 1977. He saw the street markings earlier made by Sclafani, who was also at the site. Sclafani instructed Memmolo to excavate at the markings with a jack-drill until he reached the pipe. By the end of the work day, 4:00 p.m. , Memmolo had excavated about five feet, and the pipe was visible. He returned to the job site the next morning, told Sclafani, “I see concrete down there,” and was told by Sclafani not to worry, “you can go on working.” Memmolo then continued to excavate with the drill as instructed and “all of a sudden flames came all over me and I was burning.” Just before the flames, Memmolo “heard like an explosion, a big noise.”

Almost immediately after the accident, James Behenna, a special investigator with Boston Edison Company, went to the Chelsea excavation site and saw water and a Boston Edison duct line 2 in the hole.

b. The Emergency.

The evidence on the question whether the condition existing on Gulf’s property constituted an emergency is, for the most part, conclusory. For example, when a representative *410 of Gulf called Bond, the representative allegedly described the situation as an emergency. On or about October 26th or 27th, Bond prepared written applications, which were apparently presented to the Department of Public Works, at some unascertained time, 3 seeking permission to excavate “on an emergency basis” in order “to make emergency repairs to sewerline ... in front of 123 Eastern Ave. . . . Chelsea.” No information as to the nature of the “emergency” is contained in these documents. Indeed, the only evidence appearing in the record which bears upon the circumstances of the “emergency” is Sclafani’s statement that “the toilets were backing up and sanitary facility sinks . . . [t]hey were filled up to the top.”

Evidence discrediting the notion of an exigent situation is found in Bond’s previously described applications wherein permission to excavate was sought for “an estimated period of 5 days” and in the testimony of Sclafani and Memmolo, that on their first day of work at the job site, they worked a “normal” work day, 7:30 a.m. to 4:00 p.m.

c. The Notice of Excavation.

As previously stated, on the day of the accident, G. L. c. 82, § 40, required Bond, in the absence of an emergency, to give advance (at least forty-eight hours) written notice of the intended excavation work. There is no question that Bond did not do this.

In the face of an emergency, the statute continues, notice “shall be given as soon as may be practicable.” On this point, there was evidence of the existence of a “dig safe” telephone calling system, whereby a contractor could call a particular number to inform the public utilities of the excavation work. An officer of Bond testified that he “assume[d]” a “dig safe” call had been made by someone at Bond prior to the commencement of the work, but he could not say when such a call was made, or by whom, or that the call had in fact been made. 4

*411 d. The Single Member’s Findings.

The single member found that Memmolo, following the orders of his foreman, Sclafani, used an air hammer to drill and excavate the marked area and in so doing struck an electric cable. The single member further found that the “dig safe” number “was not used to inform Public Utilities of the excavation,” that Bond had failed to prove “beyond a reasonable doubt” that an emergency had in fact existed, that Bond had not complied with c. 82, § 40, that Bond’s actions constituted “serious and wilful misconduct,” and that Memmolo was seriously injured as a result of Bond’s actions.

2. Discussion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Drumm's Case
903 N.E.2d 1127 (Massachusetts Appeals Court, 2009)
Resendes v. Boston Edison Co.
648 N.E.2d 757 (Massachusetts Appeals Court, 1995)
Inferrera v. Town of Sudbury
575 N.E.2d 82 (Massachusetts Appeals Court, 1991)
Gamere v. 236 Commonwealth Avenue Condominium Ass'n
474 N.E.2d 1135 (Massachusetts Appeals Court, 1985)
Armstrong's Case
472 N.E.2d 669 (Massachusetts Appeals Court, 1984)
Petras v. Storm
465 N.E.2d 283 (Massachusetts Appeals Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
458 N.E.2d 1204, 17 Mass. App. Ct. 407, 1984 Mass. App. LEXIS 1354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/memmolos-case-massappct-1984.