Megwinoff & Lefranc & Co. v. Sunland Biscuit Co.

67 P.R. 504
CourtSupreme Court of Puerto Rico
DecidedJune 27, 1947
DocketNo. 9434
StatusPublished

This text of 67 P.R. 504 (Megwinoff & Lefranc & Co. v. Sunland Biscuit Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Megwinoff & Lefranc & Co. v. Sunland Biscuit Co., 67 P.R. 504 (prsupreme 1947).

Opinion

Me. «1 ustick Markbeo

delivered the opinion of the Court.

This is an action originally brought in the Municipal Court of San Juan, by Megwinoff & Lefranc So Co., against the Snnland Biscuit Co., Inc. The complaint alleged, in brief, that the plaintiff contracted with the defendant for the installation of a refrigerator in the latter’s factory in Hato Rey for the agreed price of $1,000, of which sum $500 would he paid at the beginning of the work and $500 at the termination thereof; that the plaintiff started the work and received from the defendant the sum of $500 and that at the termination thereof on May 5, 1944, the latter refused to pay it the sum of $499 (sic), the balance of the amount of the contract, notwithstanding the efforts made to collect it.

The Snnland Biscuit Co., Inc., in its answer alleged that although it is true that it had contracted with the plaintiff for the installation of said refrigerator in the low retarding room of its biscuit factory in Hato Rey, the contract was entered into for the installation of the refrigerator within a reasonable time; that upon the execution of the contract, it paid $500 to the plaintiff, and that the latter, negligently and notwithstanding the demands made by the defendant, did not •finish the installation of said equipment until May 1944, or 2 years, 2 months, and 28 days after the execution of said contract. By way of counterclaim, it alleged that when the plaintiff accepted the order it knew that said refrigerator was urgently needed and that its prompt installation formed part of the contract; that the plaintiff violated the contract [506]*506by delaying its performance as already mentioned, well knowing that with such delay it caused the defendant the following damages: (1) limitation of the production of biscuits by the defendant factory; and (2) decrease in the yield of sacks of flour due to deficiencies in the fermentation process, for which the contracted refrigerator was essential ; and that the damages suffered by the defendant exceed the sum of $5,000, but that in order to submit itself to the jurisdiction of the municipal court, it reduced its counterclaim. to the sum of $499.

The municipal court as well as the District Court of San Juan sustained the complaint and dismissed the counterclaim. From the judgment rendered by the latter court, an appeal has been taken to this Court by the defendant, and in the brief filed by it only two errors are assigned, the first of which is that the lower court erred in holding that the plaintiff-appellee acted diligently and in good faith in the performance of the contract; and the second, that said court erred in holding that the counterclaim of the defendant did not lie.

A careful examination of the pleadings, of the oral evidence introduced, and of the correspondence between the parties regarding the contract entered into by them, lead us to the conclusion that the contentions of the appellant are not correct. From all the foregoing it appears that on February 7, 1942, the litigants herein entered into a contract by virtue of which the plaintiff would install an air conditioning equipment in defendant’s factory in the ward of Hato Hey, Kio Piedras, for the agreed price of $1,000, to be paid in the following manner: $500 at the execution of the contract and $500 at the completion by the plaintiff of the installation of said equipment. The agreed price included the total installation of the freezing equipment, plus free service for the period of one year. The initial $500 was paid by the defendant, who in a letter dated February 7, 1942, addressed [507]*507to the plaintiff, stated “that in accordance with our conversation, you must have ordered by air mail to the United States all the materials and machinery necessary to proceed to the installation of the equipment within the shortest time possible(Italics ours.)

Three days later, the plaintiff answered that letter by stating that all the materials required for the installation had already been ordered by air mail to the United States, and that the defendant could he assured that the installation would be made as soon as possible. On June 4 following, the defendant insisted with the plaintiff that it make the greatest efforts to obtain the remaining materials in order to be able to make the installation, and on the next day the plaintiff answered that the only part needed to make the installation was the compressor, which “as you already know was lost in the sinking of the shipment en route New York. to San Juan.” (Italics ours.) The plaintiff also informed the defendant that the order for said compressor had been immediately duplicated, but that when the compressor was ready for shipment an embargo order detained it.

From the numerous letters which the record contains it is also evident that the efforts to obtain a priority for the shipment of said compressor were to be made by the defendant, and that the latter agreed. It likewise appears that the compressor did not reach Puerto Rico until the end of May, 1.943, and that due to the state of war then prevailing the installation of the air conditioning equipment could not be made until a new priority from the War Production Board were procured. Said priority was not obtained by the defendant until a short time before November 29, 1943. On said date it wrote to the plaintiff advising it ‘ ‘ on last Friday the undersigned telephoned your office to inform Mr. Meg-winoff that we had received from Washington the permit to install in our factory the equipment detailed in your letter of October 11th. . . . Since there is no obstacle now to com-[508]*508píete said contract, we would appreciate your proceeding to install said equipment.” On the same day, the plaintiff wrote to the defendant setting- forth that it hoped to he able to begin the installation, work during the forthcoming week, for which reason it would appreciate that the defendant should expedite the matter of extending the priority. On January 31, 1944, the defendant wrote again to the plaintiff reminding it that the priority had already been received, that almost two months had elapsed, and requested it to proceed with the work at the shortest time possible. The record fails to show whether the plaintiff answered said letter. However, on March 2, 1944, the defendant again wrote to the plaintiff requesting the performance of the contract and advising it that “if by next Wednesday, the 8th instant, you have not started the contracted work, we will turn the matter over to our counsel for proper action.’’

From the oral evidence it also appears that the work was completed on or about May 5, 1944, and that the installation of the equipment, according to the uncontradieted testimony of Iván Megwinoff, a witness for the plaintiff, lasted 2 or 3 months.

Although in the first paragraph of the answer it is set forth that “the contract was entered into to install said refrigerator within a reasonable time,’’ we will assume, as was assumed by the parties in their correspondence and by the lower court in. its opinion, that the understanding between the plaintiff and the defendant was that the refrigerating equipment would be delivered to the Sunland Biscuit Co. “within the shortest time possible.’’ It was so stated by the defendant in. its letter to the plaintiff qf February 7,. 1942, and it so appears from other letters betweén the parties. Now then, taking into consideration all the circumstances of this case, should we reach the conclusion that the freezing equipment was installed by Megwinoff &

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
67 P.R. 504, Counsel Stack Legal Research, https://law.counselstack.com/opinion/megwinoff-lefranc-co-v-sunland-biscuit-co-prsupreme-1947.