MELTON FRANK D/B/A FRANK BUILDING AND REMODELING VERSUS BILL TRAN

Louisiana Court of Appeal·Decided January 30, 2008·No. CA-0007-0983·Unknown

Opinion

STATE OF LOUISIANA

COURT OF APPEAL, THIRD CIRCUIT

07-983

MELTON FRANK D/B/A FRANK BUILDING AND REMODELING VERSUS BILL TRAN

**********

APPEAL FROM THE

THIRTY-FIRST JUDICIAL DISTRICT COURT PARISH OF JEFFERSON DAVIS, NO. C-422-04 HONORABLE ANNE LENNAN SIMON, JUDGE PRO TEMPORE

**********

MARC T. AMY

JUDGE

**********

Court composed of John D. Saunders, Marc T. Amy, and Billy Howard Ezell, Judges.

REVERSED AND REMANDED.

Steve Gunnell Cassidy & Gunnell Post Office Box 1446 Jennings, LA 70546 (337) 824-7322 COUNSEL FOR DEFENDANT/APPELLEE:

Jeff Davis Bank & Trust Company

Timothy O'Dowd 921 Ryan Street, Suite D Lake Charles, LA 70601 (337) 310-2304 COUNSEL FOR PLAINTIFF/APPELLEE:

Melton Frank

Blaine A. Doucet Doucet, Lorio & Moreno One Lakeshore Drive, Suite 1695 Lake Charles, LA 70629 (337) 433-0100 COUNSEL FOR DEFENDANT/APPELLEE:

Rick Rion

Kendrick J. Guidry Plauche, Smith & Nieset Post Office Drawer 1705 Lake Charles, LA 70602 (337) 436-0522 COUNSEL FOR DEFENDANT/APPELLEE:

Charles Duhon

Melanie Smith Daley 127 West Broad Street, Suite 801A Lake Charles, LA 70601 (337) 721-8183 COUNSEL FOR DEFENDANT/APPELLEE:

George Jones

Robert W. Higgason 4747 Research Forest Drive Suite 180, No. 289 The Woodlands, TX 77381 (281) 363-3200 COUNSEL FOR DEFENDANT/APPELLANT:

Bill Tran

Sera H. Russell, III Post Office Box 53866 Lafayette, LA 70505-3866 (337) 237-7171 COUNSEL FOR DEFENDANT/APPELLANT Bill Tran

AMY, Judge.

The plaintiff home builder alleged that the defendant failed to make the two final payments on the contract entered into for construction of the defendant’s home. The defendant filed a reconventional demand relating to what he contends were deviations from the construction contract and/or plans for the home. The trial court granted the plaintiff’s motion for summary judgment, awarding the sum due on the contract. The trial court also dismissed the defendant’s reconventional demand, finding the defendant’s notice of the alleged deficiencies inadequate under the New Home Warranty Act. The defendant appeals. For the following reasons, we reverse and remand for further proceedings.

Factual and Procedural Background Melton Frank d/b/a Frank Building and Remodeling and Bill Tran entered into a home construction contract on May 27, 2003, wherein Mr. Frank agreed to construct Mr. Tran’s home in Jennings, Louisiana. The contract established the bid price as $136,000, payable in five draws after completion of designated portions of the contract. The parties completed an addendum the following month.

While work on the home proceeded and the first three payments on the contract were made, the record reveals that Mr. Tran began making complaints regarding the construction. Ultimately, he failed to make the final two payments. In July 2004, Mr. Frank filed the petition instituting this matter, alleging that only minor detail work remained uncompleted on the house and that Mr. Tran had denied him access to the home to complete the work. He sought the $34,000 remaining under the contract.

Mr. Tran denied the petition’s allegation, asserting that Mr. Frank failed to “perform the work as specified in the contract and addendum” and that Mr. Frank’s refusal to “perform the work called for in the contract and its addendum was the

reason why he[] was not allowed back into the home.” Mr. Tran asserted that Mr. Frank failed to satisfactorily complete construction as designated by the contract’s payment schedule and, therefore, additional payments were not due under the contract. In a reconventional demand, Mr. Tran and his wife alleged that Mr. Frank failed to comply with the building plans in a number of respects, including a number of areas identified in the demand. Mr. Tran asserted that Mr. Frank refused to repair or rectify the problems and, therefore, he was contractually liable for damages associated with the “incomplete and incorrect construction” of the home. Mr. Tran and his wife sought damages and attorney’s fees pursuant to the New Home Warranty Act. In response, Mr. Frank alleged that the New Home Warranty Act provided Mr. Tran’s exclusive remedy and that he was precluded from recovery thereunder as he did not provide notice by registered or certified mail as required by La.R.S. 9:3145.

Mr. Frank filed a motion for summary judgment on his claim and that of Mr.

Tran. He supplemented the motion with the construction contract, the addendum of June 2003 and a deposition excerpt in which a bank official describes negotiations between the parties regarding an inspection of the complained of areas. Mr. Frank also submitted his own affidavit wherein he explained in part that he had “caused substantial performance of the obligations he owed[.]” He further stated that “[P]rior to February 1, 2007, Bill Tran had not caused to be delivered to Melton Frank written notice, by registered or certified mail advising him of all defects and giving him a reasonable opportunity to comply with the New Home Warranty Act.” Mr. Tran opposed the motion for summary judgment with various exhibits, including the depositions of Mr. Frank and the bank officer assigned to the project who explained that a list of Mr. Tran’s complaints were delivered via facsimile to Mr. Frank.

The trial court granted Mr. Frank’s motion for summary judgment, finding that, due to substantial completion of the project, he was entitled to the remaining payments on the contract. The trial court awarded the sums due on the construction contract together with judicial interest. The trial court also dismissed Mr. Tran’s reconventional demand, finding that the notice requirements of the New Home Warranty Act were not met.

Mr. Tran appeals, assigning the following as error:

1. The Trial Court improperly allowed the general contractor to contest the homeowner’s alleged non-compliance with La.R.S. 9:3145 through a Motion for Summary Judgment. The sole proper procedural mechanism for contesting non[-]compliance with La.R.S. 9:3145 is through an Exception of Prematurity.

2. The Trial Court failed to recognize that the homeowner complied with L[a]R.S. 9:3145 because the general contractor had actual knowledge of and undertook repair of the defects prior to the filing of Bill Tran’s reconventional demand.

3. The Trial Court improperly allowed the contractor to shield himself from liability for numerous defects for which the contractor had actual knowledge of and had actual time to remedy, merely because the defects were not itemized in written notice prior to the homeowner’s reconventional demand.

4. The Trial Court improperly granted the plaintiff general contractor’s Motion for Summary Judgment on his contractual obligation claim against the homeowner, while applying the certified mail notice requirement of the New Home Warranty Act to preclude the homeowner’s defenses against that contractual claim.

5. The Trial Court improperly granted the general contractor’s Motion for Summary Judgment against the homeowner’s reconventional demand where the contractor waived written notice by certified mail, by bringing a contractual obligation claim against the homeowner after having actual knowledge of the numerous problems with the incomplete home.

6. The Trial Court erred by granting the general contractor’s Motion for Summary Judgment because [the] contractor had the opportunity to “fix first” but did not do so.

Discussion

Reconventional Demand Mr. Tran contests the trial court’s determination that his claims were precluded by failure to give appropriate notice under the New Home Warranty Act. He chiefly asserts that the trial court erred in strictly applying the New Home Warranty Act’s notice requirements when Mr. Frank had actual notice of his various complaints.

Free access — add to your briefcase to read the full text and ask questions with AI

MELTON FRANK D/B/A FRANK BUILDING AND REMODELING VERSUS BILL TRAN, (La. Ct. App. 2008).

MELTON FRANK D/B/A FRANK BUILDING AND REMODELING VERSUS BILL TRAN (MELTON FRANK D/B/A FRANK BUILDING AND REMODELING VERSUS BILL TRAN) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Barrack v. JF Day & Co., Inc.
966 So. 2d 1064 (Louisiana Court of Appeal, 2007)
Thorn v. Caskey
745 So. 2d 653 (Louisiana Court of Appeal, 1999)
Supreme Services v. Sonny Greer, Inc.
958 So. 2d 634 (Supreme Court of Louisiana, 2007)
Carter v. Duhe
921 So. 2d 963 (Supreme Court of Louisiana, 2006)