Mehaffy v. United States

499 F. App'x 18
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 10, 2012
Docket2012-5069
StatusUnpublished
Cited by2 cases

This text of 499 F. App'x 18 (Mehaffy v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mehaffy v. United States, 499 F. App'x 18 (Fed. Cir. 2012).

Opinion

RADER, Chief Judge.

In this case, Appellant Mike Mehaffy seeks compensation from the government, claiming a taking of his real property in violation of the Fifth Amendment to the United States Constitution. Mr. Mehaffy’s claim arises from a decision by the United States Army Corps of Engineers (the “Corps”) denying Mr. Mehaffy’s fill permit application under section 404 of the Clean Water Act, 33 U.S.C. § 1344. The United States Court of Federal Claims granted summary judgment for the government on the ground that Mr. Mehaffy had not met the requirements for a regulatory taking under Penn Central Transportation Co. v. City of New York, 438 U.S. 104, 98 S.Ct. 2646, 57 L.Ed.2d 631 (1978) (“Penn Central ”). This court affirms the decision of the trial court.

I.

The land subject to this litigation is a seventy-three acre parcel bordering the Arkansas River in North Little Rock, Arkansas. In 1970, the property was owned by Nomikano, Inc. (“Nomikano”), an Arkansas corporation holding assets for the benefit of the Mehaffy family and whose business was conducted by Mr. Mehaffy’s father, the Honorable Pat Mehaffy.

*20 On March 2, 1970, the United States purchased a flowage easement (“the easement”) from Nomikano that covered roughly forty-nine acres of the subject property. The easement was purchased as part of a congressionally authorized effort to construct locks and dams along the Arkansas River. It gave the government the right to, among other things, “permanently overflow, flood and submerge the land lying below elevation 249, [mean sea level], and to occasionally overflow, flood, and submerge the land lying above elevation 249, m.s.l., in connection with the operation and maintenance of Lock and Dam No. 7, Arkansas River project.” Mehaffy v. United States, 102 Fed. Cl. 755, 757 (2012).

However, the easement also contained a reservation of certain rights. According to the easement deed, Nomikano reserved for itself, its successors, and assigns,

all such rights and privileges as may be used and enjoyed without interfering with [the government’s purpose in obtaining the easement]. Included among those rights specifically reserved to the landowner, its successors and assigns, is the right to place All in the area of said tract and to place structures on said fill above elevation 252 feet, m.s.l. Notwithstanding, the above exception does not permit the placing of structures for human habitation thereon.

Id. This reservation of rights was included in the easement deed at the request of Mr. Mehaffy’s father.

After the government purchased the easement, Congress enacted the Clean Water Act of 1972, Pub.L. No. 95-217, 91 Stat. 15656 (as amended at 33 U.S.C. §§ 1251-1387 (2006)) (the “CWA”). Section 404 of the CWA, codified at 33 U.S.C. § 1344, “establishes a program for the regulation of fill activities involving waters of the United States. The basic premise of the program is that no discharge of dredged or fill material into waters of the United States is permitted if a practicable alternative exists that is less damaging to the environment.” Norman v. United States, 429 F.3d 1081, 1086 n. 1 (Fed.Cir.2005) (internal quotations omitted). On October 10, 1980, the Corps notified Nomi-kano and its officers (including Mr. Mehaffy), that the property and the easement were subject to the terms of the CWA. The letter specifically stated the easement, by itself, “is not sufficient to authorize work requiring authorization under [the CWA],” and thus a section 404 permit would be required should Nomikano desire to place fill material in any of the wetlands located on the property. Mehaffy, 102 Fed. Cl. at 758.

In 1987, Nomikano was dissolved, its assets liquidated, and the property sold to Mehaffy Construction Company Inc. (“MCC”). While Mr. Mehaffy was the main executive for MCC at that time, the sale was a “negotiated, arm’s-length transaction for $75,000” which was then the fair market value of the land. Id. In May 2000, the property was sold a second time. Mr. Mehaffy had relinquished managerial control of MCC by that time, and MCC sold the property to him for $10.00.

In 2004, the Mehaffys began to develop the property. The Corps identified wetland-delineated areas on the subject property, and MCC cleared and leveled approximately nine to ten acres of the uplands portion of the subject property. The Me-haffys then used this cleared land as a storage yard for their construction business.

In September 2006, Mr. Mehaffy filed an application for a section 404 permit to fill approximately forty-eight acres of wetlands on the subject property. The application stated the purpose of the permit was to exercise the right granted in the 1970 easement. After several months of *21 communication between the Corps and Mr. Mehaffy, a period of public comment, and input from several federal and state governmental agencies, the Corps denied Mr. Mehaffy’s permit application. The Corps emphasized that Mr. Mehaffy had failed to demonstrate that his proposed placement of 280,000 cubic yards of fill within a designated floodway and wetland “did not have any practicable alternatives which would have less adverse environmental impacts.” Id. at 761.

The Corps informed Mr. Mehaffy of his agency appeal options, and he subsequently appealed the permit denial through the Corps’ administrative appeals process. The Corps ultimately denied his appeal, and, as the trial court found, this denial represented the final Corps decision regarding Mr. Mehaffy’s section 404 permit application. Id.

Mr. Mehaffy then filed suit in the United States Court of Federal Claims. He claimed the Corps’ refusal to provide him with a permit to fill the property “in accordance with the reservation contained in the Easement Deed” constituted a compensa-ble partial regulatory taking of Mehaffy’s land. App. 32. Following a period of discovery and an unsuccessful motion to dismiss, the government moved for summary judgment based on the parties’ Joint Stipulation of Facts.

The trial court granted the government’s motion. It analyzed the facts using the Penn Central framework and concluded that Mr. Mehaffy could not show he had a reasonable investment-backed expectation to fill the property, nor that the government action was retroactive or targeted against him specifically. [JA 14] Mr. Me-haffy appealed, and this court has jurisdiction under 28 U.S.C. § 1295(a).

II.

This court reviews the Court of Federal Claims’ grant of summary judgment without deference. Schooner Harbor Ventures, Inc. v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Columbia Venture, LLC v. Richland County
776 S.E.2d 900 (Supreme Court of South Carolina, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
499 F. App'x 18, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mehaffy-v-united-states-cafc-2012.