Meijer v. International Minerals & Chemical Corp.

741 F. Supp. 1238, 1990 U.S. Dist. LEXIS 10220, 1990 WL 113195
CourtDistrict Court, M.D. Louisiana
DecidedJuly 16, 1990
DocketCiv. A. 89-111-B
StatusPublished
Cited by2 cases

This text of 741 F. Supp. 1238 (Meijer v. International Minerals & Chemical Corp.) is published on Counsel Stack Legal Research, covering District Court, M.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meijer v. International Minerals & Chemical Corp., 741 F. Supp. 1238, 1990 U.S. Dist. LEXIS 10220, 1990 WL 113195 (M.D. La. 1990).

Opinion

RULING ON CROSS MOTIONS FOR SUMMARY JUDGMENT

POLOZOLA, District Judge.

The parties in this case seek to have the Court interpret the provisions of certain agreements which were entered into by the parties. To better understand the issues involved in this case it is necessary to set forth a summary of the facts which led to the agreements and to this suit.

In late 1980 and early 1981, International Minerals & Chemical Corporation (International) and Ashland Oil, Inc. (Ashland) acquired predial servitudes 1 from numerous landowners through eight separate agreements. These agreements permitted a pipeline to be run from the Agrico Chemical Company (Agrico) plant near Donald-sonville, Louisiana to the Allemania Chemical Company (Allemania) plant near Plaquemine, Louisiana. At the time the servitudes were acquired, International and Ashland owned Allemania as a joint venture. Allemania, which is presently owned solely by Ashland, manufactures methanol. The pipeline is used to transport carbon dioxide, which is used in the manufacturing process, from the Agrico plant to the Alle-mania plant.

From the completion of the pipeline until July of 1984, approximately 350 tons of carbon dioxide per day were transported through the pipeline. In July of 1984, the plant was shut down because of economic reasons. Although the plant was shut down, the record reveals that in the spring of 1984 and 1985, roughly 200 tons of carbon dioxide were injected into the pipeline from the Agrico end and vented at the Allemania end for the purpose of testing the integrity of the pipeline. It is also undisputed that during the shutdown, except during integrity tests, nitrogen gas was circulated through the pipeline at slightly above atmospheric pressure to prevent corrosion of the pipeline. Representatives or contractors of the Allemania flew over the pipeline approximately once a month to inspect the pipeline. Furthermore, the cathodic protection devices were tested approximately once a year.

On February 18, 1988, Allemania began selling carbon dioxide that it received from Agrico via the pipeline to another plant. Shortly thereafter, the Allemania plant be *1240 gan manufacturing methanol again. Since February of 1988, with the exception of several temporary shutdowns caused by Agrico, carbon dioxide has been continually transported through the pipeline for use in Allemania’s manufacturing process and for resale to another plant.

The landowners claim that the pipeline was not used for its intended purpose from July of 1984, when Allemania shut down, until February 18, 1988 when Allemania received carbon dioxide from Agrico for resale. They further contend that the language of the agreements supports their position that the servitudes have been terminated. Seven of the eight agreements provide in part as follows:

If at any time said right of way and easement [servitude] is not used during a period of two years for the purpose hereinabove specified, or in the event it should at any time be used for any other purpose than herein granted, then in either of such events all rights vested in GRANTEE hereunder shall, at the option of GRANTORS, and on the giving of written notice to GRANTEE, cease and terminate, [emphasis added]

The eighth agreement, which was executed on behalf of Cora-Texas Manufacturing Company, Inc. (the “Cora-Texas Agreement”) states:

Upon completion of construction of the pipeline if at any time said right of way and easement [servitude] is not used during a continuous thirty (30) month period for the purpose herein specified, or in the event that it should at any time be used for any other purposes than herein granted, then in either of such events all rights vested in the GRANTEE hereunder shall at the option of GRANTOR and on the giving of written notice to GRANTEE, cease and terminate, [emphasis added]

Between September 21, 1988 to January 4, 1989, International, Ashland, and Allema-nia were notified in writing by the plaintiffs that their rights under the servitude agreements were terminated pursuant to the above quoted provisions. The landowners have now filed this declaratory judgment action seeking a determination that the pipeline servitudes have prescribed or terminated for non-use.

As noted earlier, the landowners contend that the pipeline was not “used” during the four and a half years that Allemania was shut down. They argue that Allemania’s intent in obtaining the servitudes was to use the pipeline for the transportation of carbon dioxide to be used in the manufacturing process. The landowners contend that the defendants’ use of the pipeline which consisted of the constant flow of nitrogen, the two integrity tests using carbon dioxide, the monthly aerial inspections, and the annual testing of the cathodic protection devices were not sufficient to the constitute “use” within the meaning of the agreements and Louisiana law. According to the plaintiffs, these activities were intended to test, maintain, and inspect the pipeline which are mere accessory rights to the servitude and do not amount to use of the servitude. 2

In response to the plaintiffs’ contentions, Ashland argues that the continual flow of nitrogen, the integrity tests, the aerial inspections, and the cathodic device tests were sufficient “use” of the pipeline under the servitude agreements and Louisiana law. Ashland contends that under the agreements, which were drafted by the landowners with some input from Ashland and International, “use” was not limited to the transportation of carbon dioxide for manufacturing purposes. Ashland asserts that the servitude agreements unambiguously provide that a legitimate purpose of the pipeline servitudes is the preservation and maintenance of the pipeline for future use. Therefore, Ashland contends these activities are not accessory rights under the agreements. Furthermore, Ashland contends that the constant flow of nitrogen gas through the pipeline during the period of shutdown is sufficient “use” even if the *1241 agreements are interpreted to allow termination by the landowner if materials are not transported through the pipeline during a two year period under seven of the agreements or during a 30 month period in the Cora-Texas Agreement.

Thus, the Court must determine whether the pipeline servitude was used “for the purpose hereinabove specified” in the agreements during the period Allemania was shut down. The parties have submitted a Joint Statement of Uncontested Issues of Material Fact, in connection with the cross motions for summary judgment each has filed.

The pipeline “right of way and easement” described in the agreements is a predial servitude under Louisiana law. 3 “The use and extent of such servitudes are regulated by the title by which they are created.” 4 Therefore, it is necessary for the Court to examine the servitude agreements executed by the parties to determine whether there was “use” of the servitude 5 under the facts of this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LaFargue v. United States
4 F. Supp. 2d 593 (E.D. Louisiana, 1998)
Meijer v. Int'l Minerals & Chemical
929 F.2d 697 (Fifth Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
741 F. Supp. 1238, 1990 U.S. Dist. LEXIS 10220, 1990 WL 113195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meijer-v-international-minerals-chemical-corp-lamd-1990.