Meier Masonry v. KRT Constr.

CourtNebraska Court of Appeals
DecidedFebruary 9, 2016
DocketA-14-1061
StatusUnpublished

This text of Meier Masonry v. KRT Constr. (Meier Masonry v. KRT Constr.) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meier Masonry v. KRT Constr., (Neb. Ct. App. 2016).

Opinion

IN THE NEBRASKA COURT OF APPEALS

MEMORANDUM OPINION AND JUDGMENT ON APPEAL (Memorandum Web Opinion)

MEIER MASONRY V. KRT CONSTR.

NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. § 2-102(E).

MEIER MASONRY, INC., APPELLANT, V.

KRT CONSTRUCTION, INC., APPELLEE.

Filed February 9, 2016. No. A-14-1061.

Appeal from the District Court for Douglas County: DUANE C. DOUGHERTY, Judge. Affirmed. W. Randall Paragas, of Paragas Law Offices, for appellant. Damien J. Wright, of Welch Law Firm, P.C., for appellee.

MOORE, Chief Judge, and INBODY and BISHOP, Judges. MOORE, Chief Judge. INTRODUCTION Meier Masonry, Inc. (Meier) appeals from a jury verdict in the district court for Douglas County granted in favor of Meier for an amount of $14,245 on the basis of its unjust enrichment claim against KRT Construction, Inc. (KRT). On appeal, Meier contends that the district court erred in overruling Meier’s motion to sequester and allowing KRT’s expert witnesses to be present during the testimony of Meier’s owner, Eugene Meier (Eugene); excluding from evidence a letter written on behalf of KRT to Meier on the basis of the letter being a settlement negotiation; and admitting two exhibits depicting KRT’s expert witness’ allegedly irrelevant construction bids. Meier concludes by asserting that the jury verdict should be vacated on the basis that any verdict for less than the full amount of $54,966.15 requested by Meier should be set aside as against the weight of the evidence. Because we find no error by the district court, we affirm.

-1- FACTUAL BACKGROUND This matter arises from an informal agreement between Eugene, owner of Meier, and Kent Therkelsen (Kent), owner of KRT, that Meier would provide masonry construction services to KRT in the construction of KRT’s new office headquarters building. Eugene is the father-in-law of Kent. The dispute centers on the amount and value of the materials and labor that Meier supplied in the construction of KRT’s building, and the compensation owed to Meier as a result. In 2008, KRT decided to construct its new headquarters in Omaha, Nebraska. Around May 2008, Kent requested that Eugene’s company, Meier, provide masonry construction services for the building. Meier proceeded to complete the masonry work on the building, finishing around early October 2008. Both parties stipulated during trial that there was no contract or agreed upon price regarding these construction services. Further, Eugene admitted at trial that Meier did not provide a written estimate or bid to KRT prior to commencing its work, despite being asked by Kent for such a bid. Eugene claimed he was unable to provide a bid at that time because he had not yet been given a revised construction plan from KRT. In late September 2008, around completion of the masonry work, Meier submitted a one-line item invoice to Kent for $154,000. Kent alleges that this was the first indication from Meier regarding the amount it intended to claim for the masonry work. In response to the invoice, Kent called Eugene, stating that he needed more information than was provided in the one-line item invoice. In mid-October of 2008, Meier sent a letter to KRT, entitled “Estimate.” The date on the Estimate and Eugene’s testimony suggests that it was drafted starting on July 11, 2008. Eugene testified that while the document was entitled “Estimate,” it was meant to be the actual bill containing actual charges for the construction. The Estimate provides an itemized list of material and labor costs that went towards completion of the project. The Estimate stated a total cost of $154,966.15 for Meier’s services. Following his receipt of the Estimate, Kent instructed his employees to count the materials, specifically the “brick and block,” contained in the completed building. Kent proceeded to create a spreadsheet, comparing the quantities given to him by his employees with the Estimate. As a result, Kent claims to have found that the quantities set forth in the Estimate were considerably higher than the quantities counted by his employees. Kent also compared the materials listed in the Estimate with invoices provided by Watkins Concrete and Nebraska Brick, the companies that respectively supplied the concrete block and red brick used in the construction. Kent claims that the quantities listed in the Estimate also exceed the material quantities listed in these invoices. Kent testified at trial that he asked Meier for clarification regarding the Estimate’s numbers, but never received a clear response on how Meier was calculating his charges. On March 4, 2009, Kent sent a letter to Meier explaining the discrepancies in the amount of materials. As stipulated to during trial, KRT had already paid $100,000 to Meier during the course of the construction. In the letter, Kent offered to pay Meier an additional $32,611.38 “in full accord and satisfaction of any outstanding dispute governing this matter.” This number was based on KRT’s calculation of the total cost of the masonry work, $132,611.38, minus the $100,000 that was already paid.

