Meek Coal Co. v. George D. Whitcomb Co.

176 S.W. 354, 164 Ky. 833, 1915 Ky. LEXIS 462
Court of Appeals of Kentucky·Decided May 25, 1915·Published·Cited by 5 cases

Opinion

Opinion op the Court by

Judge Carroll

Affirming.

On April 27, 1907, the appellee, Whitcomb Company, submitted to the appellant coal company a proposition to furnish it a Norwalk Compound Air Compressor for the sum of $2,900, and certain other appliances to be used in connection with the compressor for $857.50, making the total cost of the machinery $3,757.50. The proposition also contained a stipulation that the Whitcomb Company, if the offer was accepted, would send an experienced man to take charge of setting the compressor and making connections thereto free of charge for a term not to exceed ten days; and another stipulation that the Whitcomb Company “will guarantee the material and workmanship in the above machinery to be first class in every respect and will replace free of charge f. o. b. ears, the factory, any and all parts that may fail from any defect in the material or workmanship within one year from day of sale.” The proposition [834] also contained several clauses relative to the execution of deferred notes and the time of their payment, and also provided that the proposition was not subject “to. any verbal changes or agreements, and any changes in the above contract to be binding must be made in writing and must receive the approval of an executive officer of the George D. Whitcomb Company before becoming a part of this contract.”

This proposition was accepted by the coal company, on May 2, 1907, and thereafter, on July 1, 1907, a contract was entered into between the parties. This contract was in the form of a lease of the machinery by the Whitcomb Company to the coal company, and contained a number of stipulations. Among them was one that the contract price of the machinery, which included some items of interest, was $3,925.10.

On July 9, 1908, the parties entered into another agreement setting out that the coal company had purchased from the Whitcomb Company additional machinery of the value of $864.61 and had- executed to the Whitcomb Company six notes of equal amounts for this sum, payable at specified times.

In July, 1909, the coal company brought this suit on the common law side of the docket against the Whit-comb Company, in which it averred, in substance, that it purchased the compressor for the purpose of using it in the operation of a coal mine owned by it. That the Whitcomb Company guaranteed that the compressor had capacity to operate fifteen machines, but that when it was put to use, it was discovered that it would not operate more than three. It further averred that upon making this discovery it at once notified the Whitcomb Company, and it agreed to remedy the defect, whatever it might be, in the compressor, so that it would do the amount of work guaranteed; or, in other words, operate fifteen machines, but failed, or at least did not do so. It further averred that it had expended $2,750 in installing this machinery, and it sought judgment against the Whitcomb Company for this sum, together with $1,761 that it had paid in monthly installments on the contract price, and for an additional sum of fifty-thousand dollars, damages that it had sustained by the failure of the compressor to do 'the amount of work it was guaranteed it would do. It also asked a cancellation of all unpaid notes executed by it.

[835] In an amended petition it averred that upon discovering the failure of the compressor to do the work guaranteed, it offered to return the machinery and renewed this offer a number of times, and the only reason it retained the machinery was because the Whitcomb Company refused to accept it and insisted that it should keep the machinery and permit the Whitcomb Company to remedy the defects and make it conform to its guarantee.

In another amended petition it set up specifically the damages it sustained on account of loss of profits on coal contracts incurred by reason of the failure of this machinery to do the work it was guaranteed to do.

In another amendment it averred that in purchasing the'compressor it relied on certain representations made by the Whitcomb Company and its agents as to the capacity of the compressor.

For answer to the petition as amended, the Whit-comb Company, after denying certain averments in the petition, affirmatively set up that the only contract it had with the coal company was a written contract, and the only guarantee that it made was contained in that contract, and that it had fulfilled all of the conditions and guarantees of the contract. It further set up the unpaid notes executed by the coal company in part payment of the compressor and machinery purchased by it and asked judgment on these various notes.

After the case had been prepared for trial by the taking of a number of depositions for both parties, it was submitted and a judgment. entered dismissing the petition of the coal company and giving to the Whitcomb Company a judgment for so much of its debt as remained unpaid.

The first complaint urged by counsel for appellant is the refusal of the trial court to submit certain issues to a jury. The record shows that on June 7, 1910, and after the answer and counterclaim had been filed, the following order was made: “This cause by agreement of the parties and their attorneys made in open court is transferred to equity and is ordered placed on the equity docket, but the right of the plaintiff to submit the question of the amount of damages, if any be allowed by the chancellor, to a jury is reserved. All other questions herein are to be tried by the chancellor upon evidence taken in the form of depositions.”

[836] In November, 1910, counsel for the coal company moved the court to transfer the action to the ordinary docket for trial before a jury. In support of this motion some affidavits were filed showing that there was a misunderstanding about the order transferring the case to equity and that in fact this order was not agreed to. On the other hand, counter-affidavits and exhibits were filed showing that it was agreed to, and the court, after considering the motion and affidavits for and against it, overruled the motion to transfer the case to the ordinary docket for trial by a jury. It further appears that on November 28, 1912, the court ordered the submission to the jury of the issue as to whether there was a breach of warranty in the sale of the machinery, and if so the damage the coal company had sustained by reason thereof, and that on March 3, 1913, counsel for the Whitcomb Company moved the court to set aside this order made in November and in support of and against this motion certain affidavits were filed.

The court upon considering this motion, sustained it, and then proceeded to hear and determine the case under the agreed order made in June, 1910.

Free access — add to your briefcase to read the full text and ask questions with AI

Meek Coal Co. v. George D. Whitcomb Co., 176 S.W. 354, 164 Ky. 833, 1915 Ky. LEXIS 462 (Ky. Ct. App. 1915).

176 S.W. 354 (Meek Coal Co. v. George D. Whitcomb Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

A. C. Morris Co., Incorporated v. Heaton
29 S.W.2d 617 (Court of Appeals of Kentucky (pre-1976), 1930)
Paducah Hosiery Mills v. Proctor & Schwartz
276 S.W. 803 (Court of Appeals of Kentucky (pre-1976), 1925)
Frick Co. v. Salyers
258 S.W. 310 (Court of Appeals of Kentucky, 1924)
International Harvester Co. of America v. Brown
206 S.W. 622 (Court of Appeals of Kentucky, 1918)
Oman-Bowling Green Stone Co. v. Sullivan Machinery Co.
176 S.W. 973 (Court of Appeals of Kentucky, 1915)