Melton Properties, LLC v. Illinois Central Railroad Company

District Court, N.D. Mississippi·Decided July 18, 2024·No. 4:18-cv-00079·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF MISSISSIPPI GREENVILLE DIVISION MELTON PROPERTIES, LLC et al. PLAINTIFFS v. CIVIL ACTION NO. 4:18-cv-079-DMB-JMV ILLINOIS CENTRAL RAILROAD COMPANY et al. DEFENDANTS ORDER

This matter is before the court on Plaintiffs’ June 19, 2024, motion [Doc. No. 494] by which Plaintiffs seek, generally, an order requiring timely supplementation of (1) soil and groundwater sampling results from the July 1, 2024, discovery deadline to the time of trial and (2) all of Defendant’s discovery responses through the date of the discovery deadline. Defendant has filed its response in opposition [Doc. No. 512] and Plaintiffs have filed their reply [Doc. No. 521]. For the reasons explained below, the motion is denied, with a single caveat discussed hereafter relating to the timing of Plaintiffs’ access to future sampling results through the date of trial.

I. Background and Procedural Posture As previously described in this Court’s June 14, 2024, Order [Doc. No. 489], discovery in the case has occurred in “fits and starts” due primarily to discovery stays pending remediation efforts. As it stands now, the discovery deadline ran on July 1, 2024.' Daubert motions are due August 1, 2024, and dispositive motions are due September 2, 2024. Trial is set for February 3, 2025.

| The parties have received an extension [Doc. No. 498] for the limited purpose of taking certain depositions until July 31, 2024. All other discovery was to have been completed by the prior deadline of July 1, 2024 [Doc. No. 423].

The instant motion was filed on June 19, 2024, and full briefing (which followed a typical briefing schedule with no extensions) was completed on July 10, 2024, after the close of discovery. By way of background, this action was filed on March 27, 2018, following a train derailment and spillage of heavy oil resins that occurred on or about March 30, 2018. The derailment and spillage are alleged to have contaminated Plaintiffs’ agricultural land and otherwise caused them significant economic damages. Ongoing remediation efforts are a significant point of contention in this case. Those efforts, undertaken by the defendant railroad, via its contractor GHD under the supervision of the Mississippi Department of Environmental Quality (“MDEQ”), have entered the monitoring phase. Pursuant to Agreed Order No. 7291-23 of the Mississippi Commission on Environmental Quality (“Agreed Order’) (Exhibit “A” [Doc. No. 494-1]), ICRR and/or GHD must perform quarterly monitoring of groundwater wells and soil borings at the site of the March 2015 train derailment indefinitely. These quarterly monitoring events represent an effort to ascertain if the remediation has successfully reduced DCPD contamination below the applicable target remediation goals without the remediation system actively operating, or if, instead, additional remediation will be required. To accomplish the quarterly monitoring the Agreed Order provides that GHD collects soil and groundwater samples, preserves them, and ships them to a laboratory for analysis. GHD then apparently receives the laboratory results, takes 30-60 days to prepare a report to accompany the results, and submits said report to MDEQ, copying Plaintiffs with the report at that time. The next such report is anticipated by Plaintiffs to not be prepared until the eve of trial or perhaps later.

In their motion for supplementation pursuant to FRCP 26(e), Plaintiffs seek three forms of relief: (1) An order requiring supplementation of “all [D]efendant[’s] discovery Responses”, through the date of the discovery deadline, July 1, 2024, or, alternatively, an order requiring Defendant to “declare affirmatively that throughout the past four years no new responsive documents or communications have come into existence”; (2) an order requiring supplementation of soil and groundwater sampling results occurring from the discovery deadline to the date of trial; and (3) an order clarifying ICRR’s existing obligation under the aforementioned Agreed Order to produce to Plaintiffs all future laboratory results as they are received by Defendant’s testing contractor GHD, as opposed to awaiting their provision by GHD to MDEQ in a prepared report, the creation of which is asserted to take over a month or two after the date on which the quarterly sample results themselves are received by GHD. In support of the first request, one for an order requiring supplementation, through the date of the discovery deadline, July 1, 2024, of all of Defendant’s discovery responses, Plaintiffs assert that, since 2020, they have received no supplemental discovery responses from ICRR aside from 89 photographs. Noting that in that four-year period, ICRR and GHD have engaged in active remediation and monitoring activities at the site, Plaintiffs assert “numerous emails, work plans, and other relevant documents responsive to various discovery requests may be assumed to have been created in the intervening time.” According to Plaintiffs, they are entitled to such supplementation pursuant to Local Civil Rule 26(a)(5), which requires supplementation at

appropriate intervals and in no event later than the discovery deadline set by the case management order. In support of the second request, one for an order requiring “timely” supplementation of soil and groundwater sampling results occurring from the discovery deadline to the date of trial, Plaintiffs assert the obligation to timely supplement discovery under Rule 26(e) does not end with the discovery deadline, but instead “runs through the time of trial.” They cite the following authorities for this proposition: Louisiana Corral Management, LLC v. Axis Surplus Ins. Co., Order and Reasons, Civ. Act. No. 22-2398, 2023 WL 2185981 at *12 (E.D. La. Feb. 23, 2023); Mills v. Beech Aircraft Corp., Inc., 886 F.2d 758, 764 (5th Cir. 1989); Brooks v. Stringer, 2007 WL 43819, *2 (S.D. Miss. 2007); Betts v. Gen. Motors Corp., Civ. Act. No. 3:04-CV-169, Order, 2008 WL 11342869 at *2 (N.D. Miss. Aug. 19, 2008); cf Miss. Coast Physicians LLC v. Multiplan, Inc., Civ. Act. No. 1:16¢v273, Memorandum Order, 2018 WL 9619347 at *3-4 (S.D. Miss. Jan. 23, 2018). As to Plaintiffs’ request for an order clarifying the Agreed Order No. 7291-23 of the Mississippi Commission on Environmental Quality so as to require GHD to submit to Plaintiffs the quarterly sampling results when they are received by GHD rather than 30-60 days later in the form of a compiled report, Plaintiffs cite no authority. In opposition to the instant motion, Defendants argue: (1) that it is untimely because Plaintiffs waited until June 19, 2024—less than two weeks from the expiration of the discovery deadline—to submit their “Rule 26(e)” discovery motion requesting from the Court an order “requiring” immediate and future supplementation from ICRR. Local Rule 7(b) requires that “[a] party must file a discovery motion sufficiently in advance of the discovery deadline to allow

response to the motion, ruling by the court and time to effectuate the court’s order before the discovery deadline.” L.U. Civ.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Melton Properties, LLC v. Illinois Central Railroad Company, (N.D. Miss. 2024).

Melton Properties, LLC v. Illinois Central Railroad Company (Melton Properties, LLC v. Illinois Central Railroad Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mills v. Beech Aircraft Corporation, Inc.
886 F.2d 758 (Fifth Circuit, 1989)