Mega Builders, Inc., D/B/A Mega & Associates v. Bell Tech Enterprises, Inc. and Trimcos LLC

CourtCourt of Appeals of Texas
DecidedAugust 2, 2018
Docket14-17-00642-CV
StatusPublished

This text of Mega Builders, Inc., D/B/A Mega & Associates v. Bell Tech Enterprises, Inc. and Trimcos LLC (Mega Builders, Inc., D/B/A Mega & Associates v. Bell Tech Enterprises, Inc. and Trimcos LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mega Builders, Inc., D/B/A Mega & Associates v. Bell Tech Enterprises, Inc. and Trimcos LLC, (Tex. Ct. App. 2018).

Opinion

Affirmed and Memorandum Opinion filed August 2, 2018.

In The

Fourteenth Court of Appeals

NO. 14-17-00642-CV

MEGA BUILDERS, INC., D/B/A MEGA & ASSOCIATES, Appellant V. BELL TECH ENTERPRISES, INC. AND TRIMCOS LLC, Appellees

On Appeal from the 215th District Court Harris County, Texas Trial Court Cause No. 2014-47565

MEMORANDUM OPINION In this construction dispute, appellant Mega Builders, Inc., d/b/a Mega & Associates, appeals the trial court’s judgment in favor of appellees Bell Tech Enterprises, Inc. and Trimcos LLC. Bell Tech entered into a contract with Trimcos to construct an office building. By a separate contract, Trimcos engaged Mega to provide labor and materials for construction. After a payment dispute, Mega left the project and sued Trimcos and Bell Tech for, among other things, breach of contract. Trimcos counterclaimed, contending it overpaid Mega. A jury found that Mega breached the contract and that Trimcos did not breach the contract, and awarded Trimcos damages. Consistent with the verdict, the trial court signed a judgment awarding Trimcos damages against Mega.

On appeal, Mega argues that the trial court’s exclusion of two exhibits was error and led to the rendition of an improper judgment. Concluding that the trial court either did not abuse its discretion or that any error in excluding the evidence was harmless, we affirm.

Background

This dispute stems from construction of an office building in Houston. Bell Tech is the building owner. At trial, the parties introduced two contracts into evidence. The first contract was between Bell Tech and Trimcos. That contract was signed April 25, 2013. The second contract was between Trimcos and Mega and is dated May 1, 2013. The price of both contracts was the same: $3.7 million. Under both contracts, work was to begin in May 2013 and be substantially completed by mid-March 2014.

According to Mega, Trimcos received periodic payments from Bell Tech for Mega’s work but withheld portions of those payments from Mega. D.J. Mody, Mega’s owner, testified that he was “consistently starving for funds.” In January 2014, Mody learned that the bank had distributed more money to Trimcos than Trimcos had paid Mega. Mody felt “cheated,” and Mega demanded an accounting and supplemental payment from Trimcos.

Trimcos provided an accounting of amounts invoiced and paid as of February 2014 under the May 1, 2013 contract. The accounting is a three-page spreadsheet reflecting billing details, payment and adjustment details, retention amounts,

2 discounts, and a balance due. The balance owed to Mega as of February 2014 is stated to be $23,551.28.

Mega contends it agreed with Trimcos in March 2014 to a final settlement sum Trimcos was to pay to Mega. Under the alleged agreement, (1) Mega received an immediate payment of $23,551.28 (per the accounting), and (2) Trimcos would pay a previously withheld “retainage” of $75,622.98.1 The document stated:

Received $23,551.28 from TRIMCOS, LLC as full and final settlement subject to retention amount ($75,622.95) for Belltech Office Building. Project address 14602 Presidio Sqr., Houston. The document was signed by representatives of Mega and Trimcos and dated March 3, 2014. The document included a photocopy of a check issued by Trimcos to Mega in the amount of $23,551.28. The February 2014 accounting and the alleged March 3, 2014 settlement agreement are the important documents for purposes of this appeal. They are identified in our record as Mega Exhibits 9 and 10, respectively.

Mega left the project in March 2014. According to Raffy Bell, Bell Tech’s owner, the only completed work at that point was the building’s foundation. Trimcos completed construction of the building.

A few months after Mega left the project, it filed a mechanic’s and materialman’s lien against the building project, claiming it had not been paid

1 Retainage means “an amount representing part of a [construction or repair] contract payment that is not required to be paid to the claimant within the month following the month in which labor is performed, material is furnished, or specially fabricated material is delivered.” Tex. Prop. Code § 53.001(11). To benefit potential lien claimants, the Property Code requires an owner of a construction or repair project to retain 10% of either the contract price of the work or the value of the work if there is no contract price. See id. §§ 53.101(a), 53.102.

