Melba James v. Anchor Boatlifts LLC and Jason Miller

Texas Court of Appeals, 9th District (Beaumont)·Decided May 7, 2026·No. 09-24-00272-CV·Published

Opinion

In The

Court of Appeals

Ninth District of Texas at Beaumont

NO. 09-24-00272-CV

MELBA JAMES, Appellant

V.

ANCHOR BOATLIFTS LLC AND JASON MILLER, Appellees

On Appeal from the 457th District Court Montgomery County, Texas

Trial Cause No. 21-08-11463-CV

MEMORANDUM OPINION

In a dispute involving the construction of a bulkhead on her lakefront property, Melba James1 (“James” or “Plaintiff” or “Appellant”) appeals the trial court’s Final Judgment granting Anchor Boatlifts LLC’s (“Anchor Boatlifts”) and Jason Miller’s (“Miller”) (collectively “Defendants” or “Cross-Appellants”) Motion for Traditional and No-Evidence Summary Judgment, and the Defendants filed a

1 According to the appellate record, Melba James was formerly known as Melba Johnston.

cross-appeal from the trial court’s Final Judgment denying Defendants their attorney’s fees. We affirm the trial court’s judgment.

Background

On August 19, 2021, James filed Plaintiff’s Original Petition (the “Petition”)

against Anchor Boatlifts and its registered agent Jason Miller. 2 According to the Petition, James hired the Defendants to replace her bulkhead at her property in Montgomery, Texas in 2017. James alleges that she hired the Defendants based on their representations to her that they were highly experienced with bulkhead construction and replacements and that the work done by the Defendants to repair the bulkhead would be a long-term repair. The Petition alleges that “[i]n less than three years, the bulkhead work Defendants competed failed and required immediate replacement.” According to the Petition, the Defendants failed to construct adequate bracing, drainage, or walls for the bulkhead, and because the bulkhead could not support the weight it was intended for, James incurred additional cost to tear down and replace the Defendants’ inadequately constructed bulkhead. James alleges that inspections determined that the Defendants used insufficient materials, engineering, and drainage for the project, and multiple pilings were on the verge of collapse. James asserts claims for breach of contract, violations of the Texas Deceptive Trade

2 The record reflects that at the time James filed her Petition, she no longer owned the property where the bulkhead was built. James sold the property and the bulkhead in November of 2020.

Practices Act (“DTPA”), breach of warranty, and common law fraud. James alleges that Anchor Boatlifts is liable for Miller’s acts and omissions under agency and respondeat superior theories. In her Petition, James seeks actual damages, exemplary damages, costs, attorney’s fees, pre- and post-judgment interest, and any other relief to which she may be entitled by law.

The Defendants filed an Answer, generally denying James’ claims. The Defendants also asserted the following affirmative defenses: James’ own actions and omissions caused or contributed to her damages; James’ claims are not actionable under the DTPA as the facts and circumstances pled amount to nothing more than an alleged breach of contract; Defendants’ statements as alleged were merely opinion or puffery and are not actionable under that DTPA; and James’ claims are barred in whole or in part by the applicable statutes of limitations. The Defendants also filed a cross-claim to recover “all reasonable attorney’s fees and costs necessary to defend against the groundless DTPA allegations” pursuant to section 17.50(c) of the Texas Business and Commerce Code.

Defendants filed a Traditional and No-Evidence Motion for Summary Judgment arguing, among other things,3 that it is undisputed that the Defendants

3 Because we conclude the claims are barred by the applicable statutes of limitations, we limit our discussion of the Defendants’ summary judgment motion and the responsive pleadings to the arguments made regarding the statutes of limitations. See Tex. R. App. P. 47.1.

completed the bulkhead work on James’ property (referred to by Defendants as the “Project”) more than four years before her lawsuit was filed. The Defendants allege in the summary judgment motion that claims for any tort actions for property damage and DTPA actions are subject to a two-year statute of limitations, and claims for breach of contract, breach of warranty, and fraud are subject to a four-year statute of limitations. The Defendants assert that James’ claims are barred because she failed to file her lawsuit before the applicable statutes of limitations lapsed:

[] All of Plaintiff’s causes of action began to accrue no later than the date when Defendant completed work on the Project on April 5, 2017, because the work and its quality was open and obvious. The contract, Ex. A, for the Project was for Defendant to remove the pre-existing structure and construct a new Bulkhead in exchange for payment. The Project was completed, and Plaintiff approved of the work and made the final payment on April 5, 2017. Ex. C; Ex. F. Further, each of the representations upon which Plaintiff makes her fraud and DTPA claims were made prior to April 5, 2017. The statute of limitations for her DTPA claim would have lapsed on April 5, 2019, and the statutes of limitations would have lapsed on April 5, 2021, for all her other claims.

