Medusa Corp. v. Commonwealth

415 A.2d 105, 51 Pa. Commw. 520, 1980 Pa. Commw. LEXIS 1449
CourtCommonwealth Court of Pennsylvania
DecidedMay 23, 1980
DocketAppeal, No. 2208 C.D. 1978
StatusPublished
Cited by5 cases

This text of 415 A.2d 105 (Medusa Corp. v. Commonwealth) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Medusa Corp. v. Commonwealth, 415 A.2d 105, 51 Pa. Commw. 520, 1980 Pa. Commw. LEXIS 1449 (Pa. Ct. App. 1980).

Opinion

Opinion by

Judge Craig,

Medusa Corporation has presented a petition for review of a final adjudication order of the Environmental Hearing Board (EHB), which, after holding hearings upon a civil penalties complaint of the Pennsylvania Department of Environmental Resources (DER) and also upon a DER order appealed by Medusa, imposed violation penalties and a mandate of compliance with the DER order, as more fully discussed below.

[522]*522Medusa owns and operates a cement manufacturing facility in York, Pennsylvania, consisting of four kilns with auxiliary equipment, producing portland cement by wet process.

In that process, limestone is ground in the presence of water to form a slurry which is introduced into the kilns and there subjected to heat, resulting in chemical and physical changes which form clinker, a rock-like material in the shape of small balls, which, upon emerging from each kiln, is cooled, mixed with other material and ground into the final form of cement.

Three of the kilns, the gray plant, date from 1955, 1956 and 1969; the fourth kiln, the white plant, began operation in 1963. Each kiln is presently equipped with electrostatic precipitators and an oil-fired burner for preheating the kiln before the introduction of the main heat source, consisting of coal.

Those oil-fired burners were installed in 1973, after DER, pursuant to a 1972 variance application of Medusa, granted Medusa a variance dated February 14, 1973, covering gray plant start-ups, gray plant coolers, white plant steam exhaust and certain fugitive emissions. The variance was requested, and was granted, to extend until December 18, 1973. Among other things, the variance order contained references to the installation of auxiliary heating systems, the activation of the electrostatic precipitators in start-up procedure and the requirement that all sources covered by the variance be brought into compliance on and after December 18, 1973. We will consider details of that variance order below.

On July 7, 1976, DER filed with the EHB the civil penalties complaint against Medusa. As amended on June 16, 1977 and again on October 27, 1977, that complaint sought penalties against Medusa under Section 9 of the Air Pollution Control Act, Act of January 8, 1960, P.L. (1959) 2119, as amended, 35 P.S. §4009, [523]*523with respect to five counts, the allegations of which can be summarized as follows:

Count I —hundreds of days of violations as to particulate matter from processes, 25 Pa. Code §123.13, and as to opacity standards, 25 Pa. Code §123.41, during start-ups of kilns:
Count II — twenty days of violations consisting of fugitive emissions contrary to 25 Pa. Code §123.1;
Count III — violation of the variance order with respect to the installation of auxiliary heating systems (subsequently not pressed by DER);
Count IV — violations of 25 Pa. Code §123.13, concerning particulate emissions from processes during normal operations (a charge subsequently dropped by DER); and
Count V —air pollution violations, of Section 8 of the Air Pollution Act, 35 P.S. §4008, and of 25 Pa. Code §121.7, contrary to standards in 25 Pa. Code §§131.2, 131.3.

In the above summary, the emphasis is that of the court. The noncompliance period alleged in the amended complaint extended from December 18, 1973 to October 1, 1977.

Medusa answered the complaint, and the parties exchanged petitions for discovery.

On August 17, 1977, DER issued the DER order which alleged violations as follows: (Numbers refer to the paragraphs of the order, and the emphasis is ours.)

4, 5, 6 —uncontrolled emissions “during start-ups and reactivations” of the kilns, with precipitators not activated;
7, 8 —air pollution contrary to ambient air standards as in 25 Pa. Code §§131.2, 131.3;
9, 10— emissions from gray plant kilns “during normal operations” with precipitators activated, [524]*524contrary to 25 Pa. Code §123.13 (charge subsequently dropped by DER);
11 —violation of variance order through failure to install auxiliary heating system (subsequently not pressed by DER);
12 —emissions constituting a public nuisance.

The DER order also commanded Medusa to Develop a comprehensive air pollution elimination plan to be submitted within three months, resubmitted within thirty days if not initially approved, and implemented within twenty-four months thereafter, or to cease operations within thirty days after a final disapproval of the plan.

Medusa appealed the DER order to the EHB, which agreed to consolidate the order and complaint for hearing. The DER agreed to postpone the mandates of its order until after the hearings, which began November 14, 1977 and ended December 7, 1977, resulting in a record which, as reproduced record alone, consists of approximately 1900 pages.

EHB issued its adjudication order August 23, 1978, which required Medusa to comply with the mandates of the DER order within ninety days and assessed civil penalties aggregating $215,500, broken down as follows:

Opacity violations, 25 Pa. Code §123.41, nineteen days at $500 per day $ 9,500.00
Fugitive emission violations, 25 Pa. Code §123.1, twenty days at $300 per day $ 6,000.00
Air pollution violations, 1000 days at $200 per day $200,000.00
$215,500.00

The EHB assessed no penalty for the alleged variance violation with respect to auxiliary heat or with respect [525]*525to 25 Pa. Code §123.13, particulate emissions from processes (by weight). As noted above, DER dropped the charges as to violations during normal operations (complaint Count IV and order paragraphs 9, 10) “in view of all of the data available, including some questions as to the validity of the wet catch being included in those results.” Upon so doing, DER counsel also announced that, aside from the fugitive emissions and air pollution charges, the opacity and variance charges related to start-up conditions.

As to the ninety-day compliance order, this court has granted a supersedeas.

With the variance violation charges (auxiliary heat)1 and particulate emission charges under 25 Pa. Code §123.13 exonerated by the board and not appealed by DER, our discussion can be suitably organized by first covering Medusa’s general claims and then dealing with the findings and conclusions as to opacity violations, fugitive emissions and air pollution charges, in that order.

General Issues

Medusa’s broadest issue is that it is a victim of discriminatory enforcement by DER, resulting in a denial of equal protection rights. Yick Wo v. Hopkins, 118 U.S. 356 (1886); Commonwealth v. Lewis, 443 Pa. 305, 279 A.2d 26 (1971), cert. denied, 404 U.S. 1003 (1971).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Auto Wash, Inc. v. Department of Environmental Protection
729 A.2d 175 (Commonwealth Court of Pennsylvania, 1999)
Pork Motel, Corp. v. Kansas Department of Health & Environment
673 P.2d 1126 (Supreme Court of Kansas, 1983)
Franklin Township v. Goetz
27 Pa. D. & C.3d 155 (Adams County Court of Common Pleas, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
415 A.2d 105, 51 Pa. Commw. 520, 1980 Pa. Commw. LEXIS 1449, Counsel Stack Legal Research, https://law.counselstack.com/opinion/medusa-corp-v-commonwealth-pacommwct-1980.