Melchior v. State

22 Ill. Ct. Cl. 160, 1953 Ill. Ct. Cl. LEXIS 1
CourtCourt of Claims of Illinois
DecidedDecember 18, 1953
DocketNo. 4523
StatusPublished

This text of 22 Ill. Ct. Cl. 160 (Melchior v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Melchior v. State, 22 Ill. Ct. Cl. 160, 1953 Ill. Ct. Cl. LEXIS 1 (Ill. Super. Ct. 1953).

Opinion

Wham, J.

In this case W. A. Melchior, claimant, contends that he is entitled to payment by respondent of the remaining sum due under a construction contract in the amount of $3,493.65, which respondent has failed and refused to pay. Claimant also contends that he is entitled to recover an additional sum of $1,062.20 for repairs made by Mm to equipment installed under the contract.

Respondent, having filed no answer to the complaint, is, under Rule 11 of the Court of Claims of the State of Illinois, presumed to have filed a general traverse, or demal of the facts set forth in the complaint, and, by virtue of such presumption, respondent deMes that claimant is entitled to the recovery prayed for.

The contract involved herein was entered into by claimant and respondent on August 17, 1949. The terms of the contract provide that claimant shall furnish all labor and materials to fully complete installation of the coal handling equipment for the power plant and associated utilities at the Lincoln State School and Colony, Lincoln, Illinois, in accordance with plans and specifications set forth at length in the contract, and detailed drawings furMshed by claimant and approved by respondent. The respondent agrees to pay claimant the sum of $19,891.00 for the installation of said system. The contract provides that respondent shall make payments on account to contractor on Ms obtaimng a certificate of payment from the Supervising ArcMtect upon fumisMng proof of the amounts due for services, labor, materials, etc., from time to time due, provided, however, that the amount of the payments previous to the substantial completion of the entire work shall not exceed 85% of the value of such material and labor as estimated by the Supervising ArcMtect, the final payment to be made witMn thirty days after completion in the manner, form and time required by the contract.

The contract specifically provides that:

“No payment whatever, or at any time, shall be demanded or due, except upon written certificate of the said Supervising Architect, to the effect that such payments have become due, and such certificates shall in each instance be a condition precedent to the right to require payment, and whose decision thereon shall be final.”

Article 8 of the General Conditions of the Contract provides that the Supervising Architect shall have general supervision and direction of the work. Article 9 provides that he shall make decisions on all claims of owner, or contractor, within a reasonable time.

Article 25 provides that the Supervising Architect shall issue the certificate of payment upon application by contractor when the payment falls. due ‘ or such amount as he (the Supervising Architect) decides to- be properly due”. Article 28 provides that the Supervising Architect may withhold any certificate of payment to protect owner from loss on account of defective work not remedied until such work is remedied.

Article 15 provides the contractor shall remedy any defects due to faulty workmanship, or faulty materials, upon written notice, and paragraph 1018 of the specifications provides that he shall correct at his expense any defects of manufacture, or installation, which developed within twelve months from the date of final acceptance by the Supervising Architect.

Article 14 provides that, if the Supervising Architect and owner deem it inexpedient to correct work not done in accordance with the contract, the difference in value, together with a fair allowance for damages, shall be deducted. Article 35 provides that, if the contractor shall neglect to prosecute the work properly, or fail to perform any provision of the contract, the owner may, after three days written notice to the contractor, without prejudicing any other remedy owner may have, make good the deficiencies, and deduct the cost from the payment due contractor, “provided, however, that the Supervising Architect shall approve both such action and the amount charged to contractor.”

Paragraph 2055 of the Specifications provides that the contractor shall “run- all equipment as in actual service, and demonstrate that it will perform all functions as specified”, this test to be run in the presence of a representative of the Supervising Architect. It further provides that the contractor shall instruct the operator regarding the operation and care of the equipment.

Article 36 provides that, if the contractor persistently disregards the instructions of the Supervising Architect, or otherwise is guilty of a substantial violation of any provision of the contract, the owner, upon the certificate of the Supervisng Architect that sufficient cause exists to justify such action, may without prejudice to any other right or remedy, and after giving the contractor seven days written notice, terminate the employment of the contractor, and take possession of the premises, and of all materials, tools and appliances thereon, and finish the work by whatever method he may deem expedient. In such case, the contractor shall not be entitled to receive any further payment until the work is finished. If the unpaid balance of the contract price exceeds the expense of finishing the work, such excess shall be paid to the contractor. If such expense shall exceed such unpaid balance, the contractor shall pay the difference to the owner. The expense incurred by the owner as herein provided, and the damage incurred through the contractor’s default, shall be certified by the Supervising Architect.

These provisions pertaining to action by the Supervising Architect are not uncommon in construction contracts. They appear in many contracts, both where a governmental body is a party, and where private parties are involved. In Williston on Contracts, Section 794, Vol. 3, page 2235, it is stated:

“Almost all contracts for building or engineering work of any importance provide that payment shall be made only when a certificate has been obtained from a supervising architect or engineer that the work has been performed as required by the specifications in the contract.”

And on page 2237:

“Not infrequently, however, the contract requires the certificate of the owner’s engineer or makes his decision final as to disputed matters connected with the proper performance of the contract, and such provisions are generally upheld.”

The purpose of these provisions is clear. In such projects, as is involved herein, the activities are of a technical and specialized nature. The knowledge of someone technically qualified to pass upon the performance of the contractor must be utilized, so as to arrive at, as near as possible, a compliance by both contractor and owner.

These provisions are far more than mere formalities to be complied with. When the parties to a contract agree to such, the power and discretion placed in the hands of the Supervising Architect is extensive, and the exercise thereof by the Supervising Architect is not to be easily overruled, or impeached. His decision is final in the absence of either fraud, gross mistake, unreasonable and arbitrary action, or a showing that he has knowingly and wilfully disregarded his duty, and rejected or condemned work, which he knew, or at least should have known, fully conformed in all respects to the terms of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martinsburg & Potomac Railroad v. March
114 U.S. 549 (Supreme Court, 1885)
United States v. Moorman
338 U.S. 457 (Supreme Court, 1950)
Feder v. Midland Casualty Co.
147 N.E. 468 (Illinois Supreme Court, 1925)
Palmer v. Sawyer
114 Mass. 1 (Massachusetts Supreme Judicial Court, 1873)
Moss v. Johnson
22 Ill. 633 (Illinois Supreme Court, 1859)
People ex rel. Chicago & Iowa Railroad v. Glann
70 Ill. 232 (Illinois Supreme Court, 1873)
Michaelis v. Wolf
26 N.E. 384 (Illinois Supreme Court, 1891)
Gilmore v. Courtney
41 N.E. 1023 (Illinois Supreme Court, 1895)
City of Peoria v. Fruin-Bambrick Construction Co.
169 Ill. 36 (Illinois Supreme Court, 1897)
Brownell Improvement Co. v. Critchfield
64 N.E. 332 (Illinois Supreme Court, 1902)
Wabash Railroad v. Billings
72 N.E. 2 (Illinois Supreme Court, 1904)
Hart v. Carsley Manufacturing Co.
77 N.E. 897 (Illinois Supreme Court, 1906)
Blome v. Wahl-Henius Institute of Fermentology
150 Ill. App. 164 (Appellate Court of Illinois, 1909)
Errant v. Columbia Western Mills
195 Ill. App. 14 (Appellate Court of Illinois, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
22 Ill. Ct. Cl. 160, 1953 Ill. Ct. Cl. LEXIS 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/melchior-v-state-ilclaimsct-1953.