-2- In response to KRT’s refusal to pay the full amount of $154,966.15 contained in the Estimate, Meier filed this action against KRT on July 28, 2009 to collect the unpaid amount under the theory of unjust enrichment. PROCEDURAL BACKGROUND Following KRT’s unsuccessful motion for summary judgment, a trial was held on October 20, 21, and 22, 2014 before the district court for Douglas County. Witnesses testifying for Meier included Eugene; William Morford, a mason and expert witness who testified regarding the fair and reasonable cost of the construction; and John LaRandeau, an assistant general manager at Watkins Concrete. LaRandeau was also called to testify by KRT. Witnesses testifying for KRT included Kent, John Woods, a former employee of KRT, Dean Simonson, and Albert Weis. Simonson and Weis are both masons and were called as rebuttal experts to testify regarding the fair and reasonable cost of Meier’s masonry work. Various exhibits were received into evidence. These exhibits included the Estimate, photos of the completed headquarters, building plans for the headquarters, copies of checks, invoices from Watkins Concrete and Nebraska Brick, construction bids presented by Simonson and Weis as experts, Meier’s response to interrogatories, and additional documentation from Watkins Concrete regarding its transaction with Meier. KRT successfully objected to the admission of the March 4, 2009 letter sent by Kent to Meier on the basis of the letter being an inadmissible settlement offer as established by Neb. Rev. Stat. § 27-408. During a break in Eugene’s testimony, Meier made a motion to sequester KRT’S expert witnesses, Simonson and Weis. KRT objected to the motion. KRT argued that the presence of Simonson and Weis during Eugene’s testimony was necessary as their purpose at trial was to testify as experts in rebuttal of Eugene’s testimony. Further, KRT asserted that their presence was necessary because Eugene allegedly had not yet fully explained his methodology in billing KRT, and it was anticipated that such an explanation might come during his trial testimony. In response, Meier argued that Eugene had in fact provided a sufficient explanation of his methodology during discovery. After a lengthy side bar, the court denied the motion to sequester. Eugene testified that the quantities of materials listed in the Estimate did not correspond to the actual amount of materials used in the construction. Rather, Eugene used a “build through” methodology in formulating the Estimate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Invol. Dissolution of Wiles Bros.
830 N.W.2d 474 (Nebraska Supreme Court, 2013)
Simon v. Drake
829 N.W.2d 686 (Nebraska Supreme Court, 2013)
Gourley Ex Rel. Gourley v. Nebraska Methodist Health System, Inc.
663 N.W.2d 43 (Nebraska Supreme Court, 2003)
State v. Jackson
435 N.W.2d 893 (Nebraska Supreme Court, 1989)
Poppe v. Siefker
735 N.W.2d 784 (Nebraska Supreme Court, 2007)
Baker v. Blue Ridge Insurance
337 N.W.2d 411 (Nebraska Supreme Court, 1983)
Dennis W. v. Mental Health Board
717 N.W.2d 488 (Nebraska Court of Appeals, 2006)
State Ex Rel. Nebraska State Bar Ass'n v. Miller
602 N.W.2d 486 (Nebraska Supreme Court, 1999)
Pogge v. American Family Mutual Insurance
688 N.W.2d 634 (Nebraska Court of Appeals, 2004)
Steinhausen v. HomeServices of Neb.
289 Neb. 927 (Nebraska Supreme Court, 2015)
State v. Cook
290 Neb. 381 (Nebraska Supreme Court, 2015)
Chicago, Burlington & Quincy Railroad v. Kellogg
74 N.W. 403 (Nebraska Supreme Court, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
Meier Masonry v. KRT Constr., Counsel Stack Legal Research, https://law.counselstack.com/opinion/meier-masonry-v-krt-constr-nebctapp-2016.