Medco Energi US, L.L.C. v. Sea Robin Pipeline Co.

729 F.3d 394, 177 Oil & Gas Rep. 748, 2013 U.S. App. LEXIS 13525, 2013 WL 3316635
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 2, 2013
Docket12-30791
StatusUnpublished
Cited by4 cases

This text of 729 F.3d 394 (Medco Energi US, L.L.C. v. Sea Robin Pipeline Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Medco Energi US, L.L.C. v. Sea Robin Pipeline Co., 729 F.3d 394, 177 Oil & Gas Rep. 748, 2013 U.S. App. LEXIS 13525, 2013 WL 3316635 (5th Cir. 2013).

Opinion

PER CURIAM:

Medco Energi US, a natural gas producer, brought Louisiana state law claims against Sea Robin Pipeline Company, a natural gas transporter. The claim was that Sea Robin materially misrepresented to Medco how long it would take to complete repairs to its gas pipeline that was damaged by Hurricane Ike. Medco appeals the district court’s grant of summary judgment in favor of Sea Robin. We AFFIRM.

FACTS

Sea Robin transports natural gas via pipeline for producers like Medco from the Outer Continental Shelf to onshore transportation facilities. As a transporter of natural gas, Sea Robin is subject to Federal Energy Regulatory Commission (“FERC”) jurisdiction and operates its pipeline under a tariff approved by FERC. The tariff provides terms and conditions applicable to the services Sea Robin provides to its various classes of customers. In 2008, Sea Robin offered interruptible service to its customers at l/30th the cost of firm service. The provisions of Sea Robin’s interruptible service tariff provided that its service “shall be provided on an interruptible basis,” and that

[t]o the extent that Sea Robin complies with the provisions of its General Terms and Conditions and its Rate Schedule ITS [Interruptible Transportation Service], it shall have no liability to any shipper receiving service under Rate Schedule ITS arising from or related to service thereunder except as provided in such General Terms and Conditions and Rate Schedule ITS.

The tariff also provided that “Sea Robin makes no representation, assurance or warranty that capacity will be available on Sea Robin’s Pipeline System at any time” and that “Sea Robin shall not be required to perform service unless all facilities necessary to render the requested service exist and are in good operating condition.” Medco was one of Sea Robin’s interrupti-ble service customers.

In September 2008, Hurricane Ike caused over $118 million in damage to Sea Robin’s facilities. While Sea Robin repaired its pipeline, Medco and all other producers in an area in the Gulf known as West Leg were unable to transport gas. Sea Robin initiated FERC proceedings to recover the costs associated with repairing its pipeline. Medco and other parties moved to intervene and protest in the proceedings, but Medco did not pursue its protest beyond filing the motion. Other shippers, though, claimed in the proceeding that “there [were] questions regarding whether Sea Robin did act expeditiously and efficiently to restore system operations.” FERC found Sea Robin resumed service as quickly as possible after the hurricane. It allowed Sea Robin to impose a surcharge that would allow recovery of its restoration costs over the course of 21.4 years.

*397 In May 2009, Medco filed suit in state court in Lafayette Parish, Louisiana, claiming negligence, negligent misrepresentation, detrimental reliance, fraud, and violations of Louisiana’s Unfair Trade Practices Act. Sea Robin removed the case to the United States District Court for the Western District of Louisiana, invoking diversity jurisdiction and arguing the claims arose out of operations on the Outer Continental Shelf. 43 U.S.C. § 1349(b)(1).

Medco’s claims were based primarily on its allegation that Sea Robin misrepresented when the pipeline would again be available for use. The claims were based on Sea Robin’s providing “critical notices” after the hurricane about the status of its line. These notices were posted on Sea Robin’s website and emailed to customers. Medco alleged Sea Robin announced in one notice that the pipeline would return to service in early March 2009.

Medco closely monitored the progress of Sea Robin’s repairs. Medco was contemplating purchasing another production block that also used Sea Robin’s pipeline. As Medco’s negotiations for the purchase progressed, it sought assurance from Sea Robin that its pipeline would be repaired on schedule. Medco’s president, L. Dale Wooddy, III, contacted Sean Meehan, who oversaw Sea Robin’s critical repair notices. Meehan allegedly assured Wooddy that there were no problems that would prevent the pipeline’s return to service in March 2009 other than possible weather delays or typical small problems that may slightly shift the completion date. Meehan allegedly also told Wooddy there would be no capacity limitations or pressure changes in the line that would affect production from the block Medco intended to purchase. Sea Robin denied that it represented the repairs would be completed by March.

Medco claims it purchased the additional block in reliance on Sea Robin’s representations. When delays in pipeline repairs went beyond the ostensibly promised dates, Medco constructed a gathering line to move production from the newly purchased block to market. Medco claims as damages the approximately $5 million spent to construct the gathering line. Medco also claims damages for the expenses incurred in restoring production from its existing blocks, its inability to get its production to market in a timely manner, and a reduction in the marketable value of its properties.

In March 2012, Sea Robin moved for summary judgment. It argued that Med-co’s claims were preempted by the Natural Gas Act (“NGA”), 15 U.S.C. §§ 717-717z, or, alternatively, by the filed rate doctrine. The district court granted summary judgment in favor of Sea Robin on both grounds. Medco appealed.

DISCUSSION

We do not address the validity the district court’s analysis of federal field preemption because we determine that the filed rate doctrine bars Medco’s claims. We review the district court’s grant of summary judgment de novo. O’Hara v. Gen. Motors Corp., 508 F.3d 753, 757 (5th Cir.2007).

FERC regulates transporters and sellers of natural gas in interstate commerce. 15 U.S.C. § 717. Transporters and sellers must file with FERC “schedules,” i.e., tariffs “showing all rates and charges for any transportation or sale subject to the jurisdiction of the Commission, and the classifications, practices, and regulations affecting such rates and charges, together with all contracts which in any manner affect or relate to such rates, charges, classifications, and services,” and charge only what FERC determines is “just and reason *398 able.” 15 U.S.C. § 717c(a), (c). Any change to rates or services in the tariff must be filed in advance with FERC. 15 U.S.C. § 717c(d).

The filed rate doctrine recognizes the broad authority granted to agencies and not to the courts to determine whether the rates, including the services, classifications, and practices included in the filing, are reasonable. 15 U.S.C. § 717c(c); Ark. La. Gas Co. v. Hall,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Hoboken v. Chevron Corp
45 F.4th 699 (Third Circuit, 2022)
In re: IntraMTA Switched Acces
961 F.3d 691 (Fifth Circuit, 2020)
Krukas v. Aarp
District of Columbia, 2019
Krukas v. AARP, Inc.
376 F. Supp. 3d 1 (D.C. Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
729 F.3d 394, 177 Oil & Gas Rep. 748, 2013 U.S. App. LEXIS 13525, 2013 WL 3316635, Counsel Stack Legal Research, https://law.counselstack.com/opinion/medco-energi-us-llc-v-sea-robin-pipeline-co-ca5-2013.