Megarry Brothers, Inc. v. United States

404 F.2d 479, 1968 U.S. App. LEXIS 4543
CourtCourt of Appeals for the Eighth Circuit
DecidedDecember 10, 1968
Docket19126
StatusPublished
Cited by1 cases

This text of 404 F.2d 479 (Megarry Brothers, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Megarry Brothers, Inc. v. United States, 404 F.2d 479, 1968 U.S. App. LEXIS 4543 (8th Cir. 1968).

Opinion

404 F.2d 479

MEGARRY BROTHERS, INC., a Corporation and St. Paul Fire and Marine Insurance Co., a Corporation, Appellants,
v.
UNITED STATES of America, for the Use of MIDWESTERN ELECTRIC CONSTRUCTION, INC., a North Dakota Corporation, Appellee.

No. 19126.

United States Court of Appeals Eighth Circuit.

December 10, 1968.

COPYRIGHT MATERIAL OMITTED Richard H. McGee, of McGee, Van Sickle, Hankla, Backes & Wheeler, Minot, N. D., for appellant.

Arthur W. Stokes, of Stokes, Vaaler, Gillig, Warcup & Woutat, Grand Forks, N. D., for appellants.

Before MATTHES, GIBSON and BRIGHT, Circuit Judges.

FLOYD R. GIBSON, Circuit Judge.

The defendants Megarry Brothers, Inc., and St. Paul Fire and Marine Insurance Co., surety of Megarry Brothers, appeal from a judgment of $29,400 entered in the United States District Court for the District of North Dakota on a jury verdict finding an oral contract existed between Megarry Brothers and the use plaintiff, Midwestern Electric Construction, Inc., for the installation of insulation covering sump drainlines at the United States missile site at Minot, North Dakota.1

Megarry Brothers was the prime contractor with the United States for the construction of Drainage Improvement I on 90 missile sites at Minot AFB, North Dakota. Megarry Brothers' bid was in the original amount of $746,439.61, plus an additional amount for fence replacement. As a part of the contract bid the existing sump drainlines were to be modified by wrapping them with electrical heat tape where the lines were exposed or were above the frost line. These lines were about 25 feet in length and originally consisted of three-inch diameter cast iron pipes and were so located to drain each of the concrete missile site enclosures; also included were certain pumping station facilities. Megarry Brothers subcontracted to Midwestern by written agreement the pumping station facilities and the "modification — existing sump drainline" with the notation that the latter item referred to "electrical items in their entirety," all for a stated consideration of $120,000. There is no dispute about the pumping station facilities, nor the installation of the electrical heat tape together with the electrical connections to make the heat tape operative. The heat tape is made up in one unit like copper tubing and is round and about one-fourth inch in diameter. This tape is wrapped around the drainpipe, using about three feet of tape for every foot of drainpipe. Blocks of insulation two inches in thickness are placed over the heating tape, which insulation has been precast to conform with the configuration of the pipe, and is fitted to the pipe in two halves wired together and then wrapped with scotchrap, except where it is exposed to the weather where galvanized sheeting is used for protection to the drainpipe line.

The dispute arises over the installation of the insulation and the covering for the insulation. Midwestern contends that it had an oral contract with Megarry Brothers to install the insulation and the scotchrap, and evidently the galvanized sheet metal where necessary, for $29,400, broken down into a per unit cost of $350 for each of the 84 missile sites that were modified under the contract. Megarry Brothers contends that the insulation and wrapping was an integral part of the "electrical items" included in the written subcontract.

Initially, Ronald Megarry as president of Megarry Brothers, when compiling its competitive bid on the project, asked John Schroeder, president of Midwestern, for a bid on the electrical portion of the project. Midwestern reviewed the plans and specifications and gave an oral bid of $100,000 to Megarry Brothers by telephone on June 25, 1965, the day of the bid letting in Omaha, Nebraska. Megarry Brothers was the successful bidder.

On July 2, 1965, a conference was held in St. Cloud, Minnesota, between Megarry, Schroeder and Robert Peterson, vice-president of Midwestern. After some preliminary discussion and negotiation, a letter of intent was entered into between Midwestern and Megarry Brothers. The purpose of the letter of intent was to sublet to Midwestern "the electrical items in their entirety and the pump package units for the pumping station facility" involved in the drainage improvement project, in order that bonding could be obtained prior to formulating an official subcontract agreement. The letter of intent provided "the lump sum payment for completely constructing and acceptance of the above referenced work including all labor, materials, bonds and taxes are hereby included in the lump sum figure of $120,000.00." Following execution of the letter of intent, Midwestern ordered electrical items for the job from July 6-July 13.

On July 7, 1965, a pre-construction conference was held in the office of the Corps of Engineers at the Minot AFB. Following the conference, Peterson suggested to Megarry a modification of the prime contract by use of a substitute method of insulation and covering. Instead of the 16-gauge galvanized steel jacket originally specified in the contract, Peterson proposed using scotchrap protective tape for application over the insulation. Megarry told Peterson to proceed, and Peterson prepared shop drawings covering the proposed modification; the shop drawings were transmitted to the Corps of Engineers on July 16, 1965, and were approved on July 20. The modification reduced Megarry Brothers' contract with the United States by $3,466.20; Megarry Brothers did not charge this amount against its contract with Midwestern.

On July 19, 1965, Midwestern signed a standard form subcontract which had been prepared by Megarry Brothers on July 9 and had been forwarded to Midwestern by letter on July 17, 1965. The subcontract let to Midwestern under specification sections 3 and 4 of the prime contract the "electrical items in their entirety" and the pump package units for the lump sum of $120,000.

On July 21, 1965, Midwestern ordered the insulation and tape as shown on the shop drawings, and on July 26 commenced work on the project. Midwestern did only electrical work as the insulation, which was shipped from California, did not arrive until sometime in August.

Midwestern used two crews consisting of three electricians each. Each crew worked eight to ten hours per day and completed one site per day. Work done on each site included installing heat tape and insulation, wrapping the pipe with protective tape, installing the probe, relays, circuit breakers and core drilling through an 18½ inch concrete wall into the support building. Also, a metal covering over the exposed end of the pipe was installed. Due to a lack of asbestos workers in the area, all of the insulation work was done by Midwestern's electricians.

On July 28, 1965, Midwestern assigned all accounts receivable from Megarry Brothers under the subcontract to Arthur W. Stokes. The assignment stated the amount of the account under the subcontract to be $120,000.

As the work on the project progressed during August and September, Megarry Brothers forwarded to Midwestern payments based on the Corps of Engineers' estimates for work completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
404 F.2d 479, 1968 U.S. App. LEXIS 4543, Counsel Stack Legal Research, https://law.counselstack.com/opinion/megarry-brothers-inc-v-united-states-ca8-1968.