Melbourne Bros. Construction Co. v. Department of Highways

9 Ct. Cl. 280
CourtWest Virginia Court of Claims
DecidedJune 26, 1973
DocketNo. D-534
StatusPublished

This text of 9 Ct. Cl. 280 (Melbourne Bros. Construction Co. v. Department of Highways) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Melbourne Bros. Construction Co. v. Department of Highways, 9 Ct. Cl. 280 (W. Va. Super. Ct. 1973).

Opinion

PETROPLUS, JUDGE:

This is an action to recover the sum of $55,817.82, an alleged underpayment arising from a contract, dated April 1, 1970, for a road construction project in Mason County, West Virginia, designated No. ER0485 (002), wherein Melbourne Brothers Construction Co., an Ohio corporation, hereinafter referred to as the Claimant or the Contractor, agreed with West Virginia Department of Highways, hereinafter referred to as the Respondent or the State, to construct according to plans and specifications furnished by the State, certain roads designated U. S. 35 and W. Va. Route 2, including fills for embankments and ramps, and grading and paving certain segments thereof. The contract was awarded on a bid proposal setting forth estimated quantities with unit prices for each bid item, and the aggregate estimated cost of the project was in the amount of $1,819,-679.41. The two bid items in controversy are:

Item 2
Unclassified excavation, estimated quantity of 33,570 cubic yards at $1.71 per cubic yard — $57,404.00
Item 3-1
Borrow excavation, estimated quantity of 305,125 cubic yards at $1.71 per cubic yard — $521,763.00

By way of explanation, unclassified excavation is earth movement in the project area, while borrow excavation is material brought into the area from excavations elsewhere. In both instances the material is used to complete the roadway and embankments. In this case both items happened to be the same price per cubic yard.

[281]*281In the defined work area extending approximately 1000 feet, U.S. Route 35 and W. Va. Route 2 intersected. An overpass and four ramps, identified on the Plans as Permanent Ramps A, B, C, and D, as well as two ramps designated “Temporary Ramp A” and “Temporary Ramp B”, provided approaches to the Silver Bridge crossing the Ohio River and the Shadle Bridge crossing the Kanawha River to Point Pleasant. The ramps designated Temporary “A” and “B” and the Permanent Ramps A and B were functioning prior to the contract as part of the traffic patterns for the existing Silver Bridge and Route 2.Only Permanent Ramps C and D were new construction and they required substantial fill material for proper elevation. Segments of Route 35 and Route 2 requiring fills and embankments were also new construction. All ramps provided connections with the two main highways and accommodated traffic in all directions.

The construction entailed grading, draining, paving, placing embankments, and the maintenance of traffic during the period of construction, all in accordance with the State Road Commission Standard Specifications for Roads and Bridges, adopted 1960, as amended by Special Provisions adopted in 1965. Among the contract documents are General Notes furnished to the Contractor, which set forth a so-called “Sequence of Operation”. The latter, by reason of its importance in deciding this case, is hereinafter set forth verbatim:

“SEQUENCE OF OPERATIONS
1. The contractor shall erect and maintain all necessary traffic control devices required to safeguard the public within the areas of work at all times.
2. Construct the embankment for U. S. 35, Ramp “C” omitting embankment between Stations 997+30 and 981+35, and Ramp “D” and extend the concrete box culvert on W. Va. 2 at Station 38+55.
3. Construct temporary fence on school property.
4. Construct the proposed drainage east of existing W. Va. 2.
5. Construct the proposed W. Va. 2 embankment for the northbound lanes while maintaining traffic on the southbound lanes of W. Va. 2.
6. Complete all the remaining work on U. S. 35 and W. Va. 2 including the pavement, guard rails and roadway items.
[282]*2827. Complete all work on Ramp “C” once school property has been vacated.
8. Remove the pavement and excavate the embankment from Temporary Ramp “A” and Temporary Ramp “B”. The contractor shall so schedule his work that the excavated material shall be incorporated in the roadway embankment of this contract. Cost of placing the material shall be included in the unit price bid for unclassified excavation. Place 3” penetration macadam shoulder on outside of Ramp “A” from Station 31+43 to Station 43 + 15 and on outside of Ramp “B” from Station 59+00 to Station 60+50 and from Station 63+80 to Station 65+30 as directed by the engineer.
9. The contractor shall be responsible for maintaining traffic as outlined above until completion and acceptance of the roadway pavement.
The contractor’s attention is directed to Section 1.4.6 of the Standard Specifications requiring the maintenance of local traffic.”

The 8th specification required the material resulting from removal of Temporary Ramp “A” and Temporary Ramp “B” to be utilized on the project as fill to form embankments for the new road segments.

By strictly adhering to the “Sequence of Operations” the Contractor found himself in a dilemma. After completing the new road with borrow material, it was impossible under Item 8 to incorporate the excavated material derived from the removal of Temporary Ramp “A” and Temporary Ramp “B” into the already completed roadway embankments required by the contract, and he was compelled to waste said material off the project site. For the fills and embankments of the new roadway, previously constructed with borrow material, the Contractor received payment at the unit bid price of $1.71 per cubic yard. The borrow excavation estimated in the bid proposal at 305,125 cubic yards actually overran into an additional 33,035 cubic yards. For this the Contractor was fully paid. The fill material from the removal of the Temporary Ramps could not be used and had to be wasted, as surplus material.

The Contractor now seeks payment for 32,642 cubic yards of the wasted material at $1.71 per cubic yard under the item of Unclassi[283]*283fied Excavation in the bid proposal, or a total of $55,817.82. All of the above facts were undisputed.

At the hearing, evidence was adduced by both parties on the issue of whether the plans and specifications which required the Contractor to use the excavated material and incorporate it in the work were in error, making it impossible for the Contractor to perform, thereby requiring the Contractor to waste the material, or whether the Contractor could have performed his work without wasting this material and still comply with the maintenance of traffic provisions of the contract.

The Claimant’s contention is that he was required to adhere strictly to the Sequence of Operations, completing each phase as outlined and then going on to the next phase. The Respondent contends that the plans and specifications are not in error, and that there is a certain flexibility in the sequence which permits the Contractor to work on different items at the same time, dovetailing his work, and still maintaining a traffic flow. By so doing the Contractor could have followed the specifications and used the material as fill in the project without waste.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
9 Ct. Cl. 280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/melbourne-bros-construction-co-v-department-of-highways-wvctcl-1973.