Since Plaintiff failed to file her lawsuit before the applicable statutes of limitations lapsed, instead waiting until August 19, 2021, to file suit, all of Plaintiff’s claims are barred by the statu[t]es of limitations.

Accordingly, Defendants have shown conclusive proof that they are entitled to summary judgment on their limitations defense for all the claims asserted in Plaintiff’s Original Petition, and they should be dismissed from this suit.

The Defendants’ exhibits in support of their summary judgment motion, included Exhibit A (a copy of the Anchor Boatlifts estimate for work, signed by James as “accepted” on May 23, 2016), Exhibit C (a copy of the April 5, 2017 final payment

and receipt for the work done by Anchor Boatlifts), and Exhibit F (Affidavit of Miller).

James filed Plaintiff’s Response to Defendants’ Traditional and No-Evidence Motion for Summary Judgment and Objections to Defendants’ Summary Judgment Evidence (the “Response”). In the Response, James alleges that the defects in the Defendants’ repairs to the bulkhead “first arose and were first discovered when Plaintiff listed her home for sale in mid-2020[]” and she argued “Plaintiff lost the first contract to sell the Property due to the shoddy bulkhead [and] she had to give the buyers that purchased the Property a $45,000 concession to close the sale of the house.” James stated in the Response that the commencement of limitations accrues on the date a defendant’s wrongful act causes some legal injury, James did not suffer an injury until the bulkhead failed in 2020, Defendants have not submitted any evidence to suggest Plaintiff was injured prior to 2020, and James filed suit within the statute of limitations for all claims asserted in her Petition. In her affidavit attached to her Response, James states that in 2020 “it was apparent that there were multiple cracks in the bulkhead and several piling[]s/beams were bowing significantly[,]” and that “[i]n mid-2020 . . . [a] potential buyer alerted [James] to the extensive damage to the bulkhead[]” and she “notified Mr. Miller of the damage by text in mid-2020.”

Free access — add to your briefcase to read the full text and ask questions with AI

Melba James v. Anchor Boatlifts LLC and Jason Miller, (Tex. Ct. App. 2026).

Melba James v. Anchor Boatlifts LLC and Jason Miller (Melba James v. Anchor Boatlifts LLC and Jason Miller) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
MacK Trucks, Inc. v. Tamez
206 S.W.3d 572 (Texas Supreme Court, 2006)
Via Net v. TIG Insurance Co.
211 S.W.3d 310 (Texas Supreme Court, 2006)
Unifund CCR Partners v. Villa
299 S.W.3d 92 (Texas Supreme Court, 2009)
Exxon Corp. v. Emerald Oil & Gas Co., LC
348 S.W.3d 194 (Texas Supreme Court, 2011)
Thomas v. Omar Investments, Inc.
129 S.W.3d 290 (Court of Appeals of Texas, 2004)
Dairyland County Mutual Insurance Co. of Texas v. Childress
650 S.W.2d 770 (Texas Supreme Court, 1983)
Seureau v. ExxonMobil Corp.
274 S.W.3d 206 (Court of Appeals of Texas, 2008)
Sanders v. Construction Equity, Inc.
42 S.W.3d 364 (Court of Appeals of Texas, 2001)
Woods v. William M. Mercer, Inc.
769 S.W.2d 515 (Texas Supreme Court, 1988)
Velsicol Chemical Corp. v. Winograd
956 S.W.2d 529 (Texas Supreme Court, 1997)
Stewart Title Guaranty Co. v. Sterling
822 S.W.2d 1 (Texas Supreme Court, 1992)
Pitman v. Lightfoot
937 S.W.2d 496 (Court of Appeals of Texas, 1996)
Wal-Mart Stores, Inc. v. Rodriguez
92 S.W.3d 502 (Texas Supreme Court, 2002)
Splettstosser v. Myer
779 S.W.2d 806 (Texas Supreme Court, 1989)
Montgomery v. Kennedy
669 S.W.2d 309 (Texas Supreme Court, 1984)
Fichtner v. Richardson
708 S.W.2d 479 (Court of Appeals of Texas, 1986)
Provident Life & Accident Insurance Co. v. Knott
128 S.W.3d 211 (Texas Supreme Court, 2003)
Alcan Aluminum Corp. v. BASF Corp.
133 F. Supp. 2d 482 (N.D. Texas, 2001)