Meloon Bronze Foundry, Inc. v. State

18 Misc. 2d 403, 191 N.Y.S.2d 3, 1959 N.Y. Misc. LEXIS 3091
CourtNew York Court of Claims
DecidedSeptember 2, 1959
DocketClaim No. 33351
StatusPublished
Cited by4 cases

This text of 18 Misc. 2d 403 (Meloon Bronze Foundry, Inc. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meloon Bronze Foundry, Inc. v. State, 18 Misc. 2d 403, 191 N.Y.S.2d 3, 1959 N.Y. Misc. LEXIS 3091 (N.Y. Super. Ct. 1959).

Opinion

Richard S. Heller, J.

This is a claim for an alleged appropriation of land in connection with a grade crossing elimination and for consequential damages allegedly resulting from the grade crossing elimination. The case was previously tried in this court and claimant was awarded the sum of $14,000 (8 Misc 2d 286). On appeal to the Appellate Division of the Supreme Court, Fourth Department, the judgment of the Court of Claims was reversed on the law and facts and a new trial granted. (6 A D 2d 993.) On this trial, pursuant to the judgment of the Appellate Division, the parties stipulated that the record of the first trial he made a part of the record of this trial.

Claimant was and still is the owner of the premises described in the claim and reference is made thereto for a detailed description. Prior to the improvement the claimant occupied the premises for foundry purposes with the southeasterly corner of the main foundry building located approximately 33 feet west of the westerly edge of the pavement of Lemoyne Avenue and the northeast corner of the main building located [405]*405approximately 55 feet west of the westerly edge of the pavement of Lemoyne Avenue.

The area between the pavement of Lemoyne Avenue and the foundry building was substantially at grade with the pavement and was open and unpaved.

About the middle of the easterly wall of the main foundry building was a loading dock the floor of which was above grade so that trucks and tractor-trailers could back against the dock and material could be unloaded and loaded from the foundry from within the building. There was sufficient room from this loading access of the foundry so that tractor-trailers with a trailer from 30 to 33 feet in length could back up to the building and park for loading and unloading purposes without interfering with traffic on Lemoyne Avenue.

The Lemoyne Avenue pavement was slightly upgrade to the south of the foundry and downgrade to the north. In the wintertime when the pavement was slippery, empty tractor-trailers customarily left the foundry by turning north on Lemoyne Avenue so as to avoid any problem involved in the slippery pavement and the upgrade to the south. All materials received by the foundry and shipped by the foundry were handled by truck and tractor-trailer and the usual volume of materials received was approximately 100,000 pounds per month and the usual volume of materials shipped was also about 100,000 pounds per month.

The grade crossing elimination was accomplished by depressing Lemoyne Avenue under the tracks of the New York Central Eailroad Company which constituted the northerly boundary of claimant’s plot.

At the time of this trial, immediately east of the southeast corner of the foundry building, there was a walk or retaining wall erected by the claimant approximately 2% feet in width, extending northerly along the east wall of the building for approximately 20 feet where the walk joined a loading dock constructed by the claimant which extended approximately 23 feet northeasterly perpendicular to the east wall of the foundry building. The dock was about 5 feet wide for its 23-foot length and then reduced to about an 18-foot width along the northerly 20 feet of the east wall of the foundry building. To the east of the walk at the southeast corner of the building was an open area of unpaved ground about 3% feet in width. Along the southerly face of the loading dock there was an open, unpaved area from the sidewalk of about 10 feet. East of this open area was blacktop pavement installed by the State about 20 feet in [406]*406width, and extending about 10 feet north of the south face of the loading dock and east thereof to a concrete gutter which ran northerly to the railroad right of way and a barricade south of the railroad tracks. On the east edge of the pavement there was a curb and east of the curb was a three-strand steel cable fence. From this fence there was a slope downward to a depth of 22 or 24 feet and at the base of this slope lies the newly constructed Lemoyne Avenue.

The pavement lying east of the foundry is the northerly end of a 20-foot wide street built by the State and described as the West Frontage Road. The new pavement constructed extended about 220 feet south of the railroad at which point the old pavement of Lemoyne Avenue, which was approximately 20 feet wide, was utilized as a part of the West Frontage Road. Some 1,200 feet south of claimant’s property, access was provided from the old Lemoyne Avenue pavement now known as the West Frontage Road to the new Lemoyne Avenue.

The claimant contends that a part of this new pavement was constructed on his land.

The first problem on this trial, as on the former trial, is to determine the width of the State’s right of way. The court finds that the State had a 66-foot right of way. No additional evidence was adduced on the retrial to affect the conclusion reached by the court on the first trial of this action that the State had a 66-foot right of way and the evidence and pertinent law is well set forth in the opinion following the first trial. (Meloon Bronze Foundry v. State of New York, 8 Misc 2d 286, supra.)

On the retrial, unlike the first trial, both parties presented engineers who had surveyed and located the center line of the 66-foot right of way as established by the certificate of the highway commissioners for Districts No. 2 and No. 3 of the Town of Salina on May 24, 1842 and in evidence as Exhibit "A”. The claimant’s witness who surveyed and located this center line concluded that a small triangle of pavement containing approximately 84 square feet was located on claimant’s land. This witness showed this triangle on Exhibit 38 with its base 3 t'o 3% feet in length along the southerly edge of the loading dock and with an easterly leg about 40 feet in length and a westerly leg about 38 feet in length.

The State also presented a survey locating the center line of the right of way and the right of way boundaries made by one of its employees. This survey tied in with the contract base line and the center line of Lemoyne Avenue pave[407]*407naent and with measurements made from claimant’s buildings during the trial. This survey shows no encroachments on claimant’s land.

The only substantial difference between the two surveys appears to be in the starting point. Both surveyors located a point described on the certificate of the highway commissioner dated May 24, 1842 as a point ‘ ‘ beginning on the southerly line of lot 27 of the original township of Manlius, now Salina, at a point north forty-two degrees west, fifty-two and one-half links from the northwesterly corner of Block #136 of the Village of Salina.” Claimant’s witness shows this measurement of 52% links as 31.5 feet, whereas, the State surveyor correctly shows this measurement 52% links as 34.65 feet. The court can only conclude that the starting point of claimant’s survey is about 3.15 feet east of the correct and actual starting point of the center line of the highway. It follows that this error must reflect in all courses run thereafter from the incorrect starting point.

The court finds that the claimant has failed to establish that there has been any appropriation of its property. The claimant is not entitled to any award for appropriation of its property and this leaves for determination the claim for compensation by reason of an alleged failure of the State to provide a suitable means of access to this abutting owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

La Briola v. State of NY
328 N.E.2d 781 (New York Court of Appeals, 1975)
Red Apple Rest, Inc. v. State
27 A.D.2d 417 (Appellate Division of the Supreme Court of New York, 1967)
Meloon Bronze Foundry, Inc. v. State
10 A.D.2d 905 (Appellate Division of the Supreme Court of New York, 1960)