Meighan v. Watts Const. Co.

475 So. 2d 829, 1985 Ala. LEXIS 3956
CourtSupreme Court of Alabama
DecidedJuly 3, 1985
Docket83-911
StatusPublished
Cited by7 cases

This text of 475 So. 2d 829 (Meighan v. Watts Const. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meighan v. Watts Const. Co., 475 So. 2d 829, 1985 Ala. LEXIS 3956 (Ala. 1985).

Opinion

Louise T. Meighan appeals from a summary judgment entered in favor of Watts Construction Company and James E. Watts1 constituting a holding that her suit against Watts was barred by the six-year statute of limitations. We reverse.

The motion for summary judgment was submitted on the pleadings; written interrogatories, and answers thereto; the depositions of Mrs. Meighan, F.H. Ashley, and James Watts; and documents produced in discovery proceedings. All of these disclose that Mrs. Meighan, of 613 Reynolds Street, Gadsden, executed, on 15 June 1973, under seal, a deed of easement. This occurred because the City of Gadsden was to put in a new storm sewer pipeline near her property and residence. By this deed, Mrs. Meighan conveyed to the City a permanent easement upon a portion of her property for the construction and maintenance of a permanent storm sewer drainage pipeline, and also a temporary construction easement upon another portion of her property to afford ingress and egress to the permanently installed pipeline, and for piling dirt, stone, gravel, and other such substances while excavations were being made. This instrument, executed by Mrs. Meighan under seal, also provided:

"It is further expressly understood by and between the said parties that the City of Gadsden shall be responsible for restoring said premises . . . as near as practicable to their original condition immediately following each such use of the land."

The bid opening for this construction project, Reynolds Street-Haralson Avenue Storm Sewer Project, was scheduled by the City for 19 June 1973. Watts Construction Company was awarded the contract. The contract consisted of several documents: an instrument labeled "Contract," dated 5 July 1973; a performance bond executed by Watts under seal; a labor and material payment bond, executed by Watts under seal; a bid form dated 21 June 1973; various change orders, and the voluminous "Specifications Contract Documents." These documents imposed upon Watts certain obligations regarding repair of damage to, and protection of, adjoining property. Watts, in the course of this project, undertook to restore to the original condition homeowners' premises that had been damaged or altered. There were no other contractors, or any city construction workers, that undertook to do this restoration or replacement work.

In that connection, Watts took up and replaced the driveway on Mrs. Meighan's property. At times, Watts had a number of employees and various heavy equipment on Mrs. Meighan's premises.

In the fall of 1981, Mrs. Meighan first noticed a drainage problem at her home. She saw a small crack that began in the brick wall under her living room window which kept expanding as time passed. She hired F.H. Ashley, a building contractor, who examined it and gave her an estimate of damages in April 1982. Mr. Ashley testified there were cracks in the wall the size of two hands, and a window was so skewed there was paper, rock, and other matter present around the window larger than one's fist.

Ashley commenced work to attempt the repair of the damage and further, to find the cause of the problem. He determined that a drain pipe which ran across the front and down the side of her house had been crushed or mashed. The site of the crushed or collapsed drain pipe was under the driveway which had been replaced by Watts during the 1973 construction work. This crushed pipe, after the driveway was replaced, gradually filled with dirt and became blocked. The water that had formerly drained through this pipe backed up, causing the damage to the wall and the foundation. In Ashley's expert opinion the pipe had been crushed with a heavy piece of machinery while the driveway was being *Page 831 replaced. Cost of the repairs done by Ashley was $23,731.07.

Mrs. Meighan states the issues to be:

"Whether there is a scintilla of evidence establishing contractual obligations of Watts to Mrs. Meighan arising from the `deed of easement' instrument.

"Whether there is a scintilla of evidence establishing contractual obligations of Watts to Mrs. Meighan arising from the Watts-City construction contract instruments."

Crucial to a determination of these issues is resolution of the question of whether the instruments are deemed to be under seal so that applicable statute of limitations is ten years.

Watts contends they are not and says the six-year statute of limitations is applicable. Watts, in answer to the complaint, specifically denied that it was delegated, and assumed the duties, responsibilities, and obligations of the City to Mrs. Meighan. Watts further contends there was no assignment of the sewer project contract to Watts by the City, and further, that the contract was separate and apart from the deed of easement, the performance bond, and the labor and material payment bond. This contention rests primarily upon Article 4 of the "Contract," which states:

"ARTICLE 4. Contract Documents. The Contract shall consist of the following component parts:

a. This Instrument

b. General Conditions

c. Special Conditions

d. General Scope of Work

e. Technical Specifications

f. Drawings"

Reference to the "Performance Bond" shows:

"Whereas, Contractor has by written agreement . . . entered into a contract with Owner for Storm Sewer Project, Reynolds Street-Haralson Avenue . . . which contract is by reference made a part hereof, and is hereinafter referred to as the CONTRACT."

Reference to the "Labor Material Payment Bond" shows:

"Whereas, Principal [Watts Construction] has by written agreement . . . entered into a contract with Owner [The City of Gadsden] for Storm Sewer Project, Reynolds Street-Haralson Avenue . . . which contract is by reference made a part hereof, and is hereafter referred to as the CONTRACT."

Regarding the contention that Watts was not delegated, and did not assume the duties, responsibilities, and obligations of the City, we find the record quite revealing. The specifications and contract documents contain, among others, the following provisions:

"105.23 CARE OF THE WORK

"a. The contractor shall be responsible for all damages to persons or property that occur as a result of his fault or negligence in connection with the prosecution of the work and shall be responsible for the proper care and protection of all materials delivered and work performed until completion and final acceptance, whether or not the same has been covered by partial payments made by the City of Gadsden, and whether or not the damage to his work was caused by the Contractor or by other contractors, or by others than the employees of the City of Gadsden in the course of their employment.

". . .

"d. The Contractor shall avoid damage as a result of his operations to existing sidewalks, streets, curbs, pavements, utilities, adjoining property, the work of other contractors and the property of the City of Gadsden and others, and he shall at his own expense completely repair any damage thereto caused by his operations.

"e. Wherever required by law, the Contractor shall shore up, brace, underpin, secure, and protect as may be necessary all foundations and other parts of existing structures adjacent to, adjoining, and in the vicinity of the site, which may be in any way affected by the excavations or other operations connected with the *Page 832 construction of the Project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bekken v. Greystone Residential Ass'n
227 So. 3d 1201 (Court of Civil Appeals of Alabama, 2017)
Industrial Development Board v. Russell
124 So. 3d 127 (Supreme Court of Alabama, 2013)
Wheeler v. George
39 So. 3d 1061 (Supreme Court of Alabama, 2009)
DeVenney v. Hill
918 So. 2d 106 (Supreme Court of Alabama, 2005)
Winkleblack v. Murphy
811 So. 2d 521 (Supreme Court of Alabama, 2001)
City of Birmingham v. Cochrane Roofing & Metal Co.
547 So. 2d 1159 (Supreme Court of Alabama, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
475 So. 2d 829, 1985 Ala. LEXIS 3956, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meighan-v-watts-const-co-ala-1985.