3 $107,973.30. Mega also claimed it held a constitutional lien as an original contractor on the Bell Tech project.

Mega then sued Bell Tech and Trimcos, asserting breach of the April 25, 2013, and May 1, 2013 contracts. Mega did not allege that Trimcos breached the purported March 2014 settlement agreement. Mega also asserted a fraud claim against Bell Tech and Trimcos in the alternative, and asserted a claim for unjust enrichment and quantum meruit against Bell Tech. Mega alleged that it substantially performed the work contemplated by the May 1, 2013 contract, but had not been paid all amounts due for its labor or materials. Mega sought $128,321.37 in liquidated damages, unliquidated damages for its non-contract claims, and foreclosure on the statutory and constitutional liens on Bell Tech’s building.

Trimcos filed a breach of contract counterclaim, asserting that Trimcos was entitled to a refund of money it allegedly overpaid Mega. Alternatively, Trimcos asserted a claim for money had and received. Bell Tech answered Mega’s petition but asserted no counterclaims.

Before trial, defendants Bell Tech and Trimcos filed a motion in limine, seeking to exclude mention of any agreements that did not form a basis of Mega’s claims. In particular, the defendants claimed Mega’s Exhibits 9 and 10 were irrelevant because Mega had not pled breach of any purported settlement agreement. Further, Mega argued that the exhibits were inadmissible under Texas Rule of Evidence 408.2 The trial court granted the motion in limine. The next day, the trial

2 Rule 408, governing “Compromise Offers and Negotiations,” provides: (a) Prohibited Uses. Evidence of the following is not admissible either to prove or disprove the validity or amount of a disputed claim: (1) furnishing, promising, or offering—or accepting, promising to accept, or offering to accept—a valuable consideration in compromising or attempting to compromise the claim; and

4 court ruled that it was excluding the exhibits on grounds that they constituted evidence of a settlement agreement.3 Mega presented the exhibits as an offer of proof, and the court accepted them.

After a three-day trial, the jury found:

(a) Mega entered into the May 1, 2013 contract with Trimcos to construct the office building; (b) Mega did not enter into the May 1, 2013 contract with Bell Tech to construct the office building; (c) Mega failed to comply with the May 1, 2013 contract; (d) Bell Tech and Trimcos did not fail to comply with the May 1, 2013 contract; (e) Mega’s failure to comply was not excused; (f) Mega was an original contractor on the project; (g) Trimcos did not underpay Mega; (h) Trimcos overpaid Mega $23,159.53; (i) neither Trimcos nor Bell Tech failed to promptly pay any money due to Mega; and (j) Mega did not perform any compensable work for Bell Tech for which Mega was not paid. Trimcos and Bell Tech moved to enter judgment on the jury verdict and Trimcos also moved for partial judgment notwithstanding the verdict (“JNOV”). The defendants asked the court to render judgment ordering that Mega take nothing on its claims, that Mega’s liens be dissolved, that Trimcos be awarded $23,159.53

(2) conduct or statements made during compromise negotiations about the claim. Tex. R. Evid. 408(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mancorp, Inc. v. CULPEPPEER
802 S.W.2d 226 (Texas Supreme Court, 1990)
Ford Motor Co. v. Leggat
904 S.W.2d 643 (Texas Supreme Court, 1995)
Bartosh v. Gulf Health Care Center-Galveston
178 S.W.3d 434 (Court of Appeals of Texas, 2005)
Tatum v. Progressive Polymers, Inc.
881 S.W.2d 835 (Court of Appeals of Texas, 1994)
Castillo v. American Garment Finishers Corp.
965 S.W.2d 646 (Court of Appeals of Texas, 1998)
Neely v. Commission for Lawyer Discipline
302 S.W.3d 331 (Court of Appeals of Texas, 2009)
Hooper v. Chittaluru
222 S.W.3d 103 (Court of Appeals of Texas, 2006)
Vinson Minerals, Ltd. v. XTO Energy, Inc.
335 S.W.3d 344 (Court of Appeals of Texas, 2010)
Brookshire Brothers, Ltd. v. Jerry Aldridge
438 S.W.3d 9 (Texas Supreme Court, 2014)
Vonda Barnhart v. Sylvia Morales and Luis Perez
459 S.W.3d 733 (Court of Appeals of Texas, 2015)
Garden Ridge, L.P. v. Clear Lake Center, L.P.
504 S.W.3d 428 (Court of Appeals of Texas, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Mega Builders, Inc., D/B/A Mega & Associates v. Bell Tech Enterprises, Inc. and Trimcos LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mega-builders-inc-dba-mega-associates-v-bell-tech-enterprises-inc-texapp-2018.