Mellen v. Vondor-Horst Bros.

140 P. 130, 44 Utah 300, 1914 Utah LEXIS 30
CourtUtah Supreme Court
DecidedApril 2, 1914
DocketNo. 2576
StatusPublished
Cited by1 cases

This text of 140 P. 130 (Mellen v. Vondor-Horst Bros.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mellen v. Vondor-Horst Bros., 140 P. 130, 44 Utah 300, 1914 Utah LEXIS 30 (Utah 1914).

Opinion

FEIGN, J.

Joseph W. Mellen, the appellant, commenced this action against Vondor-Horst Bros., a corporation, hereafter called the contractor, and against the board of education of Salt Lake City, hereafter designated respondent, to recover the value of labor and material which it is conceded he performed and furnished the contractor for the construction of a certain school building for respondent, as hereinafter stated. Appellant also made the Fidelity & Deposit Company of Maryland, hereafter called surety company, a party to the action, but the court sustained the demurrer of the surety company to the complaint against it, and thus the surety company went out of the case. No service was obtained upon the contractor, which is a nonresident corporation of and absent from the State of Utah. It is not necessary to refer to the pleadings. The respondent and the surety company were represented by the same counsel in the court below. The facts are really quite simple and are not in dispute.

On or about November 2, 1908, the respondent entered into a written contract with the contractor whereby the latter agreed to erect and complete a certain school building in Salt Lake City for the agreed price of $Y1,000. One of the conditions of said contract was that said contractor should furnish a bond, as required by our statute, for the sum of $35,500, conditioned for the faithful performance of said contract, and the surety company executed and delivered the bond aforesaid. After the contract and the bond had been executed and delivered, the contractor in pursuance of said contract, employed the appellant to make the excavation for the basement of the school building and to furnish some sand and gravel, all of which was to be used, and which it is conceded was used, in the construction of said building, and which excavation and material is conceded by respondent to be of the value of $2148.45, and that all was used in [303]*303the construction of said school building. After the excavation had been made and the material furnished as aforesaid, and some trees had been removed from the building site, the contractor proceeded no farther with the contract. The respondent, on the 6th day of April, 1909, using the language of its counsel, “after repeated efforts to locate” the contractor, terminated its employment under the contract. Immediately after terminating, the employment of the contractor under said contract, respondent wrote the surety company as follows:

“The board of education of Salt Lake City, Utah, on the evening of the 6th day of April, 1909, at a regular session of said board passed a resolution terminating the employment of Vondor-Horst Brothers, a corporation, under that certain contract made and entered into by and between said Vondor-Horst Brothers, a corporation, with the said board on the 2d day of November, 1908, a copy of which resolution is herewith served upon you, together with a copy of the certificate of said architect made on said 6th day of April, 1909. The said board will therefore proceed in accordance with article five of said contract to complete the work included in said conti’act.”

The surety company on April 11, 1909, replied to said letter as follows:

“As surety upon the bond of said Vondor-Horst Bros, we hereby offer to undertake the construction and completion of the said Jefferson school in accordance with the terms and condition of the contract given by you to said Vondor-Horst Bros, and in accordance with the plans and' specifications referred to in said contract. We will place a reliable contractor upon the work and rush the same to completion. All payments specified in the Vondor-Horst contract shall he made to us (as) they become due and we will settle with the contractor A (Italics ours.)

On the 19th, two days thereafterp the respondent accepted the proposition of the surety company by adopting the following resolution:

[304]*304“Resolved: (1) That the said offer made by the Fidelity & Deposit Company of Maryland, the surety as aforesaid, be and the same is hereby accepted, and the said Fidelity & Deposit Company of Maryland is hereby given the right to enter upon the lands and premises upon which the building under said contract is to be constructed and take possession of all materials, tools, and appliances thereon; (2) that all sums of money payable under said contract, as the same become due and payable, as therein set forth, shall be made to the said Fidelity & Deposit Company of Maryland at Salt Lake City, Utah, and in accordance with the terms and conditions of said contract.”

The enjoyment of the contractor was terminated by respondent pursuant to certain provisions contained in the contract, which are as follows:

“Article 5. Should the contractors at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the architects, the owner shall be at liberty, after three days’ written notice to the contractors, to provide all such labor or materials and deduct the cost thereof from any money then due or thereafter to become due the contractors under this contract; and if the architects shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractors for the work and to enter upon the premises and take possession, for the purpose of completing the work included under this contract, of all materials, tools and appliances thereof, and to employ any other person or persons to finish the work and to provide the materials therefor ; and in case of such discontinuance of the employment of the contractors they shall not be entitled to receive any further payment under this contract until such work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed all [305]*305expenses incurred by tbe owner in finishing the work such excess shall be paid by the owner to the contractors, but if said expenses shall exceed said unpaid balance the contractors shall pay the difference to the owner. The expenses incurred by the owner, as herein provided, either for furnishing materials or for finishing the work, and any damage incurred through said default, shall be audited and certified by the architects, whose' certificates thereof shall be ■conclusive upon the parties.”

The surety company, pursuant to the resolution, and with the consent of the respondent, and in accordance with the terms and condition of the contract entered into between the contractor and the respondent,. erected and completed said school building according to the plans a-nd specifications, and in doing so used the excavation made by appellant, and also used' the material furnished by him, and received from respondent certain payments in accordance with the terms of the contract. It also did some extra work for which it was allowed extra pay. The surety company, in completing said school building, however, expended considerable more money than the contract price, for which it has received nothing. While the building was in process of construction, and after the surety company had appropriated appellant’s labor and material, he, pursuant to Comp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
140 P. 130, 44 Utah 300, 1914 Utah LEXIS 30, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mellen-v-vondor-horst-bros-utah-